Attachment_1_Statement_of_Work_REVISED_5-31-24_0001.pdf

PDF 5 MB Posted

Attached to
Repair Old Chief Joseph Wall, Nez Perce NHP
Solicitation number
140P8324Q0034
Issued by

About this file

This document is a Statement of Work for the repair of the Old Chief Joseph Cemetery Wall at the Nez Perce National Historical Park in Joseph, Oregon. The work includes stabilizing and repairing the damaged section of the historic stacked rock wall pillar that was struck by a vehicle in 2021. The repair work must be conducted in a manner consistent with the Secretary of the Interior's Standards for Historic Preservation. Key details include:

The contractor will provide all labor, equipment, and materials to repair and document the repair process. Work includes transporting the damaged wall pieces from storage, repairing the damaged pillar, and documenting the repair process through photography and a final report. The contractor must have experience working with historic properties and conducting repairs on historic structures. A pre-construction meeting and various submittal documents are required prior to beginning work. The work must be completed during daylight hours Monday through Friday, excluding holidays, and the contractor must take measures to minimize disruption to the public and park staff during construction. The contract includes a single line item for the lump sum repair and documentation work. The solicitation number is 140P8324Q0034 and proposals are being sought by the National Park Service Pacific West Region.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Repair Old Chief Joseph Wall RFQ 140P8324Q0034 Attachment 1 Statement of Work revised 5-31-2024 Nez Perce National Historical Park

NATIONAL PARK SERVICE

GENERAL REQUIREMENTS

Items have been added since original version. Please see added pages 13 - 25 that are now included in the Statement of Work

Nez Perce National Historical Park

Repair Old Chief Joseph Cemetery Wall

Statement of Work

Joseph, Oregon

May 2024

Repair Old Chief Joseph Cemetery Wall FY24

Repair Old Chief Joseph Wall Solicitation No. 140P8324Q0034 Attachment 1 Statement of Work, revised 5-31-2024 Nez Perce National Historical Park

PART 1 – SUMMARY OF WORK & DEFINITION OF CLINs

1.1 WORK COVERED BY CONTRACT DOCUMENTS

A. General: All work outlined below will be performed under a single contract.

B. Project Location: This project is located at the Old Chief Joseph Grave Site at the Old Chief Joseph Memorial and Gravesite in Joseph Oregon (no physical address) (Lat/Long 45°20'11.47"N 117°13'19.26"W)

1. Project Background: In 2021, the wall fronting the Old Chief Joseph Cemetery was damaged in a single-car automobile accident. This accident caused a moderate amount of damage to one of the standing pillars at the end of the cemetery wall. This damage included the separation and collapse of approximately a quarter of the pillar. This damaged piece of the cemetery wall is mostly in-tact with a small number of stones that separated from the pillar and the broken pillar piece.

The National Park Service (NPS) currently does not have the capacity to conduct the repair of this cemetery wall in 2024. Due to this, the National Park Service seeks to contract with a third party to repair and restore this section of the cemetery wall and document the repair. The section of wall and pillar to be repaired is approximately 7’ x 3’ x 3.5’ and must be repaired in a manner that is consistent with the Secretary of the Interior’s Standards for Historic Preservation.

C. Project Scope of Work / Definition of Contract Line Items: The Work consists of the following:

1. Contract Line Item 010: This item shall consist of the stabilization and repair of the broken column/wall and the documentation of the repair process and the completed repair

Contractor will provide lump sum pricing for contract line items.

D. Contractor Tasks: The Contractor is to provide all labor, equipment, and materials to repair and document the repair of the cemetery wall/column.

Work shall include but is not limited to:

1. Demonstrating understanding and experience working with historic properties and conducting repairs on historic structures.

2. Conduct a preliminary trip to Old Chief Joseph Cemetery with NPS staff present to inspect the wall to determine the extent of damage to the mortar and stones that are/were part of the cemetery wall.

3. Document the noticeable damage to the wall that has occurred due to weathering that has occurred since the wall was damaged via automobile in 2019. This documentation shall consist of photographic documentation that clearly shows the damage, the size of the damage, the cause of the damage, and the location of the damage. The documentation shall also consist of a narrative description of the damage being documented.

