This Scope of Work (SOW) details a contract for clearing and maintaining waterway trails in the Gulf Coast District of Everglades National Park. The project involves clearing backcountry paddling trails to provide adequate passage for canoes and kayaks, removing and installing trail markers, and ensuring minimal environmental disruption within the Marjory Stoneman Douglass Wilderness Area.

Key requirements include using hand tools whenever possible, with limited motorized equipment allowances, carefully trimming vegetation to maintain a natural appearance, and installing wooden markers with specific technical specifications. The contractor must adhere to strict environmental protections, including guidelines for endangered species (Wood Storks, Eastern Indigo Snakes, Bonneted Bats, Florida Panthers, and American Crocodiles), prevent non-native species spread, and follow wilderness area restrictions. Additional constraints include no camping, specific work hours, hurricane preparation protocols, and comprehensive daily reporting requirements. The project demands precise GPS marker placement, careful trail clearing, and meticulous marker installation with vandal-proofing measures.

View the file

Other files for this federal contract opportunity

Other files attached to NW WATERWAY TRAIL CLEAR & MARKER REPLACE, newest first.
File Type Posted
Sol_140P5425Q0023_Amd_0001.pdf PDF
Sol_140P5425Q0023_Attach__0004-Q___A_0001.pdf PDF
Sol_140P5425Q0023.pdf PDF
Sol_140P5425Q0023_Attach__0002-Drawings.pdf PDF
Sol_140P5425Q0023_Attach__0003-WD_2015-4545_R_27.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CLEAR AND MAINTAIN WATERWAY TRAILS

PMIS 336685 SCOPE OF WORK - 1

SCOPE OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. This work consists of providing all labor, materials, and equipment to clear backcountry paddling trails and replace and install trail markers.

B. The following additional documents are incorporated as part of these specifications and are included in the work of this project:

1. NPS Drawing Number 160/191,406.

C. In case of conflict, the specs take precedence over the drawings.

D. Location: This project is for trails in Gulf Coast District of Everglades National Park. See drawings for specific trail locations. The work sites do not have a street address.

E. The work will be constructed under a single contract.

1.2 USE OF PREMISES AND WORK RESTRICTIONS

A. Use of Site:

1. Limit use of the premises to the area immediately adjacent to the work site. Do not disturb portions of the site beyond the work area.

2. Once you leave the roadway, all trails are within the Marjory Stoneman Douglass Wilderness

Area. The Contractor shall follow all wilderness use restrictions as stated in this section.

B. Portable Motors: Generators, chain saws and other portable motors are prohibited within the wilderness. For this project, an exception had been made for certain work as outlined in Part 3 of this document.

C. Preservation of Natural Features: Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

D. Preservation of Cultural Resources: No known archeological resources are in the area of this construction. If previously unknown archeological resources are discovered during the work of this project, the Contractor will immediately stop work in the area of discovery and notify the Contracting Officer. An equitable adjustment will be made in accordance with the Changes clause of the contract.

E. Start of Work Notification: At least two weeks prior to the start of on-site work, the Contractor shall notify the Contracting Officer of the intended start date. This will allow government personnel to conduct a final review the work site for any resource issues prior to the start of construction.

F. Threatened and Endangered Species: The following threatened or endangered species could be encountered in the project area: Wood Storks, Eastern Indigo Snakes, Bonneted Bats, Florida Panthers, and American Crocodiles.

1. All sightings of these species shall be reported to the Contracting Officer.

PMIS 336685 SCOPE OF WORK - 2

2. When an endangered species is present or observed on the work site, work shall be postponed until the individuals leaves the area.

3. Follow the Standard Protection Measures for the Eastern Indigo Snake published by the U.S.

Fish and Wildlife Service, August 12, 2013.

4. Follow all requirements of the Sea Turtle and Smalltooth Sawfish Construction Conditions 2006, published by the U.S. National Marine Fisheries Service (NMFS).

5. Follow all requirements of the Standard Manatee Conditions for In-Water Work 2011, published by the Florida Fish and Wildlife Conservation Commission (FWC).

6. Crocodile nesting season is from March 1 to September 15. Additional restrictions for ground disturbing activities may apply during this time frame.

