B09_Solicitation_Amendments_Amd_1_Atch_1_Q_A_Document_0001.pdf

PDF 212 KB Posted

Attached to
REPLACE DISPATCH GENERATOR Federal contract opportunity
Solicitation number
140P6321Q0059
Issued by
Department of the Interior National Park Service Midwest Region

View the file

Other files for this federal contract opportunity

Other files attached to REPLACE DISPATCH GENERATOR, newest first.
File Type Posted
Sol_140P6321Q0059_Amd_0003.pdf PDF
B09_Solicitation_Amendments_Amd_2_Atch_1_Q_A_Document_No__2_0002.pdf PDF
Sol_140P6321Q0059_Amd_0002.pdf PDF
Sol_140P6321Q0059_Amd_0001.pdf PDF
Attch_3_DOL_Wage_Determination_15-5367.txt TXT text file
Attch_2_Images_of_Existing_Equipment.pdf PDF
Attch_1_Specifications.pdf PDF
Sol_140P6321Q0059.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions & Answers Replace Generator

Mount Rushmore National Memorial Solicitation No. 140P6321Q0059 – Amendment 1

The following questions were generated during the solicitation phase. The questions and responses are incorporated into the solicitation and resulting contract.

QUESTIONS & ANSWERS:

Ref Question Response 1 Does the current ATS have a 2-wire start circuit? The ATS is a two wire start circuit plus a engine exerciser capability.

This transfer switch provides for a once a week 20-minute exercise period. The current generator utilizes the exercise option per ATS specifications. See identity plate image below.

2 Can the existing high discharge stack be used (with modifications as needed)?

Yes.

ATS Identity Plate