4. Transport the damaged wall pieces, mortar, and elements from storage at Nez Perce National Historical Park’s maintenance shed from Lapwai, ID to Joseph, OR for inclusion in the repair of the cemetery wall.

5. Repair the damage to the cemetery wall in such a manner that the repair is made meeting the Secretary of Interior’s Standards on historic preservation.

6. The repair shall utilize the recovered, damaged pieces of the wall.

7. The repair shall utilize the damaged pieces in such a manner that incorporates them into their original locations and orientations when determinable and possible.

8. The mortar utilized for repairs shall match the surrounding mortar on the undamaged portion of the cemetery wall pillar.

9. All repairs shall be documented via photography and written narrative in such a manner that meets Secretary of Interior Standards for documenting historic structures and repairs to said structures.

10. Provide a final report that collates the noted damage assessment that notes damage from 2019-2024, the repair process, and the completed repair. The final report shall be delivered via a paper report and via a digital submission in .pdf file format.

1.2 REFERENCE DOCUMENTS / REPORTS

A. General: The following reference documents / reports are attached or available upon request to supplement the information in the specifications:

1. NPS Forms (RFI, CM-16, and QC Daily Report)

2. Site Location Map with Project Area Limits, Preferred Access, Approved Staging and

Storage Area, and Sensitive Avoidance Areas

3. Secretary of Interior Guidelines for Restoration

4. Secretary of Interior Standards for the Treatment of Historic Properties

5. National Register Form and Description for Old Chief Joseph’s Gravesite

6. Acid Digestion Analysis of Existing Wall/Column Mortar

7. Project Proposal for Repair of Wall/Column from 2021/2022

1.4 PUBLIC / STAFF USE OF THE SITE

A. General: The project site will be open to the public during construction. The Contractor shall at all times conduct operations to ensure the least inconvenience to the public and staff. Temporary closures may be permitted upon specific written approval of the Contracting Officer.

B. Other Contracts, Work, and Events: During the contract performance period, there may be other contracts, work, or events occurring in the park or within the project area limits that may affect the Contractor’s operations. The Contractor shall conduct operations in consideration of these other activities. If the other activities are affecting the critical path of the construction schedule, the Contractor shall document the issue in the daily reports and report the issue to the Contracting Officer.

1.5 CONTRACTOR USE OF SITE

A. Construction Camp or use of park housing: Establishment of a camp within the park will not be permitted.

B. Contractor shall always conduct their operations to ensure the least inconvenience to the Park Staff. Site closures will not be permitted. Work must be coordinated to permit normal use of the site by park staff throughout the term of the project.

C. Site Access: Maintain access and safety standards for National Park Service maintenance functions throughout the construction phase.

D. Working Hours: Regular work hours shall be limited to daylight hours from 7:00 a.m. until 5:00 p.m. Monday through Friday, excluding government holidays. Work outside regular hours requires advance approval from the Contracting Officer.

E. Staging and Storage: Confine the staging and storage of equipment and materials to the small parking area for the grave site in front of the cemetery wall.

F. The Contractor will be responsible for the security of all equipment and materials at the jobsite.

G. Property Damage: The Contractor is required to report missing, lost, stolen, or damaged property occurring within the park. This report must be made to the Park Facility Manager at the first available opportunity at: 406-381-2411.

H. No Smoking Policy: Smoking is prohibited.

PART 2 – WORK RESTRICTIONS

2.1 WORK RESTRICTIONS

A. General: The Contractor must comply with the following work restrictions:

B. Vehicles / Heavy Equipment:

1. Rules of the Road: All vehicles and heavy equipment will comply with posted traffic regulations, including speed limits and double-yellow center lane markings. Vehicles and heavy equipment shall take every safe opportunity to use paved roadside pullouts in order to allow faster moving traffic to pass. Failure to comply with traffic regulations will result in a citation being issued to the driver.

2. Vehicle Parking: The contractor shall park vehicles and heavy equipment in designated areas as established at the preconstruction meeting. Vehicles are not permitted within long-term or overnight parking along park roads or in associated overlooks / pullouts.

3. Driveways and Entrances: The contractor shall keep driveways and entrances serving the premises clear and available to the government, government employees, and emergency vehicles at all times.

