This document is a Question and Answer (Q/A) file for the LAMR - Energize Storage Building project (Solicitation Number: 140P6025Q0020) issued by the Department of the Interior National Park Service Midwest Region. The project involves installing electrical equipment in a metal storage building with approximate dimensions of 35' length, 24' width, and 12' vertical wall height. Key project requirements include the contractor providing all materials, labor, and permits, installing a Square D 150 amp breaker panel inside the building, and completing work Monday through Friday from 8:00 am to 4:00 pm. The project site has no existing power or water, with the main power grid pole located approximately 35' from the building.
The solicitation requires the contractor to be registered in SAM as a Small Business under NAICS 236220, with no additional small business set-aside requirements. No liquidated damages are associated with the project, and no scope modifications are anticipated. The National Park Service will provide site access control via a locked gate. No formal site visit is planned, and Q/A will be issued as amendments. The storage building is currently empty, and no hazardous material abatement is expected. Contractors must verify exterior square footage and material quantities, and notify the electrical distributor upon completion of electrical installation for energizing the structure.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P6025Q0020_Amd_0001.pdf | ||
| Sol_140P6025Q0020.pdf | ||
| B08_Solicitation_-_Attachment_2_-_Wage_Determination.pdf | ||
| B08_Solicitation_-_Attachment_1_-_SOW.docx | DOCX document | |
| B08_Solicitation_-_Attachment_3_-_PPQ.doc | DOC document | |
| B08_Solicitation_-_Attachment_4_-_Tech_Questionnaire.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question/Answers Date: 5/27/2025 Project: LAMR – Energize Storage Building, 140P6025Q0020
1. Are the building’s exact dimensions available? I didn’t see them provided. Dimensions are approximate within about 5% for each measurement as the building is not perfectly square and are as follows: 35' length, 24' width, walls are 12' in height vertically, and the ceiling at the centerline is 15' in height. Contractor shall verify the exterior square footage and quantity of materials needed to complete the task identified in this statement of work (SOW).
2. Is there power available on site? If so, what capacity is available? Contractor shall provide power and water needed to complete the work. No power and water at site.
3. Is the electrical service underground or overhead? Upon completion of electrical installation contractor shall notify electrical distributor for energizing structure via underground service, or per distributers advise.
4. What type of studs are used in the building? This project shall consist of installing equipment on a metal storage building. Photographs are also included in the SOW
5. Will the panel be installed inside or outside the structure? One Square D 150 amp breaker panel..... in the southeast corner of building at a height of five feet along vertical frame. Inside the building
6. Where is the AC unit planned to be located? An A/C unit is not included in this contract
7. Will the contractor or the CO be responsible for pulling permits? Contractor shall provide all material, equipment, parts and labor required to perform all of the work of this contract. That shall include permits.
8. Aside from the required minimum 3-day notice for inspections, are there any typical lead times or delays in getting inspectors on site, or are they generally punctual once scheduled? Punctual.
9. Will there be a formal bidder’s Q&A session or site conference? No formal site visit. Q/A will be issued as an amendment for all interested parties to view.
10. Are as-built drawings, specifications, or utility maps available? Photographs were included in the SOW, no utility maps are included.
11. Is hazardous material abatement anticipated? No.
12. Who is responsible for temporary utilities, laydown area, and site access control? Contractor shall provide all material, equipment, parts and labor required to perform all of the work of this contract. The National Park Service will provide access control via a locked gate.
13. How close are the required utilities to the storage building? Main power grid pole is approximately 35' from the building.
14. Is weekend work permitted? All work shall be performed Monday through Friday from 8:00 am until 4:00 pm. No work shall be performed on weekends or federal holidays without prior approval.
15. Are there any liquidated damages tied to schedule delays? No liquidated damages.
16. Are any scope modifications anticipated during the project? No.
17. Beyond what’s listed in SAM or the RFQ, are there additional small business goals or set-aside requirements? No.
18. What documentation is required to confirm small business status? Contractor is required to complete the provisions included in the solicitation and also must be registered in SAM as a Small Business under NAICS 236220.
19. If not selected as the prime contractor, is there an opportunity to support the project as a subcontractor? That is not up to the National Park Service.
20. Is the storage building empty? Yes