B11_Questions___Answers_Site_Visit_Heart_B_Loop_CS_Abatement-Demo_0001.pdf

PDF 85 KB Posted

Attached to
OLYM - HEART O HILLS LOOP B ABATEMENT and DEMOLITI
Solicitation number
140P8325Q0016
Issued by

About this file

This document is a Questions & Answers (Q&A) record from a site visit for the Heart B-Loop CS Abatement and Demolition project at Olympic National Park, scheduled for Tuesday, 04/22/2025 at 10:30am PST. The document contains a single completed question and answer, where a contractor named Rick Rhoades asked if a window can be removed to set up negative pressure venting, to which the National Park Service (NPS) responded "Yes". The document provides space for two additional questions, but these remain blank. This Q&A appears to be part of the pre-solicitation phase for a federal contract opportunity involving asbestos abatement and interior demolition of a building at the park.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Heart B-Loop CS Abatement and Demolition, OLYM

Question & Answers, Site Visit Meeting Tuesday 04/22/2025, 10:30am PST

Question 1: Can a window be removed to set up neg pressure venting?

Contractor Name: Rick Rhoades

Answer 1:

NPS: Yes

Question 2:

Contractor Name________________________

Answer 2:

NPS:

Question 3:

Contractor Name________________________

Answer 3:

NPS: