This Statement of Work (SOW) details a project for the National Park Service to remove underground fuel storage tanks at the Gator Park Airboat Concessioner Site in Everglades National Park. The project involves abandoning or removing three underground storage tanks (750, 1500, and 2000 gallon capacities) located beneath the restaurant's overhang, with critical urgency due to buoyant uplift forces from rising groundwater levels associated with the Comprehensive Everglades Restoration Plan.
The required services include conducting a tank closure assessment, preparing and submitting documentation to the Florida Department of Environmental Protection, removing tank portions or fully excavating the tanks, performing soil and groundwater monitoring, disposing of any contaminated materials, backfilling with clean fill, and restoring the site's asphalt and concrete areas. The work is to be completed within 60 days after the Contracting Officer issues a notice to proceed, with the project located at 24050 SW 8th St, Miami, FL 33194. Special considerations include environmental compliance, protecting endangered species in the area, and adhering to strict safety and inspection protocols throughout the project.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW)
Remove Underground Fuel Storage Tank - Gator Park Airboat Concessioner Site Statement of Work EVER #349896 Page 1
EVERGLADES NATIONAL PARK
Remove Underground Fuel Storage Tank - Gator Park Airboat Concessioner Site
EVER PMIS #349896
NATIONAL PARK SERVICE
SOUTHEAST REGION
August 19, 2025
EVER #349896 Page 2
1. PARK INTRODUCTION
2. PROJECT INTRODUCTION AND OVERVIEW
3. REQUIRED SERVICES
4. SPECIAL CONTRACTOR RESPONSIBILITIES
5. GOVERNMENT FURNISHED PROPERTY, MATERIALS & SUPPLIES
6. WORKING HOURS
7. PERIOD OF PERFORMANCE
8. SAFETY & ENVIRONMENTAL COMPLIANCE
9. QUALITY ASSURANCE
10. MOTOR VEHICLE & TRAFFIC REGULATIONS
11. EMPLOYEE BADGES/PARKING
12. REPLACEMENT OF CONTRACTOR EMPLOYEE FOR SECURITY REASONS
13. NON-PAYMENT FOR ADDITIONAL WORK
14. CONFLICT OF INTEREST
15. CONTRACTOR’S PROPOSAL PACKAGE REQUIREMENTS
16. SUBMITTAL REQUIREMENTS LIST (POST-AWARD)
17. INSPECTION
18. ATTACHMENTS
Acronyms CERP Comprehensive Everglades Restoration Plan CLR Cultural Landscape Report CO Contracting Officer COR Contracting Officer’s Representative CQC Contractor Quality Control EVER Everglades National Park FDEP Florida Department of Environmental Protection HSR Historic Structure Reports NPS National Park Service PE Project Engineer PM Project Manager PMIS Project Management Information System RFP Request for Proposal SOW Statement of Work UST Underground Storage Tank
EVER #349896 Page 3
Remove Underground Fuel Storage Tank - Gator Park Airboat Concessioner Site
1. PARK INTRODUCTION
With the support of many early conservationists, scientists, and other advocates, Everglades National Park was established in 1947 to conserve the natural landscape and prevent further degradation of its land, plants, and animals. Although the captivation of the Everglades has mostly stemmed from its unique ecosystem, an alluring human story of the Everglades is deeply interwoven with its endless marshes, dense mangroves, towering palms, alligator holes, and tropical fauna. Various groups and people navigated through and wrestled with the watery landscape to make it home, and even to exploit its natural wonder at times. On these lands you can discover more about the Native Americans that existed and thrived; the agricultural development and drainage of the Everglades; the people and groups who advocated for the conservation of the area; the Everglades’ role in United States War efforts;
the preservation and restoration work that continues today; and much more.
2. PROJECT INTRODUCTION AND OVERVIEW
This project involves the abandonment or removal of 3 underground storage tanks (USTs) of sizes 750, 1500, and 2000 gallon, located underneath the overhang of the restaurant at Gator Park, an airboat concessions site within Everglades National Park. The work includes identifying, documenting, and closure of the tanks, conducting environmental testing if needed, and restoring the site to match existing conditions. This effort is critical due to the buoyant uplift forces associated with rising groundwater levels, influenced by the Comprehensive Everglades Restoration Plan (CERP), which are currently pushing the tanks upward.
3. REQUIRED SERVICES
The Contractor shall provide all labor, materials, tools, and equipment necessary to perform the following:
1. Conduct a tank closure assessment in accordance with State requirements.
2. Prepare and submit registration and closure documentation to the Florida Department of
Environmental Protection (FDEP).
3. Depending on State requirements, execute one of the following:
a. Remove tank top portions protruding from asphalt and ensure flotation force is not impacting the tanks. Abandon tanks in place.
b. Excavate and remove the USTs with no impact on the building structure and overhang.