4. Vehicle Exhaust: All vehicles will be properly maintained to ensure that the exhaust produced is within legal limits. Effects of excessive vehicle exhaust may be subject to enforcement of State and Federal laws regarding emissions as well as those regarding threatened and endangered species.

5. Spills: The Contractor shall be responsible for any cleanup efforts required in accordance with 40 CFR and all applicable state environmental quality laws regarding disposal and cleanup of hazardous / industrial wastes. The Contractor must immediately notify the Contracting Officer of spills.

6. DOT Compliance: All vehicles are to be compliant with all DOT requirements including but not limited to driver with appropriate license class, medical examiner card as appropriate with license class, carrying three (3) triangles or three (3) flares, mounted fire extinguisher, and valid DOT safety sticker.

C. Resource Protection:

1. General: The Park is committed to protecting natural and cultural resources found within the park and adjacent lands. The Contractor must comply with the following rules and conditions:

2. Preservation of Cultural Resources: Prevent damage to National Register listed cultural properties i Do not cause further damage to the cemetery wall, its footings, its masonry, or supporting structures.

ii Do not cause damage to the landscaping or cultural offerings left throughout the gravesite and cemetery.

3. Preservation of Natural Features: Prevent damage to natural surroundings.

a. Do not attach ropes, wires, guy lines, cables, or chains to trees or vegetation.

Restore damaged areas and replace damaged trees, vegetation, and grass at no additional expense to the government.

PART 3 – PROJECT MANAGEMENT

3. 1 SUBMITTALS

A. Submittal Documents: The following documents shall be submitted no later than 14 calendar days after contract award and a minimum of seven (7) calendar days prior to the Preconstruction Meeting. If all of these documents have not been received prior to the scheduled Preconstruction Meeting date, the meeting will be cancelled and the Notice to Proceed (NTP) will not be issued. Work shall not commence until written Notice to Proceed (NTP) has been issued.

1. Letter designating the Project Superintendent.

2. Construction Schedule - Submit a baseline schedule with start date, end date, major work activities and durations, estimated pre-final (substantially complete) and final (entirely complete) inspection dates, and other major milestones. Provide updates to baseline schedule as needed or as requested (when there is a change to the critical path).

3. Accident Prevention Plan (APP) – Submit a “site specific” accident prevention plan with the following information (at a minimum). Refer also to PART 5 Safety Requirements.

a. Name of the supervisor responsible for executing the plan.

b. Emergency contact phone numbers.

c. Map of local area emergency medical facilities relative to the jobsite.

d. First aid and emergency medical procedures / forms.

e. Company safety plan / protocol.

f. Job hazard analysis (JHA) completed for each major work activity.

g. Job specific COVID-19 plan.

4. Quality Control Plan (QCP) – Submit a “site specific” quality control plan with the following information (at a minimum). Refer also to PART 6 Quality Requirements.

a. Name of the supervisor responsible for executing the plan.

b. Organizational flow chart showing key staff / subcontractors.

c. Qualifications of key staff and subcontractors with applicable licenses / certificates.

d. Communications and reporting plan / procedures / forms (include NPS daily report form, RFI form, and CM-16 form along with Contractor forms).

e. Testing and inspection procedures at all phases of the project (i.e. preparatory, initial, follow-up) to ensure quality, with steps for correction of work / re-work.

5. Construction Waste Management Plan – Submit a construction waste management plan that addresses storage, handling, and disposal of all trash, recyclables, non-hazardous construction waste, and hazardous waste generated from the execution of the work.

Refer also to PART 8 Execution.

6. A list of Subcontractors for this project.

7. Written statements from subcontractors certifying compliance with applicable labor standard clauses.

8. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.

9. Hot Work Plan – Complete and submit a hot work management plan that addresses fire prevention for any work involving open flame or grinding metal.

B. Submittal Documents: The following documents shall be submitted to the Contracting Officer prior to construction mobilization. If these documents have not been received and approved by the NPS prior to construction start, the construction start date may be delayed.

