Attachment_2_Material_Specs.pdf

PDF 2 MB Posted

Attached to
MORA-MNT ROADS GARAGE Concrete Floors, Trench Drai
Solicitation number
140P8318Q0088
Issued by

About this file

Attachment 2 - Material Specs

View the file

Other files

File Type Posted
Sol_140P8318Q0088_Amd_0001.pdf PDF
Attachment_3_Drawings.pdf PDF
B03_Wage_Determination.pdf PDF
Sol_140P8318Q0088.pdf PDF
Attachment_5_-_Bond_Form_SF25A.pdf PDF
Read_Me_First.pdf PDF
Attachment_1_Specifications.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MOUNT RAINIER NATIONAL PARK

MORA PMIS No. 157430

REHABILITATE LONGMIRE ROADS GARAGE

100% FINAL (Revised 5-2018)

CONSTRUCTION DOCUMENTS

FOR

NPS

SWPPP & MATERIALS SPECIFICATIONS

NATIONAL PARK SERVICE

PACIFIC WEST REGION

April 2018

MORA - 157430 PROJECT TEAM - 1

MOUNT RAINIER NATIONAL PARK, WASHINGTON

REHABILITATE LONGMIRE ROADS GARAGE

MORA PMIS No. 157430

PROJECT TEAM:

CONTRACTING OFFICER:

Contact: Pam Griffin National Park Service 55210 238th Ave E Ashford, WA 98304 pam_griffin@nps.gov

(P) 360-569-6541

CONTRACTING OFFICER’S REPRESENTATIVE:

Contact: Ryan Mettler National Parks Service 55210 238th Ave E Seattle, WA 98104 ryan_mettler@nps.gov

(P) 360-569-6732

PARK POINT OF CONTACT (POC):

Contact: Mitch Anderson, Building Supervisor National Parks Service 55210 238th Ave. E.

Ashford, WA 98304 mitch_anderson@nps.gov

(P) 360-569-6726

CIVIL ENGINEER: Holladay Engineering

Contact: John Blom, Principal 32 N Main Street Payette, ID 83661 john@hecoengineers.com

(P) 208-642-3304

STRUCTURAL ENGINEER: Holladay Engineering

Contact: Elwin Butler, PE 32 N Main Street Payette, ID 83661

Elwinb @hecoengineers.com

MORA - 157430 PROJECT TEAM - 2

ELECTRICAL ENGINEER: HECO Engineers

Contact: Brett Anderson 32 N Main Street Payette, ID 83661 bretta@hecoengineers.com

MEP ENGINEER: DC Engineering

Contact: Jeff Curtis, PE 440 East Corporate Drive, Suite 103 Meridian, ID 83642 jcurtis@dcengineering.net

(P) 208-288-2181

END OF SECTION

MORA – 157430 TABLE OF CONTENTS - 1

TABLE OF CONTENTS

DIVISION 01 – RELATED SECTIONS NO. OF PAGES

01 11 40 Work Restrictions 01 35 13.22 Archeological Protection 01 57 23 Temporary Storm Water Pollution Prevention 01 73 40 Execution (Survey Control Points, Benchmarks)

DIVISION 02 – SITE WORK

02 05 00 General Site Construction Requirements

DIVISION 03 – CONCRETE

03 21 00 Concrete Reinforcing Steel 03 30 00 Cast-in-Place Concrete 03 30 01 Concrete Floor Slabs 03 31 00 Normal Weight Structural Concrete 03 40 00 Precast Concrete Items

DIVISION 05 – METALS

05 50 00 Metal Fabrications

DIVISION 07 - THERMAL & MOISTURE PROTECTION

07 21 00 Building Insulation 07 90 00 Joint Sealers

DIVISION 22 – PLUMBING

22 05 00 Common Work Results for Plumbing 22 05 29 Hangers & Supports for Plumbing Piping & Equipment 22 05 48 Vibration & Seismic Control for Plumbing Piping & Equipment 22 05 53 Identification for Plumbing Piping & Equipment 22 07 00 Plumbing Insulation 22 11 16 Domestic Water Piping 22 13 16 Sanitary Waste & Vent Piping 22 13 19 Sanitary Waste Piping Specialties 22 34 00 Fuel Fired Domestic Water Heaters

MORA – 157430 TABLE OF CONTENTS - 2

DIVISION 23 – HEATING, VENTILATING & AIR CONDITIONING

23 05 29 Hangers & Supports for HVAC Piping & Equipment 23 05 53 Identification for HVAC Piping & Equipment 23 05 93 Testing Adjusting & Balancing for HVAC 23 07 00 HVAC Insulation 23 21 13 Hydronic Piping 23 21 23 Hydronic Pumps 23 37 13 Diffusers, Registers & Grilles 23 52 16 Condensing Boilers 23 83 16 Radiant Heating Hydronic Piping 23 82 39 Unit Heaters

DIVISION 26 – ELECTRICAL

26 00 00 Electrical General Requirements 26 05 00 Common Work Results For Electrical 26 05 19 Low Voltage Electrical Power Conductors & Cables 26 05 26 Grounding & Bonding for Electrical Systems 26 05 29 Hangers & Supports for Electrical Systems 26 05 33 Raceway Boxes for Electrical Systems 26 05 48 Seismic Requirements for Electrical Systems 26 05 53 Identification for Electrical Systems 26 28 16 Enclosed Switches & Circuit Breakers

DIVISION 31 – EARTHWORK

31 10 00 Site Clearing 31 22 13 Rough Grading 31 23 00 Excavation & Fill 31 23 17 Watering 31 25 00 Erosion & Sediment Control

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 11 23 Aggregate Base Course 32 11 27 Underslab Capillary Break 32 13 13.06 Portland Cement Concrete 32 15 00 Restoration of Surfaces

DIVISION 01

RELATED SECTIONS

MORA – 157430 01 11 40 - 1

WORK RESTRICTIONS

SECTION 01 11 40

WORK RESTRICTIONS

PART 1 – GENERAL

1.1 SPECIAL SCHEDULING REQUIREMENT

A. Conduct work operations so National Park Service operations will not be disrupted. Provide not less than seven (7) calendar days’ notice to the Contracting Officer of activities that will affect National Park Service operations.

