Sol_140P6223R0001_Amd_0003.pdf

PDF 129 KB Posted

Attached to
Construct Visitor Contact Station at Ozark NSR Federal contract opportunity
Solicitation number
140P6223R0001
Issued by
Department of the Interior National Park Service Midwest Region

About this file

This document is an amendment to a solicitation for the construction of a visitor contact station at Ozark National Scenic Riverways in Missouri. The amendment provides responses to questions from offerors, as well as the National Park Service cabling standards that are to be followed. Offerors are reminded to sign and submit all amendments with their proposals. The construction project has an estimated price range between $250,000 and $500,000. It is set aside for small businesses with average annual receipts less than $45 million. Proposals are due by email to the contracting officer by the date specified. The successful offeror will be responsible for installing new utility connections outside of the existing slab, as well as providing a new propane line and 240-amp electrical service from the meter to the building.

View the file

Other files for this federal contract opportunity

Other files attached to Construct Visitor Contact Station at Ozark NSR, newest first.
File Type Posted
Attachment10-NPSCablingStandard_0003.pdf PDF
Sol_140P6223R0001_Amd_0002.pdf PDF
Attachment09-RevisedSheet_A1_0002.pdf PDF
Attachment08-DuctlessSplitSystem_0002.pdf PDF
Sol_140P6223R0001_Amd_0001.pdf PDF
Attachment04-WageDetermination-MO20220023.pdf PDF
Sol_140P6223R0001.pdf PDF
Attachment02-Specifications.pdf PDF
Attachment03-Drawings.pdf PDF
Attachment07-PastPerformance.docx DOCX document
Attachment06-PastExperience.docx DOCX document
Attachment05-LimitationsOnSubcontracting.xlsx XLSX spreadsheet
Construction_Contract_Administration.docx DOCX document
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140P6223R0001 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

PMM

Omaha NE 68102 601 Riverfront Drive DOI, NPS, MWR - Missouri MABO NPS, MWR - Missouri MABO

03/13/20230003

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

03/13/2023

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

OZAR Construct Round Springs Visitor Contact Station

The purpose of amendment three is to

1. Provide a second set of questions received and the government responses to those questions. See page 3 for questions and responses.

2. Provide the NPS Cabling Standards. See attachment 10.

Contractors are reminded that they must sign and submit all amendments with their proposal.

All other terms and conditions remain the same.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Cecilia Mitchell

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140P6223R0001/0003

All proposals must be submitted by email to cecilia_mitchell@nps.gov.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

140P6223R0001 Amendment 03

Q&A

Question 1:

Does the access cover for the water and sewer connections stay or do you want the pit backfilled and concrete poured?

Response 1:

The contractor shall provide and install new connections. They need to be made outside of existing slab, clean out installed at connection and then pit filled and concrete poured.

Question 2:

Is the current propane line being hooked back up or do we need to provide a new line?

Response 2:

Contractor shall provide a new line installed from tank to building. This shall be stubbed up and available just outside of the building for the park to connect to in the future.

Question 3:

Is the current internet cables and jacks just required in the building or do we need to establish a mainline connection to the house?

Response 3:

Refer to the Amended sheet A1 under General Electrical notes. Provide 2 data drops in each office and 2 in the multipurpose space. Coordinate placement with contracting officer’s representative (COR) on site.

Also provide 2 data drops in the Front Room (100)

All cabling shall be run to a single location within the building. Coordinate the location selected with the COR on site.

In addition, provide a telephone jack in each Office (103, 104), the Multipurpose room (101), and the Front Room (100). Route telephone line back to the same location as the data cabling.

All cabling shall be installed per the NPS cabling standards. See attachment 10 for NPS cabling standards.

Question 4:

What is the amperage of the current pedestal? Are we responsible for the connection from that disconnect to the new building? Do we need to run new feeder line if it isn’t sized properly?

Response 4:

The contractor shall provide and install new entrance wire from the meter to the building. New service shall be 240 amps. Contractor shall coordinate the installation of a new meter and box with Howell Oregon as the electric utility provider.

File details come from the government source that posted it. Updated .