B09_Amd_02_Bidder_Q_A_Corrections_0002.pdf
PDF 778 KB Posted
- Attached to
- Repair HVAC Pump Hangers Isolation Pads - Amd 2
- Solicitation number
- 140P6223Q0018
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P6223Q0018_Amd_0002.pdf | ||
| Sol_140P6223Q0018_Amd_0001.pdf | ||
| B09_Amd_01_Bidder_Q_A___Photo_0001.pdf | ||
| Sol_140P6223Q0018.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT-2
140P6223Q0018 – JEFF – HVAC Requirement
SOW & Site Visit Questions & GOV Responses
We made site visit, but would like to clarify the following:
1. That the acceptable product NPS would like for the pipe cradle isolation padding between pipe and support brackets shown in SOW are:
Cooper/B-Line- Fig. B3380 thru B3384 Pipe Shield- A1000, A2000 Erico- Model 124, 127.
1. GOV Response: No, PIPE HANGERS AND SUPPORTS
A. All pipe hangers, clamps, and supports shall conform to Manufacturers Standardization Society MSS-SP-69.
B. Oversize all hangers, clamps, and supports on insulated piping to allow insulation and jacket to pass through unbroken. This applies to both hot and cold pipes.
C. Ferrous hot piping 2-1/2 inches and larger shall have steel saddles tack welded to the pipe at each support at a depth not less than the specified insulation. Factory fabricated inserts may be used.
Acceptable Products:
Anvil- Fig. 160,161,162,163,164,165 Cooper/B-Line - Fig. 3160, 3161, 3162, 3163, 3164, 3165 Erlco - Model 630, 631, 632, 633, 634, 635 Nibco/Tolco - Fig. 260-1, 261-1 1/2, 262-2, 263-2 1/2, 264-3, 265-4
2. That there are 6 sets of double springs-12 total (orange inner/blue outer) that will be provided by NPS for replacement of only the rear ones on 3 pump pads not 4 as indicated in SOW 4.0, Item d. And that the 2 sets of white/grey springs were spares and not to be installed.
2. GOV Response: No, there are 8 sets of double springs (inner & outer) that will be provided by NPS for replacement of only the rear ones on 4 pump pads as indicated in SOW 4.0, Item d. Also, the Contractor will have to provide new cups for the springs, if required.
3. There are only 3 of the pipe cradle isolation padding between pipe and support brackets to be addressed, not four?
3. GOV Response: No, there are 4 of the pipe cradle isolation padding between pipe and support brackets to be addressed.