B. Permission to interrupt any road, trail, campground or other area shall be requested in writing a minimum of seven (7) calendar days prior to the desired date of interruption.

C. Notify Park Biologists two weeks in advance of any work in stream so frog juveniles can be removed / relocated.

1.2 PARK REGULATIONS

A. The Contractor must comply with the following rules and conditions:

1. Ensure personnel (contractors or subcontractors) working in the park become familiar with and obey all park regulations, wear hard hats in designated areas, and do not enter any restricted areas unless required to do so and until cleared for such entry.

2. Ensure equipment is conspicuously marked for identification.

3. The Contractor shall restrict employees / representatives to the work site and control travel directly to and from the work site.

4. Restore all traffic / parking / security signs and markings, including space numbers, designations, and lines, to their original form if such signs / markings are defaced or deleted during construction/repair.

5. Control and security of Contractor-owned equipment and materials at the work site.

Report immediately missing / lost / stolen property to the park dispatch / law enforcement rangers at 360-569-6600.

6. Vehicles associated with the Contractor shall be waived the entrance fee upon entering in a marked company vehicle or by providing the names of employees entering in personal vehicle(s). Please note that the entrance fee is waived only for the purpose of reporting directly to a specific work location. Any deviation for recreational purposes is subject to payment of required entrance fees.

a. Contractor will provide the Contracting Officer with a listing of its subcontractors and their associated vehicles and employees entering the park on a daily basis.

b. Contractor will provide the Contracting Officer with a listing of anticipated deliveries for each week.

MORA – 157430 01 11 40 - 2

WORK RESTRICTIONS

7. Vehicles / Heavy Equipment:

a. Rules of the Road: All vehicles and heavy equipment will comply with posted traffic regulations, including speed limits and double-yellow center lane markings. Vehicles and heavy equipment shall take every safe opportunity to use paved roadside pullouts in order to allow faster moving traffic to pass. Failure to comply with traffic regulations will result in a citation being issued to the driver.

b. Vehicle Parking: Vehicles are not permitted within long-term or overnight parking along park roads or in associated overlooks / pullouts. Vehicles and heavy equipment will be permitted at designated parking areas only.

c. Vehicle Exhaust: All vehicles will be properly maintained to insure that the exhaust produced is within legal limits. Effects of excessive vehicle exhaust may be subject to enforcement of State and Federal laws regarding emissions as well as those regarding threatened and endangered species.

d. Spills: Contractor shall be responsible for any cleanup efforts required in accordance with 40 CFR and all applicable state environmental quality laws regarding disposal and cleanup of hazardous / industrial wastes. Contractor must immediately notify the Contracting Officer of spills.

e. Commercial Vehicle Safety Inspections: The Contractor, employees, contractors, and subcontractors shall fully cooperate regarding safety inspections of commercial vehicles within the Park. Commercial vehicle safety inspections are conducted unannounced for employee and visitor safety. Vehicles are checked for safety and mechanical deficiencies and for compliance with current state and federal laws and regulations. Driver licenses and medical certificates are also checked.

f. Department of Transportation (DOT) Compliance: All vehicles are to be compliant with all DOT requirements including but not limited to driver with appropriate license class, medical examiner card as appropriate with license class, carrying three (3) triangles or three (3) flares, mounted fire extinguisher, and valid DOT safety sticker.

g. Slow Vehicles: The Contractor is to notify the Contracting Officer of slow vehicles that may cause traffic delays or extended traffic lines. Vehicles that are slow are requested to enter the Park AFTER 2:00 p.m. and exit the Park BEFORE sunset. If night delivers are necessary, they are to be completed during the months of December and January only.

h. Oversized Vehicles: Oversized vehicles are defined as vehicles where the width of the vehicle or load exceeds one lane (i.e., beyond the center line of the paved road). Oversized vehicles must not exceed the clearances along the Park road corridor. Oversized vehicles will require an escort and drivers must avoid driving on the edges of the Park road. The Contractor is to notify the Contracting Officer of oversized vehicles, scheduled dates and estimated arrival times at the park entrance, and the identity of who is escorting the vehicle (e.g., police, contractor, etc.). Vehicles that are oversized are requested to enter the Park AFTER 2:00 p.m. and exit the Park BEFORE sunset.

i. Road Work: Contractor shall provide adequate traffic control, including flaggers on either side of any work performed on the road. Any workers on or near the road must wear highly visible, bright clothing. (See Section 01 50 00 for additional details.)

MORA – 157430 01 11 40 - 3

WORK RESTRICTIONS

j. Law Enforcement: Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity. Contractor must immediately comply with any instructions issued by a park law enforcement ranger.

k. Road & Weight Restrictions: All vehicle load, weight and size limitations, as established by State law, apply to vehicles operated on the Park road (36 CFR § 4.11). No loads heavier than the current load rating for the historic Park bridge will be permitted.

8. Emergency Medical and Accident Reporting

a. The Contractor or subcontractor shall contact Park Dispatch for any medical emergency or traffic accident occurring within the Park. Emergency number:

Dial 911 as needed. Park Dispatch: 360-569-6600. Park Dispatch is called so that the entrance station will be prepared should any emergency vehicles (e.g.

ambulance) need to enter the Park and so that any available Emergency Medical Services personnel in the Park might respond until such time as the ambulance arrives.

b. The Contractor or subcontractor is required to report ANY personal injury and / or property damage incident occurring within the park. This report must be made to a Law Enforcement Ranger at the first available opportunity before leaving the park: Park Dispatch: 360-569-6600

PART 2 - PRODUCTS (not used)

PART 3 EXECUTION (not used)

MORA – 157430 01 35 13.22 - 1

ARCHEOLOGICAL PROTECTION

SECTION 01 35 13.22

PART 1 - GENERAL

1.1 SUMMARY

A. The work of this section consists of protecting archeological resources contained in soil deposits.

1.2 DEFINITIONS

A. Archeological Resources: Archeological resources are the physical evidences of past human activity, including evidences of the effects of that activity on the environment. Archeological resources represent both prehistoric and historic time periods. They are found above and below ground and under water.

