This document is an Amendment (0002) to a federal contract solicitation for flooring replacement, issued by the National Park Service (NPS), Pacific West Region, with the contract number 140P8525Q0084. The amendment includes answers to contractor questions, a site visit attendance roster, and floor plans for multiple residences. Key details include specifications for toilet reset and baseboard trim installation, confirmation that electricity and water will be available during construction, and clarification that NPS will handle water heater removal and reinstallation. The RFQ due date remains unchanged, and floor plans are available for three out of four locations. Six contractors attended the pre-bid site visit, representing companies such as 4th Pace Const., C'in Floor, Mtn Carpet, and PJ Commercial Flooring.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140P8525Q0084 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PPO
San Francisco CA 94104 Suite 500 333 Bush Street
DOI, NPS, PWR - SF/SEA MABO
PPO
San Francisco CA 94104 Suite 500 333 Bush Street
NPS, PWR - SF/SEA MABO
08/28/20250002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
08/11/2025
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Timothy Modjeski
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
140P8525Q0084 Amendment 0002
The purpose of this amendment is to answer contractor questions, add floor plans, and add the site visit attendance roster.
A. The RFQ due date remains unchanged.
B. See the site visit attendance roster below.
C. Questions and answers:
1Q. Are contractors re-using baseboard trim and toilets?
1A. Per the specifications:
SECTION 01 12 30
CONTRACT CONSIDERATIONS
PART 2 PRODUCTS
a. I. Removal and resetting of toilets shall be paid per each toilet reset and shall be full compensation for removal, new wax ring gasket, new mounting hardware, caulking, and full replacement of any toilet, clean up and disposal
b. AA. Furnish and install wood base and shoe molding (to match existing). Base and shoe molding shall be paid by the linear foot of base installed and shall be full compensation for furnishing the material, staining, installation, removal and disposal of excess material, and final cleaning.
2Q. What flooring types are to be used in each location?
2A. Please see SOW, upon award consult with NPS for specific flooring types for each location.
3Q. Are there floorplans available for all locations?
3A. Floor plans available for 3 out of 4 locations. See below.
4Q. Will electricity and water be turned on and available during construction?
4A. Yes, see section 1.04 Utilities and Facilities of the specification.
5Q. Will any other trades be present during construction? (i.e. electricians, painters) 5A. NPS will schedule work to ensure no conflicts.
6Q. Will contractors be responsible for the removal of water heaters from areas where flooring needs to be replaced?
6A. NPS will be responsible for the removal and reinstallation of water heaters before and after floor replacement.
File details come from the government source that posted it. Updated .