1. Product Data – Submit product cut sheets / material data on all products to be used for approval.

3.2 PRECONSTRUCTION AND PROGRESS MEETINGS

A. Preconstruction Meeting: Before the start of construction, the Contracting Officer will arrange for a preconstruction meeting either on site or via teleconference. The meeting agenda will include the following topics:

1. NPS Roles & Responsibilities

2. Key Contractor Personnel

3. Coordination with Subcontractors

4. Correspondence & Submittal Procedures

5. Submittals

6. Park Rules & Regulations

7. Work Hours and Weekend, Holiday, and Night Work

8. Project Information

a. Jobsite Access & Parking

b. Staging, Storage, and Laydown Area(s)

c. Temporary Facilities & Controls

d. Jobsite Restrictions

e. Resource Protection

f. Reference Documents

h. Other Contracts / Ongoing Work

9. Labor Standards Provisions

10. Labor Interviews

11. Payroll Reports

12. Payments to the Contractor

13. Change Orders / Modifications

14. Progress Meetings

15. QC Daily Reports

16. Inspections

17. Acceptance and Rejection of Work

18. Closeout Procedures & Submittals

19. Contract Period of Performance

20. Notice to Proceed

3.3 REQUESTS FOR INFORMATION (RFIs)

A. General: On discovery of the need for additional information or interpretation of the Contract Documents, the Contractor shall prepare and submit an RFI utilizing the NPS form.

1. Contracting Officer will only respond to RFIs submitted by the Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

B. RFI Form: Include a detailed, legible description of the subject or item needing information or interpretation on the RFI Form with:

1. RFI number, numbered sequentially.

2. Date.

3. RFI subject.

4. Specification Section number and title and related paragraphs, if applicable.

5. Drawing number and detail references, if applicable.

6. Photographs or sketches, if applicable.

7. Contractor's suggested resolution. If the Contractor's suggested resolution impacts the contract time or the contract sum, Contractor shall state the impact in the RFI.

C. Response to the RFI: The Contracting Officer will review each RFI, determine the action required, and respond accordingly.

PART 4 – SUBMITTAL PROCEDURES

4.1 SUBMITTAL PROCEDURES

A. CM-16 Transmittal Form: All submittals shall be transmitted using NPS CM-16 form sent via email.. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form. Complete all applicable fields, sign the form, and attach all supporting documentation.

B. General Submittal Procedures:

1. Processing Time: Allow 7 days for NPS review of a submittal. When review is complete, an e-mail notification will be sent to the Contractor. No extension of contract time will be authorized because of failure to transmit submittals in a timely manner.

2. Approved Equals: For each item proposed as an “approved equal” submit supporting data including:

a. Comparison of the salient characteristics of the proposed item with that specified.

b. Name, address, and telephone number of vendor.

c. Manufacturer’s literature.

d. Compliance with the Buy American Act.

3. Electronic Submittals: Transmit all submittals except physical samples in PDF format.

4. Physical samples: Deliver physical samples to COR (or onsite POC).

PART 5 – SAFETY REQUIREMENTS

1.1 SAFETY REQUIREMENTS

A. General: The Contractor must comply with the following safety requirements:

1. First Aid Equipment: Provide adequate first aid equipment for all contract employees for the hazards associated with the types of ongoing construction work at the site.

2. First Aid Training: Provide adequate training to all Contractor personnel to ensure prompt and efficient application of first aid.

3. Personal Protective Equipment (PPE): Provide personal protective equipment (PPE) that meets applicable OSHA and ANSI standards for all contract employees.

4. Hazardous Materials: Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury. Store hazardous materials in accordance with manufacturer’s and OSHA recommendations. Maintain MSDS onsite for each chemical used on the jobsite.

Immediately report all spills of hazardous materials to the contracting officer.

5. Safety Meetings: At a minimum, conduct weekly "toolbox" safety meetings. These meetings shall be conducted by a job superintendent or crew leader and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the week.

6. Emergency Contacts: Post telephone numbers and reporting instructions for ambulance, hospital, fire department, police, and park dispatch in conspicuous locations at the site.

7. Emergency Medical & Accident Reporting: In the event of an emergency / medical incident, the Contractor shall Dial 911 as needed.

PART 6 – QUALITY REQUIREMENTS

6.1 QUALITY REQUIREMENTS

A. General: The Contractor is responsible for all quality control to guard against defects and deficiencies in the work. Inspect and test work as needed to ensure that the quality of materials, workmanship, construction, finishes, and functional performance are in compliance with applicable specifications, drawings, codes and standards, and the QC Plan.

