CONTRACT
LINE ITEM
NUMBER
(CLIN)
CONTRACT LINE ITEM (CLI) TITLE QUANTITY
UNIT OF
MEASURE
TOTAL PRICE
Construct the Complete Entrance Station Kiosk
Building as show on the Construction Documents 1 LS $
Provide Site Demolition; provide Site Excavation, Grading and Erosion Control; and Construct Roads, Island, Unpaved Shoulders, Drainage Features and miscellaneous amenities as shown on the
Construction Documents for the Base Bid
1 LS $
Construct Site Electrical and Data Utilities as shown on the Construction Documents for the Base Bid 1 LS $
OPTION A, Construct the Complete Support Building as shown on the Construction Documents 1 LS $
OPTION B, Construct Paving and Site Amentities as shown on the Construction Documents for the Bid
Option
1 LS $
OPTION C, Construct Water and Wastewater Systems as shown on the Construction Documents for the Bid
Option
1 LS $
CONTRACT BID SCHEDULE
SOLICITATION NUMBER: 140P8419R0006
PARK ‐ PMIS: PINN ‐ 198668
DEVELOPED AREA: Approximately 0.76 acres
TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Numbers 4 through 6) ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
TOTAL PROPOSED PRICE ‐ BASE PLUS ALL OPTIONS (Contract Line Item Numbers 1 through 6) ‐‐‐‐‐‐‐‐‐‐‐
All measurement and payment information is included in the project specifications, Section 01 27 00.
Notice: Refer to the clause Evaluation of Options, found in Section M of the Solicitation. Offerors are required to submit, at a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all Option line items. Failure to do so may render the proposal unacceptable. On lump‐sum line items, provide the total price only. For all unit‐priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item.
In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts govern. Round totals and extended prices to whole dollars. The Government reserves the right to award any or no options at or after the time of award. At the option of the Government, the period for exercise of options at the proposed prices shall extend 180 calendar days from the date of award.
TOTAL BASE PRICE (Contract Line Item Number 1 through 3) ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
PROJECT TITLE: Replace the East Entrance Station, Pinnacles National Park, San Benito County, CA
PINN‐198668
CBS ‐ 1