G. Non-native species: To prevent the spread of non-native species into the park, all equipment brought to the site shall be cleaned of any foreign material which could contain non-native plants, seeds, animals, or noxious weeks.

H. Protection of the Public:

1. The Contractor shall inform the Contracting Officer daily of the locations of trail work so park staff and visitors can be informed and plan accordingly.

2. Notifications are to be posted at the trailhead to notify visitors of trail closures and/or trimming operations so they can plan accordingly.

I. Utilities and Services:

1. Communication:

a. Cellular phone: Much of the project area will be out of range of cellular service.

b. The Contractor’s crew shall carry a handheld marine radio capable of transmitting at 6 watts for emergency communication.

2. Water:

a. There is no fresh water available anywhere within the wilderness. Potable drinking water must be packed in. Keep all water and food away from park wildlife.

3. Fires/Cooking:

a. Fires are not permitted at ground sites within the wilderness area. All cooking, heating, etc. must be done with devices that will not produce any ash or a spark or ember that is capable of igniting vegetation. Wood, charcoal, or coal-fueled grills, stoves or devices are not permitted.

4. Waste:

a. Human Waste: Provide a portable (camping style) toilet on site for employee use.

b. Trash: Carry out all trash; do not bury, burn, or dispose of it in toilets.

J. Air Quality: Use best management practices to minimize dust. Minimize engine emissions by restricting idling time.

K. Artificial Lighting: Artificial lighting shall not be used on this project. This does not preclude using flashlights when traveling to and from the site during low light conditions.

L. Be prepared to encounter high levels of mosquitos, flies, and no-see-ums.

1. Use of personal bug repentant is allowed.

2. Spraying or fogging of insecticides is not permitted.

M. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 5:00 p.m., Monday through Friday, except when otherwise indicated. Requests for any work outside those hours, including weekends and holidays, must be submitted for approval at least 48 hours in advance.

PMIS 336685 SCOPE OF WORK - 3

N. Hurricanes: The government requires closing of operations between 48 and 72 hours of anticipated landfall of a tropical storm or hurricane. All project materials will be adequately secured or removed from the site within that time frame.

1.3 HOUSING

A. No Camping at the project sites is allowed.

1.4 ENVIRONMENTAL TRAINING

A. Prior to the start of work, the government will conduct environmental training to educate construction personnel with the intent of reducing impacts on water quality, wetland resources, wildlife, marine resources, and essential fish habitat. All the Contractor’s proposed workers shall take this training. The training will not exceed two hours.

1.5 FUEL CONTAINERS AND STORAGE

A. Gas powered equipment and portable fuel containers shall be inspected daily for leaks. Any equipment found leaking will immediately be drained and not used until repaired or replaced.

B. Portable fuel containers shall be DOT or OSHA approved safety cans. All fuel containers shall have a capacity of 5-gallons or less.

C. An 2A/10B:C fire extinguisher shall be available on-site.

1.6 QUALITY ASSURANCE

A. All trimming work on Mangroves shall be done under the direction of a State Authorized Professional Mangrove Trimmer (PMT) or other environmental professional with a certification to which the State of Florida grands PMT status.

B. The Government will obtain all permits required by the Florida DEP and the Army Corp of Engineers. The Contractor shall abide by all requirements of these permits including providing notifications to the permitting agency of work starting and or finishing.

C. The Contractor shall provide daily written reports of construction activity. The form of the report is up to the Contractor, but the report shall include the following information:

1. Date.

2. Project title and contract number.

3. Contractor’s name and on-site Superintendent’s name.

4. General description of weather and ground conditions.

5. Number of employees (including sub-contractors) working on-site. Employees shall be listed by job categories.

6. List of equipment working on-site.

7. Description of work performed.

8. Any issues arising including disputes, unforeseen circumstances, differing site conditions, delays, accidents, etc.

D. Reports shall be e-mailed to the Contracting Officer on a weekly basis.

PMIS 336685 SCOPE OF WORK - 4

1.7 PRECONSTRUCTION CONFERENCE:

A. Before start of construction, the Contracting Officer will arrange a meeting with the Contractor. The meeting agenda will include the following as a minimum: correspondence procedures, designation of responsible personnel, payments to the Contractor, park rules and regulations, construction schedule, submittals, and project closeout requirements.