B. Archeologically Sensitive Areas: Areas that have the potential to contain significant

(National Register eligible) archeological resources. If National Register eligible or listed archeological resources could not be avoided, an appropriate mitigation strategy would be developed in consultation with the state historic preservation officer and, if necessary, associated American Indian tribes.

C. Non-sensitive Areas: Areas with little, if any, potential of containing significant (National

Register eligible) archeological resources.

D. Archeological Monitor: Representative of the Government designated to oversee construction activities that could disturb archeological resources.

E. Archeological Resources Protection Act (ARPA) of 1979 (P.L. 96-95; 93 Stat. 712): defines archeological resources as any material remains of past human life or activities that are of archeological interest and at least one hundred (100) years old; Section 4 of the statute describes the requirements that must be met before Federal authorities can issue a permit to excavate or remove any archeological resource on Federal or Indian lands; the curatorial requirements of artifacts, and other materials excavated or removed.

1.3 SUBMITTALS

A. Daily Work Schedule; Submit a Daily work Schedule detailing construction work in archeologically sensitive areas. Submit to Contracting Officer thirty (30) days before start of ground disturbing site work.

MORA – 157430 01 35 13.22 - 2

1.4 QUALITY ASSURANCE

A. At least one (1) week before on-site work begins, Contractor shall meet with Contracting Officer and Archeological Monitor to discuss Daily Work Schedule and equipment and special methods to be used in archeologically sensitive areas. Contractor shall ensure that approved Daily Work Schedule is followed throughout construction.

PART 2 – PRODUCTS

2.1 DAILY WORK SCHEDULE

A. A Daily Work Schedule is required for all work occurring within archeologically sensitive areas. Include all work that is to occur within the area and key the schedule to the drawings to include the following:

1. Starting and ending dates of ground-disturbing construction.

2. Locations of temporary facilities, such as barriers, field offices, staging areas, sanitary facilities, borrow pits, and haul and access roads.

3. Types of construction, such as clearing, topsoil stripping, structure or trench excavation, landscaping, and post construction clean-up.

4. Methods and equipment used for each type of construction.

5. Plan for relocating work in the event of temporary work stoppages at each archeologically sensitive area

PART 3 – EXECUTION

3.1 BARRICADES

A. Comply with requirements specified in Division 01 Section “Temporary Facilities & Controls.”

3.2 ARCHEOLOGICAL INVESTIGATION BY NON-NPS PERSONNEL

A. All archeological work will be undertaken by NPS personnel, if required.

3.3 OBSERVATION

A. Archeological Monitor will observe all ground-disturbing site work, including construction of temporary facilities, at all archeologically sensitive areas, from a safe location mutually agreed on by Contractor and Monitor. As new ground is broken, Monitor will examine excavated materials, using construction layout centerline and perimeter staking as a reference point to record locations of findings.

3.4 DISCOVERY OF RESOURCES

A. If Archeological Monitor discovers resources, immediate relocation of the work to a non-sensitive area may be required to allow Monitor to identify and document resources and, if necessary, develop an appropriate mitigation plan. While Archeological Monitor is

MORA – 157430 01 35 13.22 - 3

ARCHEOLOGICAL PROTECTION

documenting resources in sensitive areas, Contractor shall relocate work to non-sensitive areas where monitoring is not normally required.

B. If resources are discovered while Archeological Monitor is absent, stop work immediately and report the discovery to the Contracting Officer.

3.5 WORK STOPPAGE

A. The Contractor shall plan, schedule, and execute the work to prevent stoppages at one area from stopping all work at the construction site.

MORA – 157430 01 57 23 - 1

TEMPORARY STORM WATER

POLLUTION PREVENTION

SECTION 01 57 23

TEMPORARY STORM WATER POLLUTION PREVENTION

A. Federal Regulations for controlling discharges of pollutants (including chemicals, erodible material, and trash) from municipal separate storm sewer systems, construction sites, and industrial activities, were brought under the National Pollution Discharge Elimination System (NPDES) permit process by amendments to the Clean Water Act (CWA), and promulgation of federal stormwater regulations issued by the U.S. Environmental Protection Agency (USEPA). The USEPA uses the amount of ground disturbance as a measure of a project potential to generate pollution from erosion. NPDES Phase I regulates discharges from construction sites that disturb five (5) acres or more. NPDES Phase II regulations expand the existing General Permit requirements under Phase I to include/regulated discharges from construction sites that disturb land equal to or greater than one (1) acre and less than five (5) acres, known as Small Construction Activity. Construction disturbances one (1) acre and above typically require a formal NPDES permit and a formal Stormwater Pollution Prevention Plan (SWPPP) must be submitted to the Authority Having Jurisdiction (AHJ) for review and approval.

B. The work of this section consists of implementing measures to prevent discharges of pollutants, including temporary storm water pollution during construction activities, either through compliance with the NPDES permit program; Or in conformance with NPS guidance for UPPPs.

1.2 DEFINITIONS

A. Definitions pertaining to sustainable development: As defined in ASTM E2114.

B. Environmental Pollution and Damage: The presence of chemical, physical, or biological elements or agents which adversely affect human health or welfare; unfavorably alter ecological balances; or degrade the utility of the environment for aesthetic, cultural, or historical purposes.

C. National Pollution Discharge Elimination System (NPDES) Phase I: Regulates discharges from construction sites that disturb five (5) acres or more.

D. NPDES Phase II: Regulations expand the existing General Permit requirements under Phase I to include and regulate discharges from construction sites that disturb land equal to or greater than one (1) acre and less than five (5) acres, known as Small Construction Activity.

MORA – 157430 01 57 23 - 2

TEMPORARY STORM WATER

POLLUTION PREVENTION

E. Storm Water Pollution Prevention Plan (SWPPP): Developed and implemented stormwater management measures to protect surface water from pollutants during construction activities disturbing an acre or more in compliance with federal, state, and local requirements for permit approval under the NPDES program.

