This document contains Questions and Answers related to Solicitation 140P8424Q0038 for the supply and delivery of concrete parking bumpers at Lassen Volcanic National Park in California. The key details are:

The delivery period has been increased to 90 days from award, with final delivery no later than October 31, 2024. Phased deliveries are acceptable if they contain a substantial number of bumpers. The National Park Service (NPS) can provide a forklift for offloading if given enough notice, but contractors are preferred to bring their own. The minimum number of bumpers per delivery is 50, although deliveries of approximately 225 bumpers are preferred.

The solicitation is a total small business set-aside with a NAICS code of 238990 and a $19.0 Million size standard. The government anticipates awarding a firm-fixed-price purchase order to the responsible quoter whose proposal is most advantageous, price and other factors considered.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers Solicitation 140P8424Q0038

Lassen Volcanic National Park, Manzanita Lake Parking Bumpers

1. How flexible is the delivery period? Would it be possible to make deliveries in phases?

The delivery period has been increased to completion of first delivery within 90 days from award. Phased deliveries will be accepted if the deliveries are scheduled out and contain a substantial number of bumpers. Final delivery must be completed no later than October 31st, 2024.

2. Many vendors worry that 30 days to make delivery will be impossible and suspect that 8-12 weeks will be more reasonable. Will this be a problem?

The delivery period has been increased to completion of first delivery within 90 days from award. Phased deliveries will be accepted if the deliveries are scheduled out and contain a substantial number of bumpers. Final delivery must be completed no later than October 31st, 2024.

3. Will NPS provide a forklift to offload deliveries?

NPS can provide a forklift if given enough notice by the contractor, but it is preferred that the forklift is brought by the contractor for offloading. For those that will bring a forklift, an extra option has been added to the quote sheet for the forklift, if so desired.

4. What is the minimum number of parking bumpers that should be included in each delivery?

The minimum number of bumpers we will allow per delivery is 50, although ideally, we are looking for deliveries of about 225.