This is Amendment 0002 to Solicitation 140P6326Q0009, issued by the National Park Service (NPS), Midwest Region (MWR) at Nekota MABO in Rapid City, South Dakota. The amendment is effective February 26, 2026, and was issued by contract specialist Joseph Kirk.

The amendment makes three substantive changes to the solicitation: (1) provides an amendment to the specifications document regarding asphalt work quality control procedures and acceptance criteria, with reference to an attached specification amendment; (2) extends the solicitation close date from March 27, 2026, to April 2, 2026, with submissions due at 10:00 AM; and (3) provides government responses to three contractor questions. Regarding project execution constraints, the government notes that site access limitations depend on whether the Rec.Gov system becomes operational in late May or early June for collecting tour fees, which could impact the concrete sidewalk area and Launch Control Building access during tours. For progress payment requests, contractors must submit a Schedule of Value, Certified Payrolls, and Invoice for approval. Offerors must acknowledge receipt of this amendment prior to the new closing date and time by completing the form, returning copies, or submitting a separate letter or electronic communication referencing the solicitation and amendment numbers. Failure to acknowledge receipt by the designated deadline may result in offer rejection.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: is not is required copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7.ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

PAGESOF

Contractor

The hour and date specified for receipt of Offers to sign this document and return

Joseph Kirk

See continuation page

NPS, MWR - NEKOTA MABO

DOI, NPS, MWR - NEKOTA MABO

820 Columbus St Rapid City SD 57701

PMN

140P6326Q0009

02/26/2026

02/26/2026

1 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140P6326Q0009/0002

The purpose of amendment two is:

1. provide an amendment to the Specifications.

See attached SPEC amendment.

2. Extend the solicitation close date from

March 27, 2026, to April 2, 2026, due at

10:00AM.

3. Provide Answers to 2 questions received.

Question 1:

For the asphalt work, are there any specific quality control procedures or acceptance criteria required by the Government (such as density testing, field verification, or reporting requirements)?

Government Response:

See Specification Amendment document.

Question 2:

Regarding project execution, are there any known constraints related to site access, phasing, or coordination with ongoing operations that should be considered during scheduling?

Government Response:

#2, the only constraints related to the site will depend on if we go operational with

Rec.Gov to start collecting tour fees and tours starting back up. The forecast for that is late May, or early June. The tours would utilize the concrete sidewalk from the upper parking lot are to the main compound gate of

Delta-01 Launch Control Facility. The tours (a group of 6) would enter the gate and stay along the first part of the Launch Control Building to enter through the Elevator Room door and into the structure. That could be an impact, it all depends on if we have enough staff to conduct tours this summer at all.

Question 3:

Please confirm if there are any specific submittals or documentation expected prior to

Continued...

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140P6326Q0009/0002 or during construction that are critical for approval or progress payment.

Government Response:

When requesting progress payments, the following will be needed before approval:

Schedule of Value, Certified Payrolls, Invoice.

End of Changes

Questions Regarding this amendment contact contract specialist Joseph Kirk, joseph_kirk@ios.doi.gov, 605.574.0510.

Amendment of solicitation/modification of contract
Contract ID code
Amendment/modification number
Effective date
Requisition/purchase requisition number
Project number
Issued by
Code
Administered by
Code
Name and address of contractor
Code
Facility code
Amendment of solicitation number
Dated
Modification of contract/order number
Dated
This item only applies to amendments of solicitations
Accounting and appropriation data
This item applies only to modifications of contracts/orders.
This change order is issued pursuant to:
The above numbered contract/order is modified to reflect the administrative changes
This supplemental agreement is entered into pursuant to authority of:
Other
Important:
Description of amendment/modification
Name and title of signer
Contractor/offeror
Date signed
Name and title of contracting officer
Signature of Contracting Officer
Date signed
Previous edition unusable
Standard form 30 (rev. 11/2016)
Continuation sheet
Reference Number
Name of Offeror or Contractor
OPTIONAL FORM 336 (4-86))

Sponsored by GSA FAR (48 CFR) 53.110

File details come from the government source that posted it. Updated .