1.3 DOCUMENTS

A. Before internal NPS pre-construction conference, prepare:

1. A SWPPP showing that the SWPPP satisfies all Federal and State NPDES permit requirements;

B. Inspection Schedule: Prepare a schedule that provides for inspection and monitoring of all storm water pollution prevention measures.

C. Erosion Control Products: Obtain manufacturer’s product information and installation recommendations for silt fence, filter fabric, erosion control blanket, straw bales, and any other materials intended for use on this project.

1.4 QUALITY ASSURANCE

A. The Park shall prepare a plan for internal review and concurrence.

B. Orientation Meeting: The Park shall be responsible for arranging and conducting an Erosion and Sediment Control meeting/briefing to inform all parties scheduled to be on-site during the project of the measures to be implemented for proper erosion and sediment control (may be included as part of the Park’s internal Pre-Construction Meeting and again during the Contractor’s Pre-Construction Meeting).

1. Installation of silt fences, storm drain protection, and all other forms of erosion and sediment control shall not begin until after the internal NPS meeting has occurred.

C. Pollution Prevention and Erosion Control Manager: The Park shall designate the Pollution Prevention and Erosion Control Manager who will be responsible for the implementation, inspection, maintenance, and amendments to the approved plan.

1. The Pollution Prevention and Erosion Control Manager shall be familiar with temporary storm water pollution prevention procedures and Best Management Practices (BMPs) and shall ensure that emergency procedures and the plan are updated as needed and available for inspection.

2. When changes in the approved plan are required, the Pollution Prevention and Erosion Control Manager shall prepare and certify an amendment and submit the amended plan for internal NPS review and concurrence.

MORA – 157430 01 57 23 - 3

TEMPORARY STORM WATER

POLLUTION PREVENTION

PART 2 – PRODUCTS

2.1 TEMPORARY STORM WATER POLLUTION PREVENTION PLAN

A. Provide a SWPPP which satisfies all Federal and State NPDES permit requirements and includes the following information and forms:

1. Site description.

2. Identification and contract information for Pollution Prevention and Erosion Control

Manager.

3. Expected sequencing of operations and construction schedule.

4. Weather monitoring procedure.

5. Descriptions and details BMPs for of pollution prevention and erosion controls, including dust control.

6. Pollution prevention and erosion control plans.

7. Controls for other potential onsite storm water pollutants.

8. Applicable specifications.

9. Maintenance and inspection procedures and forms.

10. Description of potential non-storm water discharges at site.

11. Notice of Intent (NOI) form.

12. Notice of Termination (NOT) form.

13. NPS Certification forms.

14. Contractor and Sub-contractor Certification forms.

15. Other record keeping forms and procedures.

16. Housekeeping Best Management Practices, including vehicle wash-down areas, protection of equipment storage and maintenance areas, and sweeping of roadways related to hauling activities.

PART 3 – EXECUTION

3.1 ENVIRONMENTAL PROTECTION

A. Protection of Natural Resources: Comply with applicable regulations and these specifications. Preserve the natural resources within the project boundaries and outside the limits of work performed during construction in their existing condition or restore to an equivalent or improved condition.

B. Construction Zone: Arrange construction activities to minimize pollution (i.e., erosion, trash, etc.) to the maximum practical extent.

1. Clearing, excavation, and grading shall be limited to those areas of the project site necessary for construction. Minimize the area exposed and unprotected.

2. Clearly mark and delineate the limits of work activities.

3. Equipment shall not be allowed to operate outside the limits of work or to disturb existing vegetation.

4. Excavation and grading shall be completed during the dry season to the maximum extent possible.

5. Material should be stored one hundred (100) feet from water.

MORA – 157430 01 57 23 - 4

TEMPORARY STORM WATER

3.2 REGULATORY REQUIREMENTS

A. Permits: The Park shall obtain all required NPDES permits in a manner that results in no impacts to scheduled work. The Park shall account for the possibility of significant lead time in scheduling and executing the work.

B. Implement the requirements of the NPDES permit for erosion control due to storm water runoff during construction.

C. Implement all good housekeeping practices, inspections and record keeping.

D. Prior to construction, the Park, Contractor and all subcontractors shall sign certifications (included in the plan) that they understand the requirements of the NPDES permit.

E. All subcontractors shall comply with the requirements of the NPDES under the supervision of the Contractor.

F. The accepted plan must comply with the terms and conditions of the EPA permit.

G. Notice of Intent (NOI): The Park shall file a Notice of Intent and formal SWPPP as required to the Authority Having Jurisdiction (AHJ).

H. Notice of Termination (NOT): After Substantial Completion of the construction project, file a

Notice of Termination (NOT) with the AHJ.

I. NPS Notification: The Park shall notify the Contractor in writing and by telephone of the following events:

1. The required erosion and sediment control meeting/briefing.

2. Following installation of required sediment control structures.

3. Prior to removal of or modification to sediment control structures.

4. Prior to removal of all sediment control structures.

3.3 TEMPORARY STORM WATER POLLUTION PREVENTION PLAN

A. Review and Acceptance: The Park and the Contractor will jointly review the current Plan in place prior to Contractor beginning any work and agree to any needed revisions. The Park shall incorporate all revisions, sign, and submit the final Plan to the Contractor. The final Plan will be the document enforced on the project.

B. The accepted Plan will describe and ensure implementation of the practices which will be used to reduce the pollutants in storm water discharges.

C. The Park shall maintain a current copy of the Plan and all associated records and forms at the jobsite throughout the duration of the project.

D. The Plan shall be available at all times for public inspection and for the inspection and use of the Contractor.

MORA – 157430 01 57 23 - 5

TEMPORARY STORM WATER

POLLUTION PREVENTION

E. Approval of the Park’s Plan will not relieve the Contractor or Park of responsibility for compliance with applicable environmental regulations.

F. Implementation: Implement the Plan as required throughout the construction period and maintain all erosion control elements in proper working order.

