Amd_0005_Atch_1_Questions_and_Answers_7_30_25_0005.pdf
PDF 130 KB Posted
- Attached to
- WICA Replace HVAC system in Elevator Bldg.
- Solicitation number
- 140P6325Q0010
About this file
This document is a Questions and Answers (Q&A) addendum for Solicitation 140P6325Q0010, a federal contract opportunity to replace the HVAC system in the Elevator Building at Wind Cave National Park. The Q&A addresses multiple contractor inquiries regarding project specifications, including concrete pad requirements, power panel access, restroom facilities, fall protection, thermostat replacement, parking space usage, and equipment delivery lead times. Key clarifications include: contractors must provide their own fall protection and toilet facilities, can close adjacent parking spaces for material laydown, must replace the existing thermostat, and cannot reuse the existing housekeeping pad location. The National Park Service demonstrates flexibility regarding equipment delivery delays, indicating willingness to collaboratively adjust the 60-calendar-day performance period if manufacturers or supply chain issues are documented and formally requested in writing.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
140P6325Q0010 Wind Cave National Park-Replace HVAC System in Elevator Building
Questions and Answers Updated 7.30.25
Clarification for concrete pad:
The new heat pump unit will be installed in the same location as existing unit. Contractor may choose to use the existing concrete pad, as long as the pad meets the requirements called out in the flag notes. "Pad shall extend 6" beyond the outside dimensions of heat pump." (Sheet 4 of 4 construction drawings).
If the existing pad does not meet this requirement, the contractor will remove and dispose of the existing pad and replace in same location, a new pad meeting the requirements called out in the same flag note for a new pad "New outdoor heat pump to sit on new 6" concrete pad, pad shall extend 6" beyond the outside dimensions of heat pump." (Sheet 4 of 4 construction drawings).
Measurements of existing pard are 6" X 48" X 60" (5ft X 4 ft X 6 in).
Question 1.
We were unable to open the power panel. Will pictures be taken and posted with the amendment? Please confirm.
Government Response:
The park is currently attempting to gain access to the power panel, as the keys are missing. Once access is obtained, photos may be provided; however, the exact date is unknown, and the photos may ultimately not be available.
Question 1A:
Was there any update on being able to provide photos for the panel in the electrical room? If not, will any change found during construction be addressed via change order?
Government Response:
The government feels that this should not impact pricing as the needed information is within the specifications and drawings. If an issue occurs during construction, it can be handled through a request for information and possibly change order.
Question 2.
Are restrooms available for contractor use?
Government Response:
Per the Project Specifications, Item 3.3, Section D, Subsection 4A:
Toilets: The contractor is required to provide toilet facilities for contractor personnel. These must be sufficiently lighted and ventilated, weatherproof, sight-proof, sturdy enclosures with privacy locks, and handicap accessible if required. Coordinate with the COR for an approved location if not already indicated on the attached site plan.
Question 3.
Will the contractor be required to provide their own fall protection?
Government Response:
Yes, the contractor is responsible for providing all necessary fall protection equipment in compliance with applicable OSHA standards and project safety requirements.
Question 4.
Sheet 3, Note 1, third floor. Will contractor be replacing thermostat?
Government Response:
Yes, the thermostat shall be replaced.
Question 5.
Can the contractor reuse the existing housekeeping pad location?
Government Response:
No, the existing pad location cannot be used.
Question 6.
Confirm the transformer unit and pad is to remain?
Government Response:
Yes, the transformer is to remain.
Question 7.
Will the contractor be able to close down nearby parking spaces for equipment/material laydown and parking?
Government Response:
Yes. During the period of performance, the parking spaces adjacent to the elevator building may be closed and reserved for contractor use and material laydown, as needed. The contractor is responsible for the security and safety of any materials or items placed within the designated area. Refer to Item 3.3, Section E, Subsections 5 and 6 of the project specifications.
Question 8. 7.30.25 What is required for reclamation on the existing housekeeping pad?
• Sod, seeding, erosion blankets, etc.?
Government Response:
If using existing pad. No Reclamation.
If unit on existing pad requires different dimensions. Reclamation shall include demolition of the existing pad and associated dirt work to restore proper elevation and slope. Re-seeding will be completed by park personnel using the park’s designated seed mixture.
Question 9. Not Applicable as we are not changing the elevation of the pad. 7.30.25 Attachment 2 drawings: Flag Note 1. The proposed new location of the outdoor heat pump pad has a drastic elevation difference from the existing pad. Will the contractor be required to excavate matching grade to the existing pad?
Government Response:
The contractor will not be required to excavate to match the existing grade.
Question 10. Not Applicable 7.30.25 In response to Question 9 above, if the contractor has to excavate matching grade to the existing pad. Will the contractor be required to install a retaining wall?
Government Response:
Not Applicable
Question 11. 7.30.25 Will the National Park Service be providing the seed mixture for reclaiming disturbed areas?
Government Response:
The park will provide the seed mixture and personnel to reseed all disturbed areas at the conclusion of the contract.
Question 12.
Current lead times on equipment show delivery past the period of performance of 60 calendar days. Contingent on issuance of Notice to Proceed. Will the park/contracting work with the contractor to accommodate those lead times?
Government Response:
The Government understands that current lead times on equipment may extend beyond the 60-calendar-day period of performance. The period of performance is contingent upon the issuance of the Notice to Proceed (NTP).
If the contractor provides documentation demonstrating unavoidable manufacturer or supply chain delays, the park/contracting is willing to work collaboratively to assess the situation.
Adjustments may be considered on a case-by-case basis, such as modifying the period of performance or issuing the NTP in alignment with delivery timelines.
However, any adjustments must be formally requested in writing, justified, and approved prior to issuance of the NTP.