B. Quality Control (QC) Daily Reports: Submit quality control daily reports documenting the progress and quality of the work. The daily report shall be typed, legible, and complete and include representative photos. The daily report shall be submitted on a daily basis no later than the day after the work. The NPS prefers that the contractor use the NPS daily report form, but an alternate form will be allowed if it contains all major sections of the NPS form.

PART 7 – TEMPORARY FACILITIES & CONTROLS

7.1 TEMPORARY FACILITIES & CONTROLS

A. General: The contractor will be allowed to set up temporary facilities and controls as outlined. All temporary facilities and controls shall be removed from the site before final acceptance of the work.

B. Temporary Utilities: The following utilities / services are available for use at the project site:

Electrical Power Service: No electrical power is available at the grave site or cemetery.

Water Service: potable water service is available from facilities at or near the project site for use on the contract without charge.

Sanitary Facilities: Restrooms are available at the site.

Telephone Cellular Service: The project site does have cellular service.

C. Temporary Storage: The Contractor is responsible for ensuring all materials are new and undamaged from weather, age, or neglect.

PART 8 – EXECUTION

8.1 EXECUTION

A. Examination: Examine the project area and site facilities and verify compatibility between existing conditions and the scope of work.

B. Preparation: Take field measurements or conduct surveys to verify quantities and dimensions before procurement and fabrication or installation.

C. Utilities: Existing utilities should not be interrupted by this work. In the event of a necessary interruption notify Contracting Officer and utility companies 48 hours in advance of proposed interruption.

D. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repairs to the utility will be at no additional expense to the Government.

E. Cutting & Patching: Examine surfaces to be cut and patched and conditions under which cutting and patching are to be performed. Before patching, verify compatibility with and suitability of substrates, including compatibility with in-place finishes or primers. Proceed with installation only after unsafe or unsatisfactory conditions have been corrected.

F. Installation: Install all components according to the specifications, manufacturer’s recommendations, permit conditions (where applicable), and local, State, and Federal codes, standards, and regulations. All components shall be complete and operable.

G. Correction of the Work: Upon discovery of defects or damage of new work or to existing facilities damaged by new work, repair or replace damaged systems or components and restore substrates and finishes.

H. Progress Cleaning: Clean the project site and work area on a daily basis. Keep site free of waste and debris in proper containment. Properly dispose of all waste and debris offsite.

I. Final Cleaning & Waste Disposal: At the completion of the work, clean all surfaces and remove all waste materials, trash, tools, equipment, machinery, and surplus items from the project site and legally dispose of all waste items.

PART 9 – CLOSEOUT PROCEDURES

9.1 SUBSTANTIAL COMPLETION AND FINAL INSPECTION

A. When the project, or a designated portion of the project, is substantially complete, the Contractor shall request a pre-final inspection in writing at least fourteen (14) calendar days in advance of the inspection date.

B. If the work is determined to be substantially complete at the pre-final inspection, the Contracting Officer will prepare a Letter of Substantial Completion with a Punch List of deficiencies to be corrected before final inspection / acceptance. The Contractor shall complete the work described in the Punch List within thirty (30) calendar days, as weather permits. Once all Punch List work is complete, the Contractor shall request a final inspection in writing to arrange for the confirmation of punchlist completion.

C. If the Contractor fails to complete the Punch List work within this timeframe, the Contracting Officer may either replace or correct the work with an appropriate reduction in the contract price or charge for re-inspection costs in accordance with the Inspection of Construction clause of the contract.

D. If the work is determined to be not substantially complete at the time of the pre-final inspection, the Contracting Officer will notify the Contractor in writing. The Contractor may request a new pre-final inspection; however, all re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction clause of the contract.

E. After all deficiencies have been corrected and the project is complete, a Letter of Final Acceptance will be issued by the Contracting Officer.

9.2 CLOSEOUT SUBMITTALS

A. Submit to the Contracting Officer with all applicable operation and maintenance information including but not limited:

1. Product / material cut sheets (all approved products used on the project).

2. Final report documenting work completed on the historic resource

3. Progress photos showing all phases of the work numbered sequentially.

4. Product warranties for individual products and systems.

5. A one (1) year Contractor-issued warranty on all workmanship starting from the date of final acceptance.

NOThe following information and photos on pages 13 - 25 have been added since the original Statement of Work.