G. Do not perform clearing and grubbing or earthwork until the Plan has been implemented.

H. The SWPPP (including inspection forms) and all data used to complete the NOI shall be kept by the Park for their records and provided to the Contractor after Substantial Completion of the project.

3.4 SITE INSPECTIONS AND PLAN REVISIONS

A. Inspections: The Park and the Contractor will perform a weekly inspection of the site.

B. The inspection shall include disturbed areas that have not been completely stabilized, areas used for storage of materials, locations where vehicles enter or exit the site, and all other erosion and sediment controls that are included in the Plan.

C. Inspections shall be documented.

D. The inspection forms shall be retained onsite in the Plan notebook throughout the construction period.

E. Plan Revisions: It may be necessary to revise the Plan during construction to make necessary improvements, revisions, or to respond to unforeseen conditions noted during construction or site inspections.

F. The Plan shall specify the mechanism whereby revisions may be proposed by the Contractor or the Park.

G. The Contractor and the Park will jointly review each revision to the Plan before changes are incorporated and implemented. The Park will then provide a revised copy of the Plan to the Contractor.

H. Accepted modifications will be implemented within 7 calendar days following the date of the inspection when deficiencies or necessary corrections are first noted.

I. Negligence: Provide additional temporary erosion and pollution controls made necessary by Park’s errors or negligence at no additional cost to the Contractor.

3.5 HOUSEKEEPING AND SITE MANAGEMENT

A. Materials stored on site should be stored in conformance to federal, state, local, and manufacture’s regulations and specifications. Additionally, BMPs should be used to minimize the risk of materials coming into contact with environmental conditions (i.e. water and wind) that could disperse them.

MORA – 157430 01 57 23 - 6

TEMPORARY STORM WATER

POLLUTION PREVENTION

B. Solid waste should be managed in conformance to federal, state, and local regulations. BMPs should be used to minimize the risk of materials coming into contact with the environmental conditions (i.e. water and wind) that could disperse them.

C. The project should include a spill prevention and control plan with provisions placed in the

SWPPP.

D. Hazardous waste (including contaminated soil) should be managed in conformance to federal, state, local and NPS regulations and guidelines.

3.6 EROSION CONTROL MEASURES

A. Erosion control measures shall consist of any and all BMPs for storm water discharges, including but not limited to silt fencing, barrier protectors, straw bales, temporary soil retention blankets, excelsior drainage filters, sediment traps and berms.

B. Berms and excelsior drainage filters shall be used to form sediment traps and to control run-on and run-off into other areas, including creeks, streams, marshes, access roads, well areas, and the staging areas.

C. Erosion control measures shall be used to contain only direct precipitation in the construction zone. The contained water shall be allowed to percolate into the ground or drain slowly through the drainage filter sediment traps.

D. Earthen sediment traps or holding ponds shall not be used unless accepted by the Park.

E. Reduce runoff velocity as well as direct surface runoff around and away from all fuel containment, storage, and borrow areas.

F. Divert surface runoff around and away from cut and fill slopes.

G. Place drainage filters around all catch basins to create sediment traps to control run-off from the construction area.

H. Excess water used for dust control shall be contained within the demolition areas by the erosion control measures.

I. The Park and Contractor shall prevent the deposition of materials onto paved areas. The Park and Contractor shall inspect the paved areas for deposited materials weekly and remove the materials immediately.

J. Furnish, install, maintain, and operate necessary control measures and other equipment necessary to prevent erosion as described in the approved SWPPP.

K. Before the work begins, sufficient equipment shall be available on the site to assure that the operation and adequacy of the erosion control system can be maintained.

MORA – 157430 01 57 23 - 7

TEMPORARY STORM WATER

3.7 MAINTENANCE OF TEMPORARY FACILITIES

A. Ensure erosion and sediment control structures remain effective throughout excavation and grading operations. Relocate structures as necessary.

B. Inspect control structures after each significant rainfall. Promptly repair breaches which occur.

C. The Park shall remove entrapped sediment from behind excelsior drainage filter after each storm.

3.8 REPORTING

A. If a discharge occurs or if the project receives a written notice or order from any regulatory agency, the Park will file a written report to the AHJ within seven (7) days of the discharge event, notice, or order. Corrective measures shall be implemented immediately following the discharge, notice, or order. The report to the AHJ shall contain the following items at a minimum:

B. The date, time, location, nature of operation, and type of discharge, including the cause or nature of the notice or order.

C. The BMPs deployed before the discharge event, or prior to receiving the notice or order.

D. The date of deployment and type of BMPs deployed after the discharge event, or after receiving the notice or order, including additional BMPs installed or planned to reduce or prevent re-occurrence.

E. An implementation and maintenance schedule for any affected BMPs.

3.9 SEDIMENT DISPOSAL

A. Sediment excavated from temporary sediment control structures shall be disposed on the site with general fill, or with topsoil. Sediment shall be allowed to dry out as required before reuse.

B. The Park shall place the sediment removed from traps and other structures where it will not enter a storm drain or watercourse and where it will not immediately reenter the basin.

3.10 REMOVAL OF TEMPORARY STORM WATER POLLUTION CONTROL MEASURES

A. All temporary control measures shall be removed by the Park within twenty (20) working days after final acceptance of the project, and/or once grading is completed and slopes have stabilized.

MORA – 157430 01 73 40 - 1

EXECUTION

SECTION 01 73 40

EXECUTION

A. This Section includes general procedural requirements governing execution of the Work including, but not limited to, the following:

1. Construction layout.

2. Field engineering and surveying.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 CONSTRUCTION LAYOUT

A. Verification: General: Engage a land surveyor to lay out the Work using accepted surveying practices.

1. Establish benchmarks and control points to set lines and levels of construction and elsewhere as needed to locate each element of Project.

2. Establish dimensions within tolerances indicated. Do not scale Drawings to obtain required dimensions.

3. Inform installers of lines and levels to which they must comply.

4. Check the location, level and plumb, of every major element as the Work progresses.

5. Notify NPS Project Manager when deviations from required lines and levels exceed allowable tolerances.

6. Close site surveys with an error of closure equal to or less than the established standard.

MORA – 157430 01 73 40 - 2

EXECUTION

B. Site Improvements: Locate and lay out site improvements, including pavements, grading, fill and topsoil placement, utility slopes, and invert elevations.

