This document contains questions and answers related to solicitation number 140P6321B0015 to replace the North Unit boundary fence at Theodore Roosevelt National Park. All disturbed areas around the replacement fence must be seeded using the ND 13 seed mix standard. Woven wire fencing must be used for any areas with a flat grade, while barbed wire fencing can be installed where there are significant changes in grade elevation, such as shown in technical drawing G8.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amd_4_Atch_1_Scope_of_Work_Specifications_Rev_08_06_21_0004.pdf | ||
| Amd_4_Atch_3_Seeding_Guidance_0004.pdf | ||
| Sol_140P6321B0015_Amd_0004.pdf | ||
| Sol_140P6321B0015_Amd_0003.pdf | ||
| Amd_2_Atch_1_Questions_Answered_Seeding_Guidelines_0002.pdf | ||
| Sol_140P6321B0015_Amd_0002.pdf | ||
| Sol_140P6321B0015_Amd_0001.pdf | ||
| Amd_1_Atch_1_Government_Furnished_Property_0001.pdf | ||
| B08_Solicitation_Atch_2_Drawings.pdf | ||
| B08_Solicitation_Atch_7_Statement_and_Acknowledgement_SF_1413.pdf | ||
| Sol_140P6321B0015.pdf | ||
| B08_Solicitation_Atch_4_RFI_Form.docx | DOCX document | |
| B08_Solicitation_Atch_3_Wage_Determination.pdf | ||
| B08_Solicitation_Atch_1_Scope_of_Work_Specifications.pdf | ||
| B08_Solicitation_Atch_8_DI-137_Release_of_Claims.pdf | ||
| B08_Solicitation_Atch_6_Payroll_Form_DOL_WH_347_7_14_06.pdf | ||
| B08_Solicitation_Atch_5_Submittal_Form_CM16.doc | DOC document |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions & Answers Replace North Unit Boundary Fence Theodore Roosevelt National Park
Solicitation No. 140P6321B0015 – Amendment 4
The following questions were generated during the solicitation phase. The questions and responses are incorporated into the solicitation and resulting contract.
QUESTIONS & ANSWERS:
Ref Question Response 1 Are all disturbed areas required to be seeded? Is the
ND 13 seed mix to be used?
Yes. All disturbed areas must be seeded. The seed guidelines are attached.
2 In cove where fence is inaccessible with equipment, the existing fence has barbed wire. Is the barbed wire fence in these areas to be replaced with similar barbed wire fence?
Woven wire fence must be used along any areas that have a flat grade. Barbed wire fence will be used in areas where there is a significant and/or abrupt transition of grade elevation. Reference technical drawings sub-sheet G8 for example of barbed wire fence design and transition.