1.8 SUBMITTALS

A. All submittals shall be transmitted electronically in PDF or MS Word format.

B. Pre-Construction Submittals:

1. Submit a Progress Schedule (normally in bar chart form) showing estimated starting and completion dates for each part of the work.

2. Submit a Schedule of Values showing the breakdown of the Contract amount into appropriate units of work. Include general condition costs, overhead, and profit in each part of the work and not as separate items. The Schedule of Values will form the basis for progress payments as provided for in the General Provisions.

3. Submit a safety plan per the accident prevention paragraph of this scope of work.

B. Material Submittals:

1. All material submittals shall be transmitted using National Park Service form DSC-1(CS). No action will be taken on a submittal item unless accompanied by the transmittal form.

2. Material Submittals Required:

a. Cut sheet for marker poles, hardware, reflectors and signs.

b. List of major equipment to be used including all watercraft and power tools.

3. As specified in the individual sections, forward submittals to the Contracting Officer at least 21 days before need for approval.

4. The Government will return the submittals either approved, approved with notations, or disapproved.

C. Post Construction Submittals:

1. Submit the MRA report.

2. The Contractor shall provide the following installation records.

a. The Contractor shall maintain records for markers removed, installed or repaired (sign/reflector replacement) under this contract. For each sign site, these records shall include the type of work performed, the date of installation, the size and length of the piles, the depth of penetration of each pile, and other work.

b. The Contractor must provide the Government with the coordinates in decimal degrees to five decimal points (example 30.12345°N, 81.12345°W) of all markers demolished, installed, or repaired. These positions must be accurate to two (2) meters (6 feet) resolution using DGPS or WAAS enabled with WGS-84 map datum.

c. The Contractor shall provide digital photographs of each installed major marker. Major markers include all markers/signs with 4x4 piles. Photos of the 2-inch diameter trail markers is not required. The photographs must be clear, legible, and identified with the trail and the waterway marker plan’s reference number.

1.9 ACCIDENT PREVENTION

A. Before on-site work begins, submit a written accident prevention plan containing the following:

1. Identification of personnel responsible for safety at and both corporate and project level including on-site personnel.

PMIS 336685 SCOPE OF WORK - 5

2. Emergency Response Plan including site specific emergency contact information and location of the nearest emergency room.

3. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, National Park Service personnel, and Contractor's employees.

B. The Contractor shall follow all federal, state, and local safety and health requirements

C. The Contractor shall report all accidents to the Contracting Officer as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.

1.10 CONSTRUCTION MATERIALS:

A. All materials shall be Contractor furnished from outside the park.

1.11 DISPOSAL

A. All removed marker material becomes the property of the Contractor and shall be disposed of outside the park.

B. Trimmed vegetation debris is to be scattered outside the footprint of the trail to not create debris piles, and should, to the extent practicable, be unnoticeable by the casual observer.

1.12 FIELD VERIFICATION:

A. Field verify all new and existing dimensions affecting the work of this contract before ordering products. Any discrepancies between construction drawings, construction specifications, and field conditions shall be brought to the attention of the Contracting Officer before work is to be performed. Any work that is performed without notifying the Contracting Officer will be done at the Contractor's own expense.

1.13 DELIVERY, STORAGE, AND HANDLING

A. The Contractor is responsible for all delivery, storage, and handling of all materials used. The Contractor may store materials at the NPS maintenance yard at Flamingo. The Contractor shall remain responsible for securing stored materials at NPS sites.

1.14 WARRANTIES

A. All materials utilized shall be able to withstand the elements under outdoor marine conditions for a continuous period of not less than five (5) years.