C. Record Log: Maintain a log of layout control work. Record deviations from required lines and levels. Include beginning and ending dates and times of surveys, weather conditions, name and duty of each survey party member, and types of instruments and tapes used. Make the log available for reference by NPS.

3.2 FIELD ENGINEERING

A. Reference Points: Locate existing permanent benchmarks, control points, and similar reference points before beginning the Work. Preserve and protect permanent benchmarks and control points during construction operations. Controls that are destroyed by Contractor will be replaced by the Contractor at their expense.

1. Existing Monuments: All bench marks, land corners, and triangulation points, established by other surveys, existing within the construction area shall be preserved.

If existing monuments interfere with the work, secure written permission before removing them.

B. Benchmarks: Establish and maintain a minimum of two (2) permanent benchmarks on

Project site, referenced to data established by survey control points. Comply with NPS requirements for type and size of benchmark.

1. Record benchmark locations, with horizontal and vertical data, on Project Record

Documents.

DIVISION 02

SITE WORK

MORA – 157430 02 05 10 - 1

GENERAL SITE CONSTRUCTION REQUIREMENTS

SECTION 02 05 10

1.1 DESCRIPTION

A. The work of this Section includes the general procedures and requirements for Site Work.

PART 2 – PRODUCTS (not used)

3.1 EXAMINATION

A. Site Verification of Conditions

1. Construction work shall be coordinated with the drawings to assure that no conflict with the proposed work exists.

2. Upon discovery of conflicts or problems with construction documents, notify Engineer within twenty-four (24) hours.

3.2 PREPARATION

A. Protection

1. Spillage -

a. Avoid spillage by covering and securing loads when hauling on or adjacent to public streets or highways.

b. Remove spillage and sweep, wash, or otherwise clean project, trails, streets, and highways.

2. Dust Control - See Soil Erosion & Sedimentation Control – Section 31 25 00.

3. Sediment and Erosion Control - See Soil Erosion & Sedimentation Control – Section

31 25 00.

4. Existing Plants And Features - Do not damage tops, trunks, and roots of existing trees, shrubs or other vegetation on site which are intended to remain. Do not use heavy equipment within branch spread. Do not damage other plants and features which are to remain.

MORA – 157430 02 05 10 - 2

3.3 REPAIR / RESTORATION - Per NPS

3.4 FIELD QUALITY CONTROL

A. Additional testing may be required to re-affirm suitability of completed work including compacted soils which have been exposed to adverse weather conditions.

DIVISION 03

CONCRETE

MORA – 157430 03 11 19 - 1

INSULATING CONCRETE FORMING

MORA – 157430 03 21 00 - 1

CONCRETE REINFORCING STEEL

SECTION 03 21 00

CONCRETE REINFORCING STEEL

A. The work covered in this Section includes furnishing and installing concrete reinforcing steel for concrete construction as indicated in the Contract Documents.

1.2 REFERENCES

A. American Concrete Institute

1. ACI 318-08

B. American Society For Testing And Materials

1. ASTM A615 / A615M-15a, 'Standard Specification for Deformed and Plain Billet- Steel Bars for Concrete Reinforcement'

2. ASTM A934 / A934M - 13 Standard Specification for Epoxy-Coated Prefabricated Steel Reinforcing Bars

C. Concrete Reinforcing Steel Institute

1. CRSI ‘Reinforcing Steel—The Manual of Standard Practice.’

1.3 SUBMITTALS

A. As specified in Division 01 Section 01 33 23 “Submittal Procedures.”

B. Certification from steel supplier that meets minimum requirements of specification.

1.4 DELIVERY, STORAGE, AND HANDLING

A. Reinforcing steel shall be free of heavy rust scales and flakes, or other coating at time of delivery and placing. Properly protect rebar on site after delivery.

MORA – 157430 03 21 00 - 2

CONCRETE REINFORCING STEEL

PART 2 - PRODUCTS

2.1 MATERIAL

A. Reinforcing Steel

1. Rebar shall have grade identification marks and conform to ASTM A 615.

a. Grade sixty (60) minimum.

b. Bars shall be deformed type.

c. Bars shall be epoxy coated and conform to ASTM A934 for use in cast in place construction where ground water has been encountered.

d. Bars shall be free of heavy rust scales and flakes, or other bond-reducing coatings.

B. Welded Wire

1. Welded wire fabric shall conform to ASTM 185.

2.2 FABRICATION - NOT USED.

3.1 INSTALLATION

A. Bend bars cold according to the recommendations of Chapter 7, the current ACI 318.

B. Accurately place and support with chairs, bar supports, spacers, or hangers as recommended by the current edition of CRSI ‘Reinforcing Steel—The Manual of Standard Practice’.

MORA – 157430 03 30 00 - 1

CAST-IN-PLACE CONCRETE

SECTION 03 30 00

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of contract, including Division 0 1 Specification Sections apply to work of this Section.

