Questions_and_Answers_0001.pdf

PDF 97 KB Posted

Attached to
Fence Replacement Federal contract opportunity
Solicitation number
140P6424Q0012
Issued by
Department of the Interior National Park Service Midwest Region

About this file

This document contains questions and answers regarding a solicitation to replace cattle fencing and gates at Indiana Dunes National Park. The solicitation will be a firm-fixed price construction contract set aside 100% for total small businesses between $25,000 and $100,000. The work includes removing and replacing cattle fencing with 12.5-gauge wire and 14-gauge barbs spaced no more than 5 inches apart. Posts will be non-structural treated wood pounded into the ground with regular post lengths of 7 feet 6 inches and 2 feet 6 inches buried. The total fence height will be 5 feet. Electrical grounding is required per the National Electrical Code and no footers or foundations will be provided for gate posts.

View the file

Other files for this federal contract opportunity

Other files attached to Fence Replacement, newest first.
File Type Posted
Sol_140P6424Q0012_Amd_0001.pdf PDF
Price_Schedule_-_Fence_Replacement.pdf PDF
Price_Schedule_-_Fence_Replacement.xlsx XLSX spreadsheet
Specifications_-_Fence_Replacement.pdf PDF
Technical_Questionnaire.docx DOCX document
Sol_140P6424Q0012.pdf PDF
Attachment_-_Appendix_A_Drawings.pdf PDF
Attachment_-_Provisions_to_be_Completed.pdf PDF
Wage_Determination_-_Porter_Co.pdf PDF
Attachment_-_Appendix_B_Pictures.pdf PDF
Attachment_-_Construction_Contract_Administration.pdf PDF
Technical_Questionnaire.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation #: 140P6424Q0012

Amendment #: 0001

Fence Replacement – INDU

Questions and Answers listed below:

QUESTIONS:

Question # Question Answer/Response 1.

Is there a specific product spec'd for the cattle wire? The specs listed in the SOW doesn't describe exactly what kind of wire is needed.

See Section 32 31 26 Page 19, ASTM A121 aluminum-coated, Type A, Class 3 with 12.5-gauge wire with 14 gauge, round, 4-point barbs spaced no more than 125 mm 5 inches apart.

2.

Moving Gates to 16 ft openings consists of moving a post that will end up changing line post positions. How do we use the same holes if we are moving a post at the gate to keep every line post distance correct (spacing)?

Driving new post into the ground “In-pound” as necessary to follow drawings and specifications.

3.

Structural Post or Non structural ? Lines and Corners.

Non-Structural posts will be use in this project including lines and corners.

4.

On the south side of the second phase posts are doubled, meaning one post then one at 4' or 5' then one is at 9' approximately. Do we keep the post every 4' or 5'?

If we remove the center post of these and they are over 9' spacing what would be the biggest spacing, we could have?

Install single post where there is no gate and don’t exceed the maximum post separation as shown in the drawings. Driving new post into the ground “In-pound” in those areas as necessary. (No excavation is allowed)

5.

Specifications section 3.2.5 mentions electrical grounding.

We do not see any details showing the means and method of attaching an electrical grounding system to the fence at the specified locations. Can the USG provide this information?

Means and methods to be provided by the contractor and to follow National Electrical Code 23rd edition.

6.

The drawing details provided do not show the height of the new fence, only projection into the ground. Are we to replace the old fence with posts and wire similar dimensions to the existing or is a specific requirement not called out in the drawings? What are the dimensions of the 9-gauge wire fabric and height of the post that is requested for this scope?

See detail A/C4. Regular post lengths are 7’-6” and bury 2’-6” into the ground. Total fence height is 5’.

7.

Should the wood used to be treated or untreated?

Post will be treated in accordance with AWPA U1 see Section 2.2.3.3 Wood Posts.

8.

Do you want footers for the gate posts? And if so do you want a hole dug and concrete poured for the footer, or just pound it into the ground?

No foundation will be provided. All posts will be pound into the ground including the gate posts.

File details come from the government source that posted it. Updated .