PART 2 - PRODUCTS

2.1 FIRST AID FACILITIES

A. Provide adequate facilities for the number of employees and the type of construction at the site.

PMIS 336685 SCOPE OF WORK - 6

2.2 PERSONNEL PROTECTIVE EQUIPMENT

A. Meet requirements of OSHA and ANSI.

2.3 TRAIL MARKERS

A. 4x4 Wood Piles

1. American softwood lumber standard PS-20, No 2 grade or better.

2. Moisture content: 19 percent maximum (dry) at time of manufacture.

3. Surfacing: S4S, unless otherwise specified. All dimensions are nominal.

4. Treatment: Chromated Copper Arsenate (0.8 pcf).

2.4 WOODEN SIGNS

A. Sign with routed lettering approximately ¼ inch deep.

1. Materials: ¾-inch minimum thickness. Weather Resistant Wood or High Density Urethane.

Weather resistant wood includes cedar, redwood, and teak.

2. Size: Two-inch lettering with 1-inch minimum margin between lettering and sign edges.

3. Colors: White lettering with NPS Brown (Pantone PMS 1615) background.

4. Coat sign with 3 coats of a clear spar varnish or spar urethane.

2.5 REFLECTORS

A. Retroreflectors, Three-inch minimum diameter, acrylic reflector, hermetically sealed with Center mounting hole. Shall meet Florida DOT Standard Specification 993-1.2.

2.6 HARDWARE

A. All hardware including bolts, nuts, screws, threaded rod, nails, and washers shall be 316L Stainless Steel.

2.7 MARKER PAINT

A. Alkyd primer and alkyd enamel topcoat made specifically for marine use. System shall be one coat of primer and two layers of topcoat. Topcoat to be the color White.

B. Rust-oleum Marine Coating Primer and Rust-oleum Topside Paint, Sherwin-Williams Pro-Line 45 primer and Proline 1000 topcoat, or approved equal.

PART 3 - EXECUTION

3.1 WATERCRAFT AND ACCESS METHODS

A. The Contractor shall abide by all NPS boating restrictions.

B. The trails to be cleared are intended for the use of paddling watercraft, but use of small, motorized watercraft is also permitted. Any watercraft used shall be small enough to pass through the trail

PMIS 336685 SCOPE OF WORK - 7

when cleared to the minimum dimensions. Clearing vegetation beyond the prescribed amount to facilitate access by larger watercraft is prohibited.

3.2 TOOLS

A. Hand tools (e.g., machetes, loppers, pruning saws) shall be used whenever possible except as described below.

B. The Contractor shall use his best judgement and only employ approved motorized tools as needed and allowed. Motorized tools are allowed in the following situations:

1. Battery-powered chainsaw, pole saw, and/or reciprocating saw to cut complex (i.e. branch clusters where use of a hand saw is not practicable) or branches over 2 inches.

2. Gas-powered chainsaw and/or pole saw to cut branches over 10 inches. Combustion motors are only to be run during active use.

3. Generator to charge batteries shall of the inverter type, 2,000 watts or less, and produce less than 70 decibels of noise. If possible, generator is to be staged outside of wilderness, either near the trailhead or on a motorized vessel.

4. If motorized equipment is incorporated, battery-powered tools are to be used to the greatest extent possible in order to minimize noise and the potential impacts associated with petroleum leaks and spills.

5. Chipping Hammers or Hammer Drills can be used for the installation of markers into rock.

Direct engine powered, electric with generator, pneumatic with engine driven compressor, or hydraulic with engine driven power unit can be used to drive piles, breakup rock prior to driving, or drill rock prior to driving. Combustion motors are only to be run during active use.

C. For use of battery-powered equipment, field crews are to obtain and carry as many fully charged batteries into the field as practicable to reduce or eliminate the need to run a generator which is to only be operated as necessary.

3.3 TRAIL CLEARING

A. The intent of clearing is to provide adequate space for the passage of Canoes and Kayaks. The existing trails naturally vary in width. No trimming is to be done on trail sections which already meet the trimming dimensions shown on the drawings.

B. Trim trails to the dimensions shown on the drawings.

C. Thinning cuts shall primarily be used when trimming back vegetation.

D. Trimming shall be done in a method to leave the existing vegetation as natural looking as possible.

E. Individual branches or fallen tree trunks that stick out should be trimmed back as far as practical to minimize leaving a stub sticking out from the surrounding vegetation.

