This document is an Addendum (Amendment #1) for Solicitation 140P6425B0001 for the West Beach Picnic Shelter Replacement project at Indiana Dunes National Park. The addendum addresses a significant change in project scope due to a fire on May 30, 2025, which destroyed one of the shelters in the project area. The amendment now requires the contractor to include demolition of the fire-damaged shelter, specifically noting the removal of the concrete slab, steel columns, grills, and remaining debris.
The addendum includes two photographs documenting the current condition of the fire-damaged picnic shelter, showing a burned-out structure with charred remains, yellow caution tape, and surrounding landscape with trees and open ground. The images provide visual evidence of the damage and the area that will require demolition as part of the contract's expanded scope.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Questions___Answers_-_Part_2_0002.pdf | ||
| Sol_140P6425B0001_Amd_0002.pdf | ||
| Sol_140P6425B0001_Amd_0001.pdf | ||
| Questions___Answers_0001.pdf | ||
| Revised_Bid_Opening_Information_0001.pdf | ||
| Sol_140P6425B0001.pdf | ||
| Appendix_A_-_Drawings.pdf | ||
| Bid_Schedule.xlsx | XLSX spreadsheet | |
| Appendix_B_-_Pictures.pdf | ||
| Project_Specifications.pdf | ||
| DBA_WD_-_Porter_County__IN.pdf | ||
| Limitations_on_Subcontracting_Report.xlsx | XLSX spreadsheet | |
| Notice_to_Contractors.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum
Solicitation 140P6425B0001
Amendment #1
West Beach Picnic Shelter Replacement
Indiana Dunes National Park
On May 30, 2025, one of the shelters in the project scope was destroyed by fire. See attached photos showing current conditions. Demolition of what remains shall remain in the contract scope, including concrete slab, steel columns, grills, and remaining debris.