Nez Perce National Historical Park

Old Chief Joseph Century Rock Wall Restoration

A. Introduction

The Old Chief Joseph Cemetery (OLJO) is located immediately south of the community of Joseph, Oregon near the north shore of Wallowa Lake. The 5-acre site is held in trust by the BIA for the Nez

Perce Tribe (NPT) and Confederated Tribes of the Umatilla Indian Reservation (CTUIR). The property was formerly owned by the Cooperative Farmers Ditch Company who transferred ownership of the property to the U.S. Government in 1923. The property was used by Nez Perce descendants as a burial area prior to the land transfer with the earliest marked grave being the 1897 grave of Sarah McFarland. In 1926, the remains of old Chief Joseph were relocated to the site from his original burial location near the

Lostine River.

The late 1930’s brought many improvements to the cemetery. Much of the built landscape was constructed by the Umatilla Civilian Conservation Corps Indian Division (CCC-ID) from 1938 through

1941. Projects conducted by the CCC-ID at the cemetery site were construction of a circular drive, stacked rock boundary wall, wire boundary fencing, irrigation and water conveyance systems, a drinking fountain, a concrete cistern, and vegetative plantings.

The most recognizable feature of the CCC-ID work on the site is the stacked rock wall that defines the northeastern boundary of the cemetery. The rock wall consists of two sections flanking either side of the cemetery entrance. At the cemetery entrance each of these wall sections (north section and south section) have stacked rock pillars that are capped with roughly square shaped concrete caps. Stacked rock pillars are also located at the opposite ends of each of the wall sections. The terminal pillars are smaller than those found at the cemetery entrance and did not exhibit the concrete cap (Figure 1 & 2).

The OLJO site has numerous historic preservation designations denoting the site’s regional and national level of significance. In 1989 the site was individually listed as a National Historic Landmark (NHL) and was included in 1992 as one of 38 units of Nez Perce National Historical Park. The site is listed on the

National Register of Historic Places as a component site of Nez Perce National Historical Park, and a

National Register eligible cultural landscape for the CCC-ID built features existing on the property. The site is also the congressionally designated beginning point of the Nez Perce National Historical Trail and a component of the Hell’s Canyon All American Road.

In the late summer of 2019, NPS crews conducted extensive preservation maintenance work on both the northern and southern sections of the OLJO stacked rock wall. This work was funded under an agreement between the Oregon Department of Transportation, CTUIR, NPT, and the NPS. Conducted under the direction of Gary Zybell, former head of the masonry division for the National Conservation and Training Center, the project focused on stabilizing and repairing degraded portions of the rock wall.

Preservation work consisted of repointing and replacement of deteriorated mortar and reinserting rocks that have become dislodged from the wall through mortar failure. Work also focused on reinforcing the wall in several key areas where it had separated due to ground shifting through frost heaves, foundation settling, and/or tree root growth. Large sections of the deteriorated concrete wall cap were also repaired and stabilized.

B. Damage to Stacked Rock Wall

In the spring of 2021, a one-vehicle accident resulted in damage to the southern most section of the historic stacked rock wall. A vehicle was traveling south bound on the highway paralleling the cemetery at an excessive speed. While attempting to navigate the slight left-hand curve the driver lost control of his vehicle and veered off the roadway hitting the soil embankment along the edge of the rock wall and careening into the extreme southern end of the wall. This resulted in the full force of the vehicle striking the southern-most end pillar nearly head-on. The end pillar was heavily damaged in the accident. The vehicle impact dislodged a large portion of the top section (Figure 3) and heavily damaged the east side

(Figure 4) of the end pillar. The west side (Figure 5) of the end pillar (on the cemetery side) remains mostly intact except for the top damage as discussed above. Figure 1 below shows the same pillar (from

2012) before the vehicle accident. An inspection of the wall by NPS staff several days after the accident occurred revealed that damage was solely confined to the southernmost end pillar and the overall structural integrity of the remainder of this section of wall was not affected by the vehicle collision.

