Question_and_Answer_for_RFP_5522R0007_0001.pdf
PDF 157 KB Posted
- Attached to
- SERVICE 8 HVAC VAV BOXES - PAC Federal contract opportunity
- Solicitation number
- 140P5522R0007
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sign_in_Sheet_from_Site_visit_July_20__2022_0001.pdf | ||
| Sol_140P5522R0007_Amd_0001.pdf | ||
| Atch_2_Specifications.pdf | ||
| Sol_140P5522R0007.pdf | ||
| Notice_to_Prospective_Offerors.pdf | ||
| Atch_3_VAV_UNIT_SELECTIONS.pdf | ||
| Atch_5_PP_Questionnaire.pdf | ||
| Atch_4_Wage_Determinations.pdf | ||
| Atch_1_Drawings.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
pg. 1
Responses to Questions for RFP 140P5522R0007
HVAC VAV Boxes
1. The Specifications, 01-91-14 1.3 under Commissioning Team, calls out a Contractor’s
Commissioning Representative (CCxR). Please confirm the CCxR shall be provided by the
Contractor and shall be Certified in Commissioning?
ANSWER: Yes
2. Contractor Quality Control Supervisor (CQC). Can this person also have other responsibilities on the project such as Superintendent?
ANSWER: Yes
3. In the Specifications, 23 05 93 “Testing, Adjusting and Balancing for HVAC” part 3 “General
Requirements” item 3.07, “Commissioning” it mentions a Commissioning Authority several times. Please confirm the Commissioning Authority is provided by the Government.
ANSWER: No, the commissioning authority shall be provided by the contractor.
4. In the Specifications, 23 05 93 “Testing, Adjusting and Balancing for HVAC” part 3 “General
Requirements” item 3.08 “Scope” lists out several items that are not being addresses under the
Scope of Work such as fire pumps, plumbing pumps, packaged units, rooftop units, CRAC units...etc. Please confirm if all these items need to be included in the TAB for this project.
ANSWER: No, Just the VAV Boxes, hot water pumps, boiler, and air handler.
5. In the Specifications, 23 05 93 “Testing, Adjusting and Balancing for HVAC” part 3 “General
Requirements” item 3.08 “Scope” item number 9 and Additive #1 cannot be done because there is not enough information on the drawings to perform balancing of the air grills. Additional information would be needed to perform this scope. Please confirm this item will be removed from the requirements.
ANSWER: See Attachment #1 – Drawings and Part B – Price Schedule of the RFP
6. Please confirm that a Tax-Exempt certificate will be provided by the Government on this project.
ANSWER: No, a tax-exempt certificate will not be provided.
7. Please confirm all work will be accomplished during regular working hours.
ANSWER: Yes, all work will be done during regular business working hours:
Monday-Friday 8:00am – 4:00 pm