Attachment_A_Statement_of_Work.pdf

PDF 157 KB Posted

Attached to
Demolition Debris Removal, Olympic NP Federal contract opportunity
Solicitation number
140P8324Q0026
Issued by
Department of the Interior National Park Service Pacific West Region

About this file

This document is an Attachment A: Scope of Work for RFQ # 140P8324Q0026 for the removal of demolition debris from the Dosewallips campground in Olympic National Park.

The scope of work requires the contractor to remove all debris associated with the demolition of the Dosewallips campground and its seven structures, which consists of common household goods, appliances, and construction materials. The debris has been bundled or placed in helicopter bags by NPS day labor and flown to a private residence on 4931 Dosewallips Road. The contractor will be responsible for loading and hauling the debris into trucks or dumpsters and properly disposing or recycling it off-site. Hazardous materials surveys have been completed for the seven structures, and the reports indicate no asbestos detected and lead levels below the TCLP threshold.

View the file

Other files for this federal contract opportunity

Other files attached to Demolition Debris Removal, Olympic NP, newest first.
File Type Posted
Sol_140P8324Q0026.pdf PDF
Attachment_B_DOL_Wage_Determination.pdf PDF
Attachment_C_Forms_to_Return_with_Quote.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFQ # 140P8324Q0026

Attachment A: Scope Of Work Olympic NP

SCOPE OF WORK

Disposal of Dosewallips Demolition Debris

Olympic National Park

PART 1- GENERAL INFORMATION

The work of this contract is to remove all debris associated with the demolition of the Dosewallips campground and it’s seven structures. Debris will consist of common household goods, appliances, and construction materials.

Debris will be bundled together or loaded into helicopter bags by NPS day labor and flown to a private residence on 4931 Dosewallips Road. The contractor will be responsible for loading and hauling debris into trucks or dumpsters, and then properly disposing or recycling it off-site.

1.0 Description of Work

Contracted hazardous materials surveys for all seven structures have been completed and will be provided to the selected contractor. The reports identified the following findings:

• Dosewallips Comfort Station: No Asbestos Detected. Samples collected from on-site structure did not contain greater than or equal to 5 ppm (0.5/5,000 ppm) TCLP Lead. Leaching results <1.

• Dosewallips Hydro Building: No Asbestos Detected. Samples collected from on-site structure did not contain greater than or equal to 5 ppm (0.5/5,000 ppm) TCLP Lead. Leaching results <1.

• Dosewallips Ranger Station: No Asbestos Detected. Samples collected from on-site structure did not contain greater than or equal to 5 ppm (0.5/5,000 ppm) TCLP Lead. Leaching results <1.

• Dosewallips Residence: No Asbestos Detected. Samples collected from on-site structure did not contain greater than or equal to 5 ppm (0.5/5,000 ppm) TCLP Lead. Leaching results <1.

• Dosewallips Storage Shed: No Asbestos Detected. Samples collected from on-site structure did not contain greater than or equal to 5 ppm (0.5/5,000 ppm) TCLP Lead. Leaching results <1.

• Dosewallips Vault Toilet: No Asbestos Detected. Samples collected from on-site structure did not contain greater than or equal to 5 ppm (0.5/5,000 ppm) TCLP Lead. Leaching results <1.

• Dosewallips Firewood Shed: No Asbestos Detected. Samples collected from on-site structure did not contain greater than or equal to 5 ppm (0.5/5,000 ppm) TCLP Lead. Leaching results <1.

To the greatest extent possible, all work of the project shall remain within existing road corridors and impacted sites. The contractor shall take great care to avoid impacting any vegetation on site. The contractor will keep the landowners’ roadways clear of rocks and debris created in association with this project work.

Between August 21 – October 31 work shall be restricted as follows:

• work shall only occur between two hours after sunrise and two hours before sunset.