3.4 MARKER LOCATION

A. The Contractor shall use global positioning system equipment (GPS) to locate marker locations from the latitude and longitude coordinates given. The GPS equipment must be accurate to two (2) meters (6 feet) resolution using DGPS or WAAS enabled with WGS-84 map datum.

PMIS 336685 SCOPE OF WORK - 8

B. The Contractor shall use his judgement to make minor field adjustment to the locations. Place the markers at logical locations for their intended purpose that are visible for paddlers on the trail.

3.5 MARKER REMOVAL, INSTALLATION AND REPLACEMENT

A. Remove existing markers by removing any remaining signage, reflectors, and hardware. The pile shall be pulled if possible. If the pile cannot be pulled, it can be cut off at the mud line.

3.6 MARKER PILE/POST INSTALLATION

A. Piles/posts for markers shall be installed within 3° of vertical. Minor adjustment (less than 3° to vertical) is allowed after pile installation; however, the Contractor is fully responsible to ensure soil has settled around the pile so that no listing will occur. Piles which cannot be straightened with a minor adjustment shall be withdrawn and reinstalled. Piles damaged, not located in the proper location, or driven out of alignment shall be withdrawn and replaced by new piles.

B. If rock is encountered, pre-punch the hole by driving and removing a steel pin or drilling.

C. Pilings shall not be connected or joined together to lengthen. The Contractor shall order piles of sufficient length and cut off excess not required.

D. Sign or pile assemblies not completed at the end of each work day must be marked and made visible to day and nighttime waterway traffic.

E. Piles shall have the top cutoff at a diagonal to provide drainage.

3.7 SIGN INSTALLATION

A. Bolt holes shall be bored 1/16” larger than the diameter of the bolt.

B. Install signs and reflectors as shown, C. All fasteners shall be vandal proofed by deforming the exposed threads using a chisel or other tool to prevent the nuts from being unthreaded.

D. The tip of the bolt shall extend through the nut more than two threads but not more than 3/8 of an inch.

3.8 SUBSTANTIAL COMPLETION AND FINAL INSPECTION

A. Before scheduling the final inspection, remove all tools, equipment, surplus materials, and rubbish.

At time of final inspection, project shall be thoroughly clean and ready for use.

B. Submit written certification that project, or designated portion of project, is substantially complete, and request in writing a final inspection. Contracting Officer will make an inspection within 10 days of receipt of request.

C. If the project is determined to be substantially complete, the Contracting Officer will prepare a list of deficiencies to be corrected before final acceptance and issue a Letter of Substantial Completion.

