This document is a Questions and Answers (Q&A) Amendment 3 for Solicitation 140P8425R0002, relating to the Dunn Main House Rehabilitation and Accessory Dwelling Units Construction project at Point Reyes National Seashore. The amendment documents a second site visit on July 9, 2025, and provides detailed responses to 21 contractor questions covering technical aspects of the project, including water treatment system requirements, fire sprinkler specifications, electrical service upgrades, interior and exterior door details, and construction methodologies.

Key updates include extending the proposal due date to August 1, 2025 at 3:00 p.m. PDT, adding a new Technical Approach evaluation factor, and clarifying various construction specifications. The project involves rehabilitation of an existing main house and construction of accessory dwelling units, with specific requirements around water treatment (reverse osmosis), fire protection (NFPA 13R system), and maintaining existing architectural elements. The solicitation is managed by the Department of the Interior National Park Service Pacific West Region, with the contracting officer being Alanna Gardner.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR PROPOSAL NO. 140P8425R0002

DUNN MAIN HOUSE REHABILITATION & ACCESSORY DWELLING UNITS CONSTRUCTION

POINT REYES NATIONAL SEASHORE

SITE VISIT – JULY 9, 2025

QUESTIONS AND ANSWERS

SITE VISIT SUMMARY:

A second site visit occurred on Wednesday, July 9, 2025 from 1:30 p.m. to 3:30 p.m. Pacific Daylight Time. Par cipants met at 20401 Shoreline Hwy, Marshall, CA 94940. Upon arrival, all par cipants were asked to sign in, then par cipants were shown the site.

See: B08_A achment_8_2nd Site Visit Sign-In Sheet.pdf

B08_A achment_9_Q-A_Amendment_3_ Summary.pdf (this document)

ADDITIONAL PROJECT QUESTIONS RECEIVED TO DATE (7/18/2025):

53. Will we need to provide a HERS test or CalGreen inspec ons for this project?

A home energy ra ng system (HERS) test is not required. A CalGreen inspec on is not required.

54. Is there a pest report showing the magnitude of Wood Destroying insects?

A pest report has not been conducted for the project.

55. Will we need to off haul all landscape cleanup or is there an area where wood chips can be spread?

Wood chips may be spread on the property. Exact spreading loca ons within 400- of the residence to be coordinated with the Contrac ng Officer’s Representa ve (COR) in the field.

56. Is there a preferred New Water Treatment System? What contaminants is the system currently trea ng for? Is the home on Well Water or City Water? What is the current supply capacity?

The preferred water treatment system shall be based around reverse osmosis treatment. Prior to reverse osmosis treatment, disinfec on and filtra on would be expected. Other treatments to be included as needed to meet Safe Drinking Water Act, Federal Regula ons, California Code, and Marin County drinking water standards.

The previous system included chlorina on disinfec on, filtra on, and so ening to remove harmful microorganisms and pathogens as well as to remove magnesium and calcium from water to reduce water hardness. The previous water treatment system treated contaminants required to meet Marin County drinking water standards for well supplies.

Solicita on 140P8425R0002, A achment 9, Q-A & Amendment 3

The Dunn property water is supplied via a shallow well. The shallow well is located approximately 1,000-feet southeast of the Dunn Main House. The water from the shallow well is considered surface water. Water from the well is pumped into four (4) 3,200-gallon storage tanks located approximately 200-feet east of the main house.

The capacity of the system is currently unknown but assumed to be sufficient to provide up to

3,000 gallons per day to the Dunn property. Future water supply improvements will be made separate from this project to the source to ensure consistent supply of 4,500 gallons per day to the storage tanks.

57. In order to upgrade electrical to code, and to provide all requested addi ves, we will need to significantly increase the service size. What is the outcome of your conversa ons with PG&E regarding this?

For any service upgrade or new service meters, PG&E will require a project applica on from NPS containing project details, including proposed load sheets and line drawings. This informa on will be reviewed and approved by PG&E. Construc on of upgrades to the service and/or new service meter connec ons by PG&E will be coordinated by NPS and PG&E as needed based on informa on to be provided by the contractor. PG&E es mates 182 calendar days from the me of applica on to service energiza on.

58. Is there a list of specs for the project that outline specific:

a. Plumbing fixtures

b. Bathroom Accessories

c. Cabinet Knobs

d. Door Hardware

e. Ligh ng

If there is not a list, in the Division 00 it is requested to provide samples and op ons for all products. Since these decisions have not been made, is it acceptable to provide Allowances for items where choices are pending?