• 48-hour notification will be provided to the NPS prior to mobilization

• The landowners’ gates will be closed and secured while on-site and upon leaving the site

All refuse removed from the sites must be disposed of, recycled or salvaged, in accordance with federal and state regulations outside of the park’s boundaries. The method of removal may be determined by the contractor. If contractor anticipates that completion of work will impede traffic on roadways, they must provide traffic control and one-week advance notification to the park.

Olympic National Park Disposal of Dosiewallips Ranager Station Debris

The Park has made every effort to identify all major elements of the project below. Contractor is responsible for verification of quantities and all miscellaneous, ancillary elements. The intent is that all the material associated with the project will be hauled off-site and disposed of properly.

Approximate quantities of debris to be removed at the following location include:

SITE 1: COREY PROPERTY, 4931 DOSEWALLIPS RD, BRINNON, WA

• Dosewallips Comfort Station: 320 sf stick build structure estimated 28.2-tons.

• Dosewallips Storage Shed: 168 sf stick build structure 14.1-tons.

• Dosewallips Hydro Building: 160 sf stick build structure 14.3 tons

• Dosewallips Residence: 216 sf stick build structure 18.2 tons.

• Dosewallips Ranger Station: 385 sf stick build structure 30 tons

• Dosewallips Outhouse and Firewood Shed: 64 sf stick build structure 4.8 tons.

• Misc. demolition materials, propane tank and water tank: 45 sf, estimated 2-tons.

OPTION ITEMS: N/A

WORK DESCRIPTION:

1.1 Location: This project is located on the Corey property, which is private land located at 4931

Dosewallips Road, in Brinnon, Washington. See attachment 1 for maps of the area and project sites.

1.2 Regular Working Hours: Regular working hours at the park are from 7:00 a.m. to 5:00 p.m., Monday through Friday, excluding federal holidays. All work shall be scheduled during regular working hours.

Contractor must adhere to workday restrictions imposed to protect limit disruption to private landowners.

1.3 Notification: The Contractor shall provide a project schedule that identifies all phases of the project.

1.4 Work Restrictions: Requests to work outside of regular working hours must be approved by the

Contracting Officer (CO) through the COR one week in advance.

1.5 Waste Disposal: The contractor shall legally recycle or dispose of all project materials outside of the park boundary. Materials should be diverted away from landfills to the greatest extent possible.

Tickets identifying load weight shall be provided to the CO for all disposed materials whether recycled or sent to a landfill.

1.6 Overnight Camping: The Contractor, subcontractors, or others directly or indirectly involved with the project will not be allowed to camp or stay overnight at the removal site.

1.7 Inspection: All work shall be inspected on an ongoing basis by NPS personnel. The Contractor shall provide for and allow complete and unobstructed access to all work areas.

Olympic National Park Disposal of Dosiewallips Ranager Station Debris

1.8 Site Conditions: The removal site is located on private land. Contractor will be responsible for correcting any damage that may occur to the gravel road, ditches, or field due to equipment use during the removal process.

1.9 Equipment: The Contractor will pressure wash and/or steam clean all construction equipment, except hauling vehicles, before entering the Park to ensure that all equipment, machinery, rocks, gravel, or other materials are cleaned and weed free. Motors/engines will not be left unattended.

Equipment will be free of any fluid leaks (fuel, oil, hydraulic fluid, etc.) upon arrival to the work site and will be inspected at the beginning of each shift for leaks. Leaking equipment will be removed off site for necessary repairs before the commencement of work.

PART 2- SUBMITTALS

The Contractor shall complete and submit the following submittals in a timely fashion (as soon as feasible after award) to the NPS contacts listed below:

• Safety Plan

• Disposal plan

The following items shall be submitted upon completion of the project work:

• Weight tickets for recycled materials and for materials sent to landfill

• Listing and approximate weights of any donated materials or supplies

• Chain of custody documentation for any hazardous material disposal

• Final site inspection will be complete by NPS. The contractor will be responsible for repairing damage caused by the debris removal.

part 1- general information
Site 1: Corey Property, 4931 Dosewallips Rd, Brinnon, WA

File details come from the government source that posted it. Updated .