B09_Solicitation_Amendment_1_Attach_1_Questions_And_Answers_0001.docx

DOCX document 14 KB Posted

Attached to
MORU Rock Block Studies Federal contract opportunity
Solicitation number
140P6325Q0007
Issued by
Department of the Interior National Park Service Midwest Region

About this file

This document is a Questions and Answers addendum for the MORU Rock Block Studies solicitation (140P6325Q0007) issued by the Department of the Interior National Park Service Midwest Region. The Q&A document clarifies several key details about the rock block monitoring contract, including confirmation that the National Park Service will maintain access hardware and software, and providing guidance on mitigation plan development timelines across multiple contract years.

The Q&A addresses specific technical and procedural inquiries, notably confirming that in Year 2, the contractor will develop a Mitigation Plan for movement and water mitigation, to be submitted to and reviewed by the Contracting Officer's Representative (COR). Additionally, the document resolves a discrepancy between contract periods by instructing bidders to follow the periods outlined in the SF1449 document. The solicitation appears to be for rock block monitoring studies conducted at Mount Rushmore National Memorial, with specific requirements for developing and implementing mitigation strategies.

View the file

Other files for this federal contract opportunity

Other files attached to MORU Rock Block Studies, newest first.
File Type Posted
B09_Solicitation_Amendment_2__Attch_1_PWS_May_7__2025_0002.doc DOC document
Sol_140P6325Q0007_Amd_0002.pdf PDF
B09_Solicitation_Amendment_2_Attch_2_Price_Schedule_May_7__2025_0002.docx DOCX document
Sol_140P6325Q0007_Amd_0001.pdf PDF
Sol_140P6325Q0007.pdf PDF
B08_Solicitation_Attch_3_PWS.doc DOC document
B08_Solicitation_Attch_2_Wage_Determination.pdf PDF
B08_Solicitation_Atch_1_Price_Schedule.docx DOCX document
B08_Solicitation_Attach_4_PWS_attach_1_Photogrammetry_analysis.pptx PPTX presentation
B08_Solicitation_Attch_5_Experience_Q.xls XLS spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question
Response
1
Will Rushmore will continue to provide and maintain ropes, or will the selected Contractor provide ropes for this contractor?

Yes, The NPS will maintain the access hardware and software

2
PWS Section 5(H), I am understanding that within Year 2, we are to include labor costs for developing a Mitigation Plan for movement. This Plan will be submitted to COR, and COR's Team will select a mitigation option. We are then to include (within Year 2) labor costs for finalizing the Plan design by the end of Year 2. We are then to include (within current RFP Year 3 costs) labor costs to develop mitigation costs for the selected Plan. Is this correct?

Yes

3
Same question noted above but for Section 5(I) - Water Mitigation Plan.

Yes

4
The PWS Section 14 (Proposed Contract Periods) is different than the periods given in the SF1449 document. I am assuming we should follow SF1449?

Follow the SF1449.