For plumbing fixture specifica ons, see outline specifica ons sec on 224200. For bathroom accessory specifica ons, see outline specifica ons sec on 101010. For cabinet knob specifica ons, see outline specifica ons sec on 064100. For door hardware specifica ons, see outline specifica ons sec on 087000. For ligh ng specifica ons, see outline specifica ons sec ons 265100 and 265600.

Specific products and models for these items have not been provided in the specifica ons. Per outline specifica ons sec on 019999 General Notes and Requirements, materials and products where not explicitly specified shall be quality-grade; builder-grade materials and products will be rejected. A minimum of three op ons shall be provided by the contractor for products mee ng the general guidelines provided in these specifica ons as applicable to these items. Note: No addi onal funds will be made available post-award based on the final product selec on, as this is a firm-fixed-price contract awarded on a lump-sum basis.

Note that cabinet knobs are not an cipated with the preferred flat front cabinets. A hidden or minimal profile edge pull, channel pull, or tab pull is an cipated.

59. Is it acceptable for the Fire Sprinkler supply lines to be installed on the exis ng vaulted ceilings?

Yes, it is acceptable for fire sprinkler supply lines to be installed on the exis ng vaulted ceilings. If exposed, products and materials must meet the requirements of the standard for exposed applica ons. Non-metallic piping or piping not mee ng the requirements for exposed applica ons shall be protected in accordance with NFPA, UL, and other applicable requirements.

60. The soffit is called out to be non-vented. Will closed cell spray foam insula on be required at all the vaulted ceilings?

Closed cell spray foam insula on is not required or an cipated to be used at vaulted ceilings.

Soffit is included to allow fire rated coverings to connect the siding to soffit to flashing/gu er to roof without leaving exposed wood eaves or rakes. Vented soffit would also be an acceptable alterna ve.

61. Besides the bathrooms at the garage, art studio, and garden room, are there any other loca ons with a dropped ceiling?

The project does not include any drop ceilings. Ceiling finishes are either gypsum board/drywall or tongue & groove wood. See Figure 1 distributed as A achment 7 with the solicita on

(Amendment 0001) for a figure depic ng ceiling finish types and extents.

62. Is the art studio and garden room built on a slab?

The garden room, Unit 2, is built on a slab. The art studio, Unit 3, is also build on a slab.

63. Are the exterior doors at the entrance, breezeway, upper and lower deck to remain?

The exterior doors at the entrance, breezeway, upper and lower deck are expected to remain.

64. Contract line item #2 calls for the interior doors to match the exis ng 6 panel doors. The door schedule calls for single-flush interior doors. Please clarify.

Interior doors should match exis ng 6 panel doors to the extent prac cable based on available products. The door schedule should be referenced for loca ons and dimensions of doors only.

The family and family types listed in the door schedule are placeholders and can be ignored. The specifica on language reflects the intended door style.

65. Please confirm there are no decks at the front eleva on as shown on A02/3.

Confirming there are no decks at the front eleva on. The decks seen on A02 and A03 are the rear decks, seen in these views due to the transparency se ngs for the ground in the drawing.

66. Please confirm all new siding is Hardie shake and not lap siding as shown on A02/3&4.

All new siding is proposed as Hardie Shingle Straight Edge Panel (cedar shake style) fiber cement shingle siding or approved equivalent. The apparent lap siding shown on A01 and A02 are general siding visualiza ons used to indicate siding loca ons only. Cedar shake style is not a salient characteris c of the requirement. Other materials and visual styles of siding that are Class

A fire rated would be considered (e.g. steel, composite, engineered wood, plank, lap).

67. Please confirm if a wet pipe system is acceptable throughout, including in uncondi oned areas, or if a dry system is required in those loca ons due to climate concerns.

A wet pipe system may be acceptable if uncondi oned areas can be protected from freezing in accordance with NFPA standards. NPS will accept wet pipe systems provided the C-16 Fire

Protec on Contractor or licensed fire protec on engineer documents compliance with NFPA and applicable standards.

68. Please clarify of (sic) Unit 3 fireplace is to remain, be demolished, or sealed. Align with Unit 2 scope if applicable.

The exis ng wood stove (fireplace) and stone surround in Unit 3 are to be demolished to accommodate the construc on of the kitchen and closet shown in drawing A02.

69. In Unit 3, South Bedroom, approximately 169 square feet of concrete slab will require demoli on and replacement to match the eleva on of the surrounding finished floor. Addi onally, a new foo ng and stem wall will need to be installed to support what appears to be a load-bearing exterior wall. Please confirm:

a. Will construc on drawings for the new foo ng and stem wall be provided by the NPS?

b. Or should the contractor design and submit drawings for approval by the NPS?

The intent for the Unit 3, South bedroom is to maintain the exis ng slabs and load bearing walls.

