This Statement of Work (SOW) details a historic window restoration project for the Brown v. Board of Education National Historical Park in Topeka, Kansas. The project involves a proof of concept (POC) mockup focusing on rehabilitating a single second-story steel triple-casement window unit, which exhibits significant deterioration including rust, failing sealant, and moisture penetration. The National Park Service seeks a contractor to remove the window, restore it offsite while maintaining its historical design, and potentially investigate more energy-efficient glass options.
The project has a 270-day performance period with specific milestone deadlines, including a project start-up meeting within 30 days of contract award, window removal by day 60, contractor examination and recommended treatment plan by day 120, and project completion by day 240. Key deliverables include high-resolution documentation, restoration of the window unit's sash, frame, and hardware, and recommendations about storm window retention. Potential bidders can inspect the window units externally 24/7 and internally by appointment from Tuesdays to Saturdays, 7:00 am to 3:00 pm. All digital project data will be delivered on a flash or external drive.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P6425Q0065_Amd_0002.pdf | ||
| Sol_140P6425Q0065_Amd_0001.pdf | ||
| Technical_Questionnaire_-_Service.docx | DOCX document | |
| Price_Schedule_-_Window_Concept.xlsx | XLSX spreadsheet | |
| Past_Performance_Questionnaire.doc | DOC document | |
| Sol_140P6425Q0065.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BROWN V. BOARD OF EDUCATION
NATIONAL HISTORICAL PARK
TOPEKA, KANSAS
HISTORIC WINDOW REHABILITATION AND
PROOF OF CONCEPT
PMIS N/A
PROJECT STATEMENT OF WORK
NATIONAL PARK SERVICE
6/18/2025
SCOPE
Performance Period: The work of this contract shall be completed within 270 days a er award.
Confiden ality: Informa on developed under this contract shall not be shared and will be kept in strict confidence.
Project Iden fica on: The work of this project shall consist of the services described below for the referenced project. In all related documents, the project shall be referred to Historic Window Restora on and Proof of Concept, Brown v. Board of Educa on Na onal Historical Park.
BACKGROUND
Brown v. Board of Educa on Na onal Historical Park preserves 3.15 acres of land including the former Monroe Elementary School at 1515 SE Monroe Street in Topeka, Kansas. The Monroe School was one of four segregated elementary schools in Topeka for Black children. It opened in 1927. The park commemorates the landmark 1954 United States Supreme Court decision in Oliver Brown et al. v. Board of Educa on, which unanimously ruled that segrega on of children in public schools by race was uncons tu onal. In 1992, President George H.W. Bush signed legisla on crea ng Brown v. Board of Educa on Na onal Historic Site and in 2004, the park opened to the public on the 50th anniversary of the landmark ruling. In May 2022, President Joseph R. Biden signed the Brown v. Board of Educa on Na onal Historical Park Expansion and Redesigna on Act, which renamed and expanded the park’s boundary in Topeka, KS; added a new park unit in Summerton, SC; and created five affiliated areas in Delaware, Virginia, and the District of Columbia.
PROJECT METHODS
There are 91 total openings with steel casement windows. There are 369 sashes. This project includes only one opening: the large window unit on the south end of the second floor. The glass was replaced prior to 2004 and is 1/8” clear glass.
Experts in historic windows made these technical observa ons and condi on assessments in 2024:
Windows are a subframe, frame, and sash design with slider stay open arms.
Failing perimeter sealant where the windows meet the masonry.
Openings are currently covered with interior aluminum storm windows. Storm windows are impac ng the overall beauty of the building in an effort to gain energy efficiency. Storm windows are not ven ng correctly and crea ng a moisture containment issue.
Each observed opening showed significant rust. Rust has penetrated behind both the frames and subframes of each window. If the rust is not removed from all sides of the window components, it will come back in ma er of years.
Sash and Frames have been altered to remove an upper stay open arm, but the holes le behind were not filled and water is entering through those holes.
Observed mul ple areas many units where water is penetra ng the unit.
Glass is currently glazed with a silicon product in a manner to emulate a pu y glaze, but the product was designed for the applica on and is failing. Complete glazing failure observed on mul ple lites.
Individual glass panes are 1/8” clear glass and measure about 10 3/16” x 12 ¼”.
Sash hinges a ach to the frame between the frame and the masonry.
In par cular, these condi ons were noted for the proposed unit to be removed and restored in this project:
• Steel triple-casement transoms—paint in fair condi on; frame in fair condi on; sash in fair condi on; hardware in fair condi on; glazing in poor condi on; stone sill in fair condi on; interior plaster in fair condi on; overall in fair condi on. Also, frame/sash corrosion is present with moisture present at the plaster; glazing sealant/pu y is in need of full replacement.
The treatment report recommended that a proof of concept (POC) mockup be completed on one unit.
The window unit in ques on is the second-story unit in the photo below:
Approximate interior measurements of the window unit:
69.5 inches W x 86.5 inches H
DELIVERABLES
Deliverables for the project will include:
A proof of concept (POC) mockup of one window unit.
The unit will be removed from its opening for restora on offsite. This includes sash, frame, subframe, and hardware on the opening.
The opening will be covered securely with ¾” OSB Plywood and anchored to the building in such a way as to not disturb the historical fabric of the building.
All finishes and rust will be removed from the window unit offsite a er removal of the window from the building.
All unused penetra ons will be filled and repaired using epoxy fillers. This applies to holes in the metal frames from previous uses.
The window sash will be glazed with new or recovered glass units. The contractor will maintain the historical design of the windows while inves ga ng whether more energy-efficient glass can be installed in place of the exis ng glass.
Painted finishes will be removed from hardware, which will then be cleaned and polished.
Window sash, frame, and subframe will have shop-applied high performance steel finish. The contractor will consult with the NPS with specific product recommenda ons a er the paint and rust are removed and the unit is available for complete documenta on and inspec on of condi on.
The restored window unit will be re-installed in its opening and sealed to the masonry.
The contractor will recommend whether storm windows should be retained or modified.
The contractor will document with high-resolu on photography every step of the POC mockup.
This includes a comparison to the windows as installed to the architect’s drawings of them from 1926. (See image provided below).
All digital data will be delivered on a flash or external drive.
PROJECT SCHEDULE
Poten al bidders are welcome to observe the window units in the building from the outside 24 hours/day, seven days/week. Poten al bidders are encouraged to inspect the windows from the interior by making an appointment with the superintendent or maintenance worker from Tuesdays to Saturdays, 7:00 am to 3:00 pm.
Following the award of the contract, NPS Staff will schedule a kick-off mee ng within thirty (30) working days to finalize the project schedule and work plan.
NLT Day 30: Project Start-up Mee ng.
NLT 60 days from award: Window unit is removed and opening is covered securely.
NLT 120 days from award: Contractor examines window unit and recommends course of ac on to NPS.
Within 15 days, the NPS will approve the treatment plan.
NLT 240 days from award: Contractor completes the work, reinstalls the window, and submits its report and documenta on to the NPS for approval.
NLT 270 days from award: Final invoice and project close out.
Detail from 1926 architectural drawings of the window sashes. The POC project will confirm the as-built windows in comparison to the architectural drawings. No other drawings of the window units exist.