4. Perform any soil and groundwater monitoring that may be required by the State.
5. Transport and dispose of contaminated soil and groundwater if identified.
6. Backfill excavation with clean fill material from a local quarry.
7. Restore the old fuel island with concrete and resurface asphalt areas disturbed during excavation.
EVER #349896 Page 4
8. Submit all closure and environmental documentation to the National Park Service and relevant regulatory agencies.
The tank is situated at Gator Park located at:
24050 SW 8th St Miami, FL 33194
4. SPECIAL CONTRACTOR RESPONSIBILITIES
• An on-site pre-construction meeting is required prior to mobilizing to execute the project requirements. Contractor shall initiate meeting invitation with the Contracting Officer’s Representative (COR) at least 7-days in advance. Coordination with the Concessioner will be required for airboat operation to remain open during construction.
• The contractor shall initiate and support bi-weekly meetings in the field with the COR and other key stakeholders to discuss project schedule and field activity coordination to ensure key milestones are being communicated; the goal of this meeting is to ensure National Park Service (NPS) personnel are available to support when required. At a minimum, the site Superintendent shall be in attendance for the contractor. The COR will determine required NPS personnel attendance requirements.
• Protect other elements and finishes of the existing infrastructure from damage during the execution of this SOW. Damage to property resulting from the execution of this contract work shall be corrected at the Contractor’s expense.
• Adhere to stipulations imposed by Everglades National Park Compliance office.
• Submittals are required for this contract; contractor shall refer to Section 16 -
SUBMITTAL REQUIREMENTS LIST for details.
• Use of Site: Limit use of the premises to the area immediately adjacent to the work site.
Do not disturb portions of the site beyond the work area.
• Preservation of Natural Features: Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
• Preservation of Cultural Resources: No known archeological resources are in this work area. If previously unknown archeological resources are discovered during the work of this project, the Contractor will immediately stop work at the discovery and notify the Contracting Officer. An equitable adjustment will be made in accordance with the Changes clause of the contract if necessary.
• Start of Work Notification: At least two weeks prior to the start of on-site work, the Contractor shall notify the Contracting Officer of the intended start date. This will allow government personnel to conduct a final review of the work site for any resource issues prior to the start of construction.
• Threatened and Endangered Species: The following threatened or endangered species could be encountered in the project area: Wood Storks, Eastern Indigo Snakes, Bonneted Bats, Florida Panthers, and American Crocodiles.
EVER #349896 Page 5
• All sightings of these species shall be reported to the Contracting Officer. When an endangered species is present or observed on the work site, work shall be postponed until the individuals leave the area.
• Non-native species: To prevent the spread of non-native species into the park, the Contractor shall do the following:
1. Construction equipment brought to the site shall be cleaned of any foreign material which could contain non-native plants, seeds, animals, or noxious weeks.
2. All materials (including fill dirt and aggregates) shall be free of non-native invasive plants and animals, and noxious weeds.
• Install silt fence downhill from all earth disturbing activities to prevent runoff.
• Install necessary fence, barricade, or otherwise to block off the immediate work area to prevent unauthorized entry by visitors or NPS staff.
5. GOVERNMENT FURNISHED PROPERTY, MATERIALS & SUPPLIES
The are no government furnished property, materials, or supplies associated with this project.
6. WORKING HOURS
Contractor shall complete on-site work during normal business hours of 7:00 am to 5:00 pm, Monday through Thursday, excluding Federal holidays. Contractor shall coordinate specific on-site work schedule with the Contracting Officer (CO) and Contracting Officer Representative (COR) via the approved project schedule. While on site, the COR may be reached by mobile phone during normal business hours. Any requests to work outside of normal business hours shall be date specific and shall be pre-approved by both the CO and
COR.
7. PERIOD OF PERFORMANCE
Work shall be completed within 60 days after CO issues notice to proceed. Additional time may be granted as needed for completion of testing and monitoring if required.
8. SAFETY & ENVIRONMENTAL COMPLIANCE
• Contractor shall develop a Hazard Analysis & Safety Plan for the project and assign a safety officer to monitor and enforce it. Refer to the Submittal Section of this document for additional details.
• Personnel shall wear appropriate personal protective equipment (PPE). PPE shall meet requirements of NIOSH and ANSI.
• Contractor shall comply with pertinent provisions of the Occupational Safety and Health Act (OSHA), and state, local, safety, laws.
• Contractor shall comply with pertinent Environmental Protection Agency laws and regulations.
• The Park safety officer shall have the authority to issue restraint, or a stop work order to the contractor when violations or unsafe acts are present and threaten Government and contractor employees or damage to Government property.
EVER #349896 Page 6
• Contractor shall immediately report to the CO, COR, and Park Safety Officer all accidents resulting in employee injury or death or damage to property while performing this contract.
9. QUALITY ASSURANCE
The Contractor shall provide daily reports of construction activity. The form of the report is up to the Contractor, but the report shall include the following information:
• Date
• Project Title and Contract Number
• Contractor’s name and On-site Superintendent’s name
• General description of weather and ground conditions
• Number of employees (including sub-contractors) working on-site. Employees shall be listed by job categories.