1.2 SECTION INCLUDES

A. Reinforcing Steel

B. Concrete Formwork, shoring and bracing.

C. Cast in place concrete foundations, walls and structure.

1.3 REFERENCES

A. All references shall be the latest adopted edition.

B. American Concrete Institute International:

1. ACI 117 - Tolerances for Concrete Construction and Materials

2. ACI 211.1 - Standard Practice for Selecting Proportions for Normal, Heavyweight, and Mass Concrete

3. ACI 301 - Specifications for Structural Concrete for Buildings

4. ACI 304R - Guide for Measuring, Mixing, Transporting, and Placing Concrete

5. ACI 305R - Hot Weather Concreting

6. ACI 306R - Cold Weather Concreting

7. ACI 308R – Guide to Curing Concrete

8. ACI 309R - Guide for Consolidation of Concrete

9. ACI 315 – Details and Detailing of Concrete Reinforcement

10. ACI 318 - Building Code Requirements for Reinforced Concrete and

Commentary

11. ACI 347R – Formwork For Concrete

12. ACI 347.2R – Guide for Shoring/Reshoring of Concrete Multistory Buildings

C. ASTM International:

1. ASTM C33 - Standard Specification for Concrete Aggregates

2. ASTM C94 - Standard Specification for Ready-Mixed Concrete

3. ASTM C143 - Standard Test Method for Slump of Hydraulic-Cement Concrete

4. ASTM C150 - Standard Specification for Portland Cement

5. ASTM C231 - Standard Test Method for Air Content of Freshly Mixed

Concrete by the Pressure Method

MORA – 157430 03 30 00 - 2

CAST-IN-PLACE CONCRETE

6. ASTM C260 - Standard Specification for Air-Entraining Admixtures for Concrete

7. ASTM C494 - Specification for Chemical Admixtures for Concrete

8. ASTM C618 - Standard Specification for Coal Fly Ash and Raw or Calcined

Natural Pozzolan for Use in Concrete

9. ASTM C989 - Standard Specification for Slag Cement for Use in Concrete and

Mortars

10. ASTM C1059 - Standard Specification for Latex Agents for Bonding Fresh to

Hardened Concrete

11. ASTM C1077 - Standard Practice for Laboratories Testing Concrete and Concrete

Aggregates for Use in Construction and Criteria for Laboratory Evaluation

12. ASTM E329 - Standard Specification for Agencies Engaged in Construction

Inspection and/or Testing

D. Concrete Reinforcing Steel Institute:

1. CRSI – Manual of Standard Practice

1.4 SUBMITTALS

A. Refer to Division of the specifications for submittal procedures.

B. Product Data: For each type of manufactured material and product indicated.

C. Design Mixes: For each concrete mix, submit proposed mix designs minimum of fifteen (15) days in advance of placing operations for each type of concrete.

Submitted mix designs shall include the following:

1. Supporting test data for mixes shall not be more than twelve (12) months old.

Include a sufficient number of tests, conduct a statistical analysis in compliance with ACI 301.

2. Gradation of fine and coarse aggregates not more than ninety (90) days old showing compliance with ASTM C33. No substitutions of aggregate type or size from those submitted shall be allowed.

3. Proportions of all ingredients, including all admixtures added either at time of batching or at job site. Aggregate weights shall be based upon saturated surface dry conditions.

4. Water/cement ratio.

5. Slump as measured according top ASTM C143. Provide slump test for each mix.

6. Air content of freshly mixed concrete as measured according to ASTM C231.

7. Strength measured at seven (7) and twenty-eight (28) days. Provide strength test for each mix at a frequency of both the seventh (7th) and twenty-eighth (28th) day.

Strength shall be tested using four inch (4”) diameter by eight inch (X 8”) cylinders in accordance with ASTM C31 and ASTM C39.

8. Certifications that all ingredients in each mix are compatible.

9. Locations or intended use of each mix design.

10. Source of all materials.

MORA – 157430 03 30 00 - 3

CAST-IN-PLACE CONCRETE

D. Material Certificates: Signed by manufacturer’s certifying that each of the following items complies with the requirements:

1. Cementitious materials and aggregates. Include mill certificates for cement.

2. Steel reinforcement and reinforcement accessories.

E. Steel Reinforcement Shop Drawings: Details of fabrication, bending, and placement prepared according to ACI 315, “Details and Detailing of Concrete Reinforcement” and as follows:

1. Include material, grade, bar schedules, stirrup spacing, bent bar diagrams, arrangement, and supports of concrete reinforcement.

2. Include special reinforcement required for openings through concrete structures.

3. Provide placement details for all specific reinforcing intersections and clearance conditions not shown by the typical details on the structural drawings.

4. Prepare drawings in sufficient detail to resolve all reinforcing intersections.

F. Embedded Item Placement Drawings: Drawings indicating the location and type of plates, anchorages, or other items to be embedded in the finished concrete surfaces.

G. ICBO reports for mechanical splice couplers.

1. Admixtures

2. Mechanical Splice Couplers

3. Reinforcing Steel

4. Concrete Accessories

5. Joint Devices and Materials

6. Embedded Items Placement Drawings

7. Concrete Mix Design

8. Material Certificates

1.5 QUALITY ASSURANCE

A. Installer Qualifications: installers shall be experienced and have completed concrete work similar in material, design and extent to that indicated for this project, and whose work has resulted in construction with a record of successful in-service performance.

B. Comply with reference documents unless more stringent provisions are indicated.

C. Perform form work in accordance with ACI 347R, ACI 301, and ACI 318.

D. Perform reinforcing steel installation in accordance with ACI 301.

E. Perform concrete work in accordance with ACI 301 and ACI 318.

F. Follow recommendations of ACI 305R when concreting during hot weather.

G. Follow recommendations of ACI 306R when concreting during cold weather.

MORA – 157430 03 30 00 - 4

1.7 DELIVERY, STORAGE AND HANDLING

A. Store materials in accordance with ACI 301.

B. Deliver, store and handle steel reinforcement to prevent bending and damage.

1.8 COORDINATION AND SEQUENCING

A. Coordinate schedule with other trades where embedments, attachments or interferences occur.

B. Schedule and sequence concrete work to coordinate with fabrication and delivery schedules for items to be embedded in concrete work.

1.9 FIELD MEASUREMENTS

A. Verify that field measurements and conditions are as shown on drawings, shop drawing or as instructed by Product Manufacturer.

1.10 DESIGN RESPONSIBILITY: FORMWORK, BRACING, SHORING & RESHORING

A. Contractor is responsible for designing and engineering formwork along with associated bracing, shoring and re-shoring to withstand all imposed construction forces.

2.1 FORM MATERIALS

A. Form Materials (for concrete not exposed to view): Provide per ACI 347R at discretion of Contractor.

B. Form Material For Type 1 and 2 Concrete Finish (exposed to view): APA rated B-B

High Density Concrete Form Overlay plywood, Class I, conforming to PS 1.