New stairs would be constructed to connect the south bedroom slab to the upper slab. NPS would prefer to avoid any altera ons to the eleva on of the South Bedroom floor that would require new foo ngs, founda ons, or roof profiles. New interior walls and stairs will not require new construc on drawings from NPS or the Contractor.

70. Do you have a planholders list/sign in sheet available?

See the solicita on amendment a achments found with the solicita on on sam.gov for a list of site visit a endees. You may also visit www.sam.gov and search for the opportunity using keyword 140P8425R0002; there you should be able to see/add yourself to the Interested

Vendors List. You may need to create an account and sign in to see this informa on.

71. Can the fire sprinkler system be designed per NFPA 13R instead of NFPA 13?

The system should be designed per NFPA 13R.

72. There is currently no supply for the fire sprinklers. Is there a design pressure for the fire sprinkler system that will conform to the performance of the future pump?

The current supply would be the elevated storage tanks located adjacent to the main house. A future fire pump would be expected to be designed in accordance with NFPA 20. Required flow rates would be expected to be supplied at 40 psi or greater. The pump must deliver water at the correct pressure to ensure the fire suppression system func ons properly, typically at 65% of the pressure at 150% of the rated flow.

73. Can we get the bid date extended a week since we are s ll wai ng on addi onal informa on for a number of the bid items?

Yes, in addi on to the previous extension provided by Amendment 0002, this Amendment 0003 extends the due date of proposals through 3:00 p.m. Pacific Daylight Time (PDT) on Friday, August 1, 2025.

SUMMARY OF AMENDMENT 0001 ITEMS:

The offeror shall make the following changes, amendments and addi ons to the per nent sheets, pages and paragraphs of the specifica ons and all associated Solicita on documents, and shall take the same into considera on in the proposed prices:

1. Updated provisions and clauses

a. Sec on I is updated as follows:

Remove reference to deviated version of 52.222-6 Construc on Wage Rate Requirements (AUG 2018) as the devia on has been rescinded.

Remove reference to deviated version of 52.222-11 Subcontracts (Labor Standards) (MAY 2014) as the devia on has been rescinded.

Remove reference to deviated version of 52.222-12 Contract Termina on— Debarment (MAY 2014) as the devia on has been rescinded.

Update 52.244-6 Subcontracts for Commercial Products and Commercial Services (JAN 2025) with (DEVIATION FEB 2025) version.

b. Sec on J is updated to include the following new a achments:

B08_A achment_2_Wage_Determina on_18Jul2025.pdf

B08_A achment_8_2nd Site Visit Sign-In Sheet.pdf

B08_A achment_9_Site Visit Notes_Q-A_Amendment_3_Summary.pdf

c. Sec on K is updated as follows:

Within 52.204-8, remove references to “(xiv) 52.222-22, Previous Contracts and Compliance Reports” and “(xv) 52.222-25, Affirma ve Ac on Compliance” under 52.204-8 – simply changes both (xiv) and (xv) to: [RESERVED].

d. Adds instruc ons for responding to a new Evalua on Factor (Technical Approach) as follows:

FACTOR 3 – TECHNICAL APPROACH

Technical approach is your means and methods to complete a technical aspect of required work in this solicita on. Submit a wri en narra ve limited to 10 pages describing your technical approach to the specific aspects below. Addi onal pages will not be evaluated. Pictures can be included and will count towards the page limita on. There is no preprinted form for this submi al.

Approach to Cri cal Contract Requirements: Describe your approach to successfully accomplish the work outlined in the specifica ons within proposed contract performance period and budget. Iden fy poten al related risks or reasons for project me or cost impacts and your solu ons to mi gate and resolve them. Include approach to minimize electrical load required by the final constructed project.

e. Add a new evalua on factor (Technical Approach) as follows:

FACTOR 3 – TECHNICAL APPROACH: Technical approaches that comply with applicable contract requirements; are realis c, appropriate, and efficient; and demonstrate clear logic and scope understanding present lower levels of risk and will be more favorably rated. Approaches not demonstra ng these a ributes present higher levels of risk and will be less favorably rated.

f. Changes Past Performance evalua on factor from Factor 3 to Factor 4 (as referenced in

Sec on L and Sec on M).

Updates to the Federal Acquisi on Regula on (FAR) are underway with changes to date incorporated into this Amendment as summarized above.

The full text of a solicita on provision or clause may be accessed electronically at this/these address(es):

h p://www.acquisi on.gov/far/ h ps://www.acquisi on.gov/diar h ps://www.acquisi on.gov/caac-le ers

Alterna vely, please reach out to the contrac ng officer at alanna_gardner@nps.gov for any ques ons or clarifica ons.

--END OF NOTES--