REQUEST_FOR_INFORMATION_0001_0002.pdf

PDF 259 KB Posted

Attached to
Weekend Custodial Services Contract - Cabrillo Nat Federal contract opportunity
Solicitation number
140P8523Q0057
Issued by
Department of the Interior National Park Service

About this file

This document contains responses to a request for information (RFI) regarding a new weekend custodial services contract for Cabrillo National Monument. The National Park Service seeks custodial services for visitor centers, lighthouse complexes, and administrative buildings totaling approximately 4,500 square feet. The contractor must provide transportation such as an electric cart legal for speeds up to 35 miles per hour. Employees will require background checks and identifiable uniforms but not badges. Parking and pathway areas of approximately 220,000 square feet also require trash pickup. There is no bond requirement. This RFI relates to the formal solicitation for weekend custodial services at Cabrillo National Monument with solicitation number 140P8523Q0057 to be awarded by the Department of the Interior National Park Service.

View the file

Other files for this federal contract opportunity

Other files attached to Weekend Custodial Services Contract - Cabrillo Nat, newest first.
File Type Posted
B08_Supplemental_Clauses_and_Evaluation_Criteria_Q0057_v_3_0002.pdf PDF
Sol_140P8523Q0057_Amd_0002.pdf PDF
Sol_140P8523Q0057_Amd_0001.pdf PDF
Attachment_5_-_Relevant_Experience_Questionnaire.doc DOC document
Attachment_1_-_Statement_of_Work.pdf PDF
Attachment_4_-_Subcontracting_Percentage_Worksheet.xlsx XLSX spreadsheet
Attachment_3_-_QASP.pdf PDF
Attachment_2_-_Wage_Determination.pdf PDF
Sol_140P8523Q0057.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR INFORMATION 0001 - 140P8523Q0057 – Cabrillo Weekend Custodial Service

1. Who is the current contractor?

N/A. This is a new requirement.

2. What is the current contract amount?

See above.

3. If you are unable to provide the current contract amount, what is the current budget your agency has for this project?

The NPS is unable to provide that information.

4. Is there a bond requirement?

No performance bonds required.

5. Will the contractor's employees be required to pass a background check?

Yes.

6. Will the contractor's employees be required to wear a badge?

Contractor’s employees will not be required to wear a badge, but will be required to wear identifiable uniform as stated in SOW.

7. Square Footage for each location?

Approx SF provided is only for areas that require: sweeping, mopping, or vacuuming. Square footages not provided in SOW are: Lighthouse complex approx. 1500SF, Admin approx. 300SF.

8. It seems to be an emphasis implying in the sow that a vehicle (for example a maintenance utility cart) for the service of the sites is required, is this correct?

Contractor will need to provide their own transportation...this could be and electric cart as long as street legal for speeds up to 35mph.

9. What is the parking and pathway acreage?

Parking and Pathway area is appox 220,000SF (note these areas do not require sweeping, the requirement is to go through these areas and pick up any visible trash).

10. VC Admin building sq footage missing.

VC admin building is approx. 300SF.

11. What is the square footage of the lighthouse area?

Lighthouse area SF is approx. 1500SF.