C. Restoration Options

As discussed above, a large section of the upper portion of the southern end pillar was dislodged by the collision but remains intact. This portion of the stacked rock pillar still remains mortared together and seems to have maintained its structurally integrity (photo xx). In consultation with tribal representatives, it was determined the best course of action would be to attempt to rebuild and restore the pillar as close as possible to the original condition. In reviewing the post-accident condition of the end pillar, the nature of its original construction, and the way the pillar broke apart as a result of the collision two options for restoration seem feasible.

1. The first option is to attempt to reset the large, intact upper portion of the end cap back into place on top the lower section of the pillar. This will require lifting and supporting the top section in place and then rebuilding the supporting structure below through replacing dislodged rocks and mortaring them back together.

2. The second option is to attempt to rebuild the damaged end pillar from the intact base on up. This would require disassembly of the dislodged upper section of top pillar through manual removal of the mortar around the stones. Once completed the entire pillar could be rebuilt using stones dislodged from the existing base along with those from the disassembled top fragment.

Through onsite examination of the damage by NPS staff and consultation with tribal representatives it was determined to proceed with option one – resetting the dislodged top portion of the pillar back to its original location and then reassembling the middle section of the pillar with dislodged stones . This would effectively connect the original top section to the existing base of the pillar resulting in only the middle portion of the pillar being rebuilt.

This option is preferred for three primary reasons. 1) It retains as much of the original fabric (both stones and mortar) as possible; 2) Once properly set and realigned, it allows for restoration of the rock pillar with the majority of the rocks in their original location and orientation; and 3) disassembly

(through chipping out the existing mortar) of the top fragment required for the second option is likely to result in damage to the stones and may also result in a less accurate restoration process.

D. Proposed Process for Restoration

Through careful examination of before and after photographs we can identify the original location and orientation of the upper section of the damaged end pillar. Though the majority of the upper section of the pillar remains intact, much of the rocks and mortar in the middle of the pillar (especially the east side) was heavily damaged and broken apart by the vehicle accident. It is believed that many, if not all, those rocks from the damaged middle section remain on site and with some effort can be reinstalled in their original location. It is possible some of these rocks will not be found or are too damaged to reuse and in those cases other local rocks of the same size can be gathered from the area and used in their place. As noted below some of the rocks are easily visible in before and after the accident photographs of the end pillar. We can use this photographic evidence to establish their original orientation prior to the damage which should make the overall restoration process much easier.

Note: For sections 1 and 2 below please refer to the photographs located in Appendix 1. This appendix includes two sets of photographs (A1 & A2 and B1 & B2) that can be used to determine the original orientation and location of the dislodged top part of the pillar.

1. In photo A1 are seven rocks numbered 1-7 and one rock labeled with an “A”. These numbered rocks are also visible and identified by the same numbers in photo A2 showing the dislodged top piece. Please note that the top piece displayed in photo A2 is sitting upside down (i.e. the original top of the pillar is now resting on the ground in this photo). Additionally, the rock labeled as “1” in photo A2 was originally located on the cemetery side of the pillar resting just above (or at the level of) where the concrete wall cap meets the undamaged end pillar in photo A1. The rock labeled in photo A1 as “A” is missing from the top piece displayed in photo A2 as depicted by the “A” in the open space near the ground.

2. Photo B1 shows the remaining portion of the bottom pillar after the vehicle accident. There are nine numbered locations identified on the damaged bottom section of the pillar. Photo B2 shows the dislodged top piece again with the corresponding locations identified by the same numbers as noted in photo B1.

What these two sets of photos depict is that the original orientation of the top piece can be easily ascertained, and that enough of the corresponding features, stones, and mortar pockets can be matched up between the dislodged top piece and the intact lower pillar to reset the top piece on the lower pillar in exactly the same orientation as it was previously. Once set in place (and possibly temporarily supported) the remaining stones for the middle section of the pillar can then be reinstalled and mortared back together.

Restoration efforts should start by attempting to reset the top piece in its original location and orientation first to see if there are enough common attachment points to allow it to be self-supporting.

This will require a tractor with a bucket, small crane, or a tripod support structure built over the lower pillar section with a chain hoist to lift and support the piece in position. For secure lifting the top piece will likely require installation of lifting points (i.e. bolts or pins drilled and set into the mortar joints) to attach chains or straps from the lifting device (tractor bucket, tripod with hoist, or some lifting mechanism) to allow for the dislodged piece to be lifted up, over, and set down on the damaged lower section. Note: If the top piece can be lifted by straps or some other device or system not requiring holes and installation of lifting bolts that would be preferable.