• List of equipment working on-site.
• Description of work performed.
• Any issues arising including disputes, unforeseen circumstances, differing site conditions, delays, accidents, etc.
• Reports shall be e-mailed to the Contracting Officer on a weekly basis.
10. MOTOR VEHICLE & TRAFFIC REGULATIONS
Contractor employees operating motor vehicles shall possess a valid driver's license. Driver and vehicle permits, licenses, registrations and proof of insurance shall be maintained in the vehicle at all times and made available upon request. Contractor employees shall comply with federal vehicle motor law requiring seat belts be worn at all times. Contractor employees shall adhere to the posted speed limits.
11. EMPLOYEE BADGES/PARKING
All Contractor employees shall comply with parking procedures published for the Park.
Contractor employees shall return any Park issued personal or vehicle identification badges immediately upon termination of employment or completion of this contract.
12. REPLACEMENT OF CONTRACTOR EMPLOYEE FOR SECURITY REASONS
The Government retains the right to request removal of the Contractor’s employee(s), regardless of prior clearances.
13. NON-PAYMENT FOR ADDITIONAL WORK
Any additional Contractor performed services not specified in contract, either at its own volition or at the request of an individual other than a warranted CO, shall be performed at the financial risk of the Contractor. Only a warranted CO is authorized to bind the Government to a change in specifications, contract terms, or conditions.
EVER #349896 Page 7
14. CONFLICT OF INTEREST
Contractor shall not employ off-duty COR’s or other Government employees if such employment would create a conflict of interest (COI) or be contrary to the policies contained in COI directives.
15. CONTRACTOR’S PROPOSAL PACKAGE REQUIREMENTS
The following deliverables are required to be submitted with offer in response to this SOW.
• Total Cost for the Project Proposal
• Price breakdown of the Project Proposal as specified in Section 3, of this document.
• Any additional FAR requirements as specified by the CO (ie: Bonds, Insurances, etc.)
16. SUBMITTAL REQUIREMENTS LIST (POST-AWARD)
• The contractor shall submit a post-site visit “Summary of Work” document to the COR for review at least 14 days prior to proposed construction start date. The Summary of Work document shall be a description of the work described by the Contractor which includes any activities omitted from the original scope of work contained herein.
• Contractor shall provide a list of equipment being utilized to conduct the work, and a work plan, that details means and methods for removal of the tank and for testing and monitoring if required.
• Contractor Hazard Analysis & Safety Plan and qualifications of safety person.
• Contractor’s Debris Disposal Plan: plan shall include description of the proposed procedures to transport all debris, methods to reduce potential for introduction of invasive species into the park, proposed debris receiving site, and documentation methods.
• Initial Project Schedule and monthly updates with baseline markers.
• Inclement Weather/Hurricane Plan
• Contractor’s Contract Modification Request Form and example procedures for submission and justification.
• Use Attachment A: Submittal Form for all submittals. Anticipate 14-day government review period for all submittals.
• See Attachment B: List of Required Submittals to develop official project Submittal
Register. Submittal Register is due within 10 days of Award.
17. INSPECTION
The Government will conduct periodic inspections during contract performance. Inspections shall be both random and at identified milestones during the project. These milestones shall be identified during the project schedule submittal and approval procedure. There shall also be a Final Inspection upon project completion. Final payment shall only be processed upon confirming that all noted Contractor performance deficiencies identified during the Final Inspection have been satisfactorily corrected. A release of claims shall be submitted with final invoice.
Before scheduling the final inspection, remove all tools, equipment, surplus materials, and rubbish. At time of final inspection, project shall be thoroughly clean and ready for use.
EVER #349896 Page 8
Submit written certification that project, or designated portion of project, is substantially complete, and request in writing a final inspection. Contracting Officer will perform inspection within 10 days of receipt of request. If the project is determined to be substantially complete, the Contracting Officer will prepare a list of deficiencies to be corrected before final acceptance and issue a Letter of Substantial Completion.
18. ATTACHMENTS
Attachment A: Submittal Form Attachment B: List of Required Submittals Attachment C: Staging Area
| 1. Park Introduction |
| 2. Project Introduction and Overview |
| 3. Required Services |
| 4. Special Contractor Responsibilities |
| 5. Government Furnished Property, Materials & Supplies |
| 6. Working Hours |
| 7. Period of performance |
| 8. Safety & Environmental Compliance |
| 9. QUALITY ASSURANCE |
| 10. Motor Vehicle & Traffic Regulations |
| 11. Employee Badges/Parking |
| 12. Replacement of Contractor Employee for Security Reasons |
| 13. Non-Payment for Additional Work |
| 14. Conflict of Interest |
| 15. Contractor’s Proposal Package Requirements |
| 16. Submittal Requirements List (Post-Award) |
| 17. Inspection |
| 18. AttAchments |