Questions_and_Answers_0001.pdf

PDF 36 KB Posted

Attached to
REPLACE BACKFLOW PREVENTER ON LIGHTHOUSE ROAD AT C Federal contract opportunity
Solicitation number
140P5426R0016
Issued by
Department of the Interior National Park Service Southeast Region

About this file

This is a Questions and Answers document for federal contract solicitation 140P5426R0016 issued by Cape Hatteras National Seashore for replacing the backflow preventor on Lighthouse Road.

The document addresses technical specifications and coordination requirements for the backflow prevention system replacement project. Key technical details include: the piping type outside the vault must be DIP (ductile iron pipe); the existing backflow loop is operational; the new backflow system and water meter must incorporate a bypass loop; and all plumbing installation must comply with local and state regulations including the International Building Code, North Carolina Building Code, Dare County Water Department specifications, American Waterworks Association (AWWA) standards, and American Society of Sanitary Engineering (ASSE) requirements. Specific requirements include proper spacing of pipe fittings in accordance with Dare County Water Department and AWWA specifications, concrete thrust blocks approximately one cubic foot around underground 90-degree bends, and proper elbow turning radius and depth of burial. The document clarifies that Dare County Water Department will provide and install the new meter and smaller bypass meter, requiring contractor coordination immediately after award. Similarly, Cape Hatteras Electric will provide the electrical meter and service to the new meter/panel box for the enclosure heater circuit, also requiring direct contractor coordination immediately after award.

View the file

Other files for this federal contract opportunity

Other files attached to REPLACE BACKFLOW PREVENTER ON LIGHTHOUSE ROAD AT C, newest first.
File Type Posted
Sol_140P5426R0016_Amd_0001.pdf PDF
Sol_140P5426R0016.pdf PDF
Wage_Determination.pdf PDF
Past_Performance_Questionnaire.pdf PDF
Statement_of_Work.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Cape Hatteras National Seashore

Replace the Backflow Preventor on Lighthouse Road

Solicitation 140P5426R0016

Questions and Answers

1. Piping type outside of vault? DIP/PVC

DIP

2. Is the existing backflow loop operational?

YES

3. Will the new backflow system/water meter need to have the bypass loop incorporated into it?

YES

4. Dare County water dept be providing and installing new meter and including a smaller bypass meter?

YES - However, you will need to coordinate this effort directly with them, immediately after award.

5. Any required spacing of pipe fitting direction change before or after meter? Old rule of thumb is 10X Pipe size for any 90’s/45’s etc.

Yes, All installation of plumbing for this water line must be in accordance with all local (county) and state regulations to include International Building Code/North Carolina Building Code, North Carolina Department of Environment Quality Code/Requirements, Dare County Water Department Code/Requirements/Specifications, American Waterworks Association (AWWA), and American Society of Sanitary Engineering (ASSE). Elbows, fittings, and all other materials are included to meet Dare County Water Department and AWWA specifications for size, location, elbow turning radius, thrust blocks, depth of burial, etc. Provide concrete thrust blocks approximately 1 cubic ft around underground 90-degree bends below ground

Option 1

6. Will Cape Hatteras Electric provide service and meter? We would install as noted backboard mounting surface with a new meter base/breaker panel to incorporate a single circuit for the encloser heater. Service provider to energize new meter /panel box incoming power or is left to the contractor to provide service tap? Generally, service provider will provide service to new meter.

Yes, Cape Hatteras Electric will provide the meter and service to the new meter/panel box. However, you will need to coordinate that effort directly with them, immediately after award.