Once the “fit” of the top piece on the damaged lower section can be determined, mortaring of that piece back into position can begin. This will require applying either a thin coat of mortar or an exterior stone and masonry approved adhesive to all the interior mating surfaces between the top and lower sections.

Based on the pre-mortar set of the top piece, it may or may not require bracing to hold it in position until the mortar or adhesive cures properly. If bracing is needed it will likely be on the southern, Wallowa Lake and/or highway sides of the top piece as those experienced the most damage from the accident. The side of the pillar adjacent to the cemetery and where it meets up to the wall section likely will not require bracing because of the number of intact stones and the corresponding fitment points in common between the existing pillar and the top piece.

All rocks found around the accident site that likely came from the damaged pillar should be gathered and sorted on site. To the best extent possible (by using photographs of the end pillar prior to the accident) these remaining dislodged rocks should be reinserted where they originally were located. For those areas of the pillar where viable photos do not exist, the original rocks cannot be found and/or are damaged, or the original orientation of the rocks cannot be determined, new stones found in the local area should be used. Every effort must be taken to place these stones in the same manner and fashion as was done originally.

The external mortar on this end pillar is a rusty red color. Some of the internal mortar was a natural grey. The NPS has the mortar mix and color tint information to match the original rusty red and internal grey color from the 2019 restoration efforts. The red mortar should be used throughout the restoration process. There is no need to attempt to match the grey interior mortar as the red mortar is what is visible from the outside and the color used internally will not be visible.

If an exterior grade stone and mortar adhesive can be identified, then it can be used in cases where original rocks are being reinserted into existing mortar pockets. Or, in situations like those depicted in photo B1 and B2 #7 and #8 where two rocks were broken and half by the collision and a piece of the same rock is present in both the bottom pillar and the top piece. In these locations there will likely not be enough space to allow for an adequate layer of mortar to be placed to secure the stone in place. For situations like this, a thin coat of adhesive can be applied to the intact mortar pocket or broken stone surface to allow for the top piece to sit in its original orientation. The adhesive will be provide a stronger bond to the mating surfaces in a much thinner application than can be achieved with mortar. Adhesive application must be limited to the internal surfaces only. It should not visible from the finished, external surfaces of the pillar.

Once the internal mortar and/or adhesive has set all the external joints can be repointed around the stones. This will create a water-tight seal, cover any signs of adhesive usage, and return the pillar to a uniform appearance. The joint between the wall cap and the newly reconstructed end pillar should be inspected as well and repointed as needed. It is likely that some of the gray top cap of the wall section where it meets the end pillar will need restoration work to keep the seam where the two features meet tight and minimize water intrusion.

E. Documentation of Restoration Work

All restoration work should be carefully photo documented through every step of the process. Photo points should be established on all sides of the pillar to allow for a series of uniform photographs taken from the same locations on a routine basis to document restoration efforts. Other close-up and detail photos should also be taken to document restoration efforts not visible from the established photo points. A brief restoration report should be produced detailing the methods, all products used, and procedures implemented in the restoration efforts.

Figure 1. Photograph of southern end pillar prior to accident (2012)

Figure 2. Photograph of northern end pillar after restoration work in 2019.

Figure 3. Photograph showing dislodged, but intact, top portion of southern end pillar (taken several days after the accident).

Figure 4. Photograph of southern end pillar noted damage to east side (facing the road).

Figure 5. Photograph showing the west side (cemetery side) of southern end pillar.

Photo A1

Photo A2

Photo B1

Photo B2

PART 1 – SUMMARY OF WORK & DEFINITION OF CLINs
PART 2 – WORK RESTRICTIONS
PART 3 – PROJECT MANAGEMENT
PART 4 – SUBMITTAL PROCEDURES
PART 5 – SAFETY REQUIREMENTS
PART 6 – QUALITY REQUIREMENTS
PART 7 – TEMPORARY FACILITIES & CONTROLS
PART 8 – EXECUTION
PART 9 – CLOSEOUT PROCEDURES