1. Plywood shall be new, or used once with face free of defects and nail holes filled.

2.2 FORMWORK ACCESSORIES

A. Form Ties: Factory-fabricated cone type, fixed length, removable or snap off metal or glass fiber reinforced plastic form ties designed to break off below face of wall after formwork is stripped.

1. Strength and spacing as required to resist fresh concrete placement and vibration loads and to prevent spalling of concrete on removal.

MORA – 157430 03 30 00 - 5

CAST-IN-PLACE CONCRETE

2. Furnish units that will leave no corrodible metal closer than one (1) inch to the plane of the exposed concrete surface.

3. Furnish ties that, when removed, will leave holes not larger than 1-inch in diameter in concrete surface.

B. Shoring And Bracing: Provide materials/system designed by Contractor to withstand all imposed construction forces.

C. Form Release Agent: Colorless, non-staining, low or no VOC, shall not adversely affect surface coatings or waterproofing.

D. Nails, Spikes, Lag Bolts, Through Bolts, Anchorages: Sized as required, of sufficient strength and character to maintain formwork in place while placing concrete.

2.3 REINFORCEMENT

A. Reinforcing Steel: As specified in General Notes on the Structural Drawings.

B. Reinforcement Accessories:

1. Tie Wire: Annealed, minimum sixteen (16) gage.

2. Chairs, Bolsters, Bar Supports, Spacers: Sized and shaped for adequate support of reinforcement during concrete placement.

a. Manufacture bar supports according to CRSI’s “Manual of Standard Practice” from steel wire, plastic or precast concrete or fiber-reinforced concrete of greater compressive strength than concrete.

b. Provide plastic or stainless steel chairs and accessories in walls where finish wall surface is exposed to view.

c. Provide stainless steel or plastic components for placement within one and one-half inches (1-1/2”) of weathering surfaces.

3. Mechanical Splices: Where approved by the Engineer, provide ICBO listed mechanical splices of Type 1 or Type 2 as defined by ACI 318. If splice type is not otherwise defined, provide Type 2.

C. Reinforcement – Fabrication

1. Fabricate concrete reinforcing in accordance with CRSI - Manual of Standard Practice.

2. Fabricate in accordance with ACI 315, providing concrete cover as specified or indicated.

3. Bending and straightening in accordance with ACI 318, Chapter 7, unless otherwise noted on the drawings. No bending or straightening of reinforcement permitted after partial embedment in concrete. Heating of reinforcement shall not be permitted unless approved in writing by Contracting Officer.

4. Splicing: Lap splice reinforcing bars for tension with lap lengths as noted on the structural drawings.

MORA – 157430 03 30 00 - 6

CAST-IN-PLACE CONCRETE

5. Welding of reinforcement is permitted only with the specific approval of Structural Engineer. Perform welding in accordance with AWS D1.4.

6. Locate reinforcing splices not indicated on drawings at point of minimum stress.

Indicate locations on shop drawings.

2.4 CONCRETE MATERIAL

A. Cement: Portland Cement: as specified on the Structural Drawings.

1. Provide cement from same source for entire project.

B. Slag Or Flyash:

1. Slag Or Flyash - Select One Only:

a. Slag: Ground granulated blast furnace slag conforming to ASTM C989

Grade 100 or 120.

b. Flyash: Conform to ASTM C618, Class F.

c. Manufacturers:

1) Boral Material Technologies, Inc.

2) Full Circle Solutions, Inc.

3) Headwater Resources, Inc.

4) Holcim US, Inc.

5) Lafarge North America

6) Mineral Resources Technologies, LLC

7) Mineral Solutions, Inc.

8) The SEFA Group

C. Aggregates:

1. Aggregates: Conform to the requirements of ASTM C33 and subject to the approval of the Contracting Officer.

a. Do not use high alkaline content aggregates that would prevent slab surface from achieving a pH of nine (9) or less after curing and dehydration.

b. Provide aggregate from same source for entire project.

c. Comply with requirements for limits for deleterious substances and physical property requirements of aggregate per ASTM C33 for severe weathering.

D. Water: Potable and complying with ASTM C94.

2.5 ADMIXTURES

A. Admixtures: As specified in Structural General Notes and the following:

1. Admixtures certified by manufacturer to contain no more than 0.05 percent water-soluble chlorine ions by mass of cementitious material. Do not use admixtures containing calcium chloride or thiocyanate.

MORA – 157430 03 30 00 - 7

CAST-IN-PLACE CONCRETE

2. Where more than one admixture is used in the mix, submit manufacturer’s certification that admixtures are compatible in combination with cement and aggregates.

3. Accelerating admixtures shall not be used.

B. Air-Entraining Admixture: ASTM C260

1. Master Builders Micro-Air

2. W.R. Grace Daravair 1000

2.6 CONCRETE ACCESSORIES

A. Bonding Agent: ASTM C1059, Type II acrylic non-redispersable type.

B. Non-Shrink Grout: As specified in General Notes on Structural Drawings.

C. Patching (For finishing concrete exposed to view):

2.7 JOINT DEVICES AND MATERIALS

A. Waterstops:

1. Composite Bentonite and butyl rubber waterstop; Volclay Waterstop-RX or approved.

2. PVC with heat/chemically welded seams.

2.8 CONCRETE MIX DESIGN

A. Prepare design mixes for each type and strength of concrete determined by either laboratory trial mixtures or field experience according to ACI 211.1 and ACI 301.

B. Use a qualified independent testing agency for preparing and reporting proposed mix designs for laboratory trial mix basis.

C. Concrete mix design: comply with Structural Drawing requirements.

D. Provide percentage by weight of cementitious materials other than Portland Cement in concrete.

E. Minimum Requirements:

1. Provide minimum cement content per ACI 301.

F. Limit water soluble chlorine ion content in hardened concrete to 0.15 percent by weight of cement.

MORA – 157430 03 30 00 - 8

CAST-IN-PLACE CONCRETE

G. Use admixtures according to manufacturer’s written instructions.

H. Maximum aggregate size is one-inch for walls.

2.9 MIXING

A. Transit Mixers: Measure, batch, mix and deliver concrete according to ASTM C94,…