PMIS 336685 SCOPE OF WORK - 9

D. After all deficiencies have been corrected, a Letter of Acceptance will be issued.

END OF SECTION

PART 1 - GENERAL
1.1 SUMMARY
A. This work consists of providing all labor, materials, and equipment to clear backcountry paddling trails and replace and install trail markers.
B. The following additional documents are incorporated as part of these specifications and are included in the work of this project:
1. NPS Drawing Number 160/191,406.
C. In case of conflict, the specs take precedence over the drawings.
D. Location: This project is for trails in Gulf Coast District of Everglades National Park. See drawings for specific trail locations. The work sites do not have a street address.
E. The work will be constructed under a single contract.
1.2 USE OF PREMISES AND WORK RESTRICTIONS
A. Use of Site:
1. Limit use of the premises to the area immediately adjacent to the work site. Do not disturb portions of the site beyond the work area.
2. Once you leave the roadway, all trails are within the Marjory Stoneman Douglass Wilderness Area. The Contractor shall follow all wilderness use restrictions as stated in this section.
B. Portable Motors: Generators, chain saws and other portable motors are prohibited within the wilderness. For this project, an exception had been made for certain work as outlined in Part 3 of this document.
C. Preservation of Natural Features: Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
D. Preservation of Cultural Resources: No known archeological resources are in the area of this construction. If previously unknown archeological resources are discovered during the work of this project, the Contractor will immediately stop work in ...
E. Start of Work Notification: At least two weeks prior to the start of on-site work, the Contractor shall notify the Contracting Officer of the intended start date. This will allow government personnel to conduct a final review the work site for an...
F. Threatened and Endangered Species: The following threatened or endangered species could be encountered in the project area: Wood Storks, Eastern Indigo Snakes, Bonneted Bats, Florida Panthers, and American Crocodiles.
1. All sightings of these species shall be reported to the Contracting Officer.
2. When an endangered species is present or observed on the work site, work shall be postponed until the individuals leaves the area.
3. Follow the Standard Protection Measures for the Eastern Indigo Snake published by the U.S. Fish and Wildlife Service, August 12, 2013.
4. Follow all requirements of the Sea Turtle and Smalltooth Sawfish Construction Conditions 2006, published by the U.S. National Marine Fisheries Service (NMFS).
5. Follow all requirements of the Standard Manatee Conditions for In-Water Work 2011, published by the Florida Fish and Wildlife Conservation Commission (FWC).
6. Crocodile nesting season is from March 1 to September 15. Additional restrictions for ground disturbing activities may apply during this time frame.
G. Non-native species: To prevent the spread of non-native species into the park, all equipment brought to the site shall be cleaned of any foreign material which could contain non-native plants, seeds, animals, or noxious weeks.
H. Protection of the Public:
1. The Contractor shall inform the Contracting Officer daily of the locations of trail work so park staff and visitors can be informed and plan accordingly.
2. Notifications are to be posted at the trailhead to notify visitors of trail closures and/or trimming operations so they can plan accordingly.
I. Utilities and Services:
1. Communication:
a. Cellular phone: Much of the project area will be out of range of cellular service.
b. The Contractor’s crew shall carry a handheld marine radio capable of transmitting at 6 watts for emergency communication.
2. Water:
a. There is no fresh water available anywhere within the wilderness. Potable drinking water must be packed in. Keep all water and food away from park wildlife.
3. Fires/Cooking:
a. Fires are not permitted at ground sites within the wilderness area. All cooking, heating, etc. must be done with devices that will not produce any ash or a spark or ember that is capable of igniting vegetation. Wood, charcoal, or coal-fueled gril...
4. Waste:
a. Human Waste: Provide a portable (camping style) toilet on site for employee use.
b. Trash: Carry out all trash; do not bury, burn, or dispose of it in toilets.
J. Air Quality: Use best management practices to minimize dust. Minimize engine emissions by restricting idling time.
K. Artificial Lighting: Artificial lighting shall not be used on this project. This does not preclude using flashlights when traveling to and from the site during low light conditions.
L. Be prepared to encounter high levels of mosquitos, flies, and no-see-ums.
1. Use of personal bug repentant is allowed.
2. Spraying or fogging of insecticides is not permitted.
M. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 5:00 p.m., Monday through Friday, except when otherwise indicated. Requests for any work outside those hours, including weekends and holida...
N. Hurricanes: The government requires closing of operations between 48 and 72 hours of anticipated landfall of a tropical storm or hurricane. All project materials will be adequately secured or removed from the site within that time frame.
1.3 HOUSING
A. No Camping at the project sites is allowed.
1.4 ENVIRONMENTAL TRAINING
A. Prior to the start of work, the government will conduct environmental training to educate construction personnel with the intent of reducing impacts on water quality, wetland resources, wildlife, marine resources, and essential fish habitat. All t...
1.5 FUEL CONTAINERS AND STORAGE
A. Gas powered equipment and portable fuel containers shall be inspected daily for leaks. Any equipment found leaking will immediately be drained and not used until repaired or replaced.
B. Portable fuel containers shall be DOT or OSHA approved safety cans. All fuel containers shall have a capacity of 5-gallons or less.
C. An 2A/10B:C fire extinguisher shall be available on-site.
1.6 QUALITY ASSURANCE
A. All trimming work on Mangroves shall be done under the direction of a State Authorized Professional Mangrove Trimmer (PMT) or other environmental professional with a certification to which the State of Florida grands PMT status.
B. The Government will obtain all permits required by the Florida DEP and the Army Corp of Engineers. The Contractor shall abide by all requirements of these permits including providing notifications to the permitting agency of work starting and or f...
C. The Contractor shall provide daily written reports of construction activity. The form of the report is up to the Contractor, but the report shall include the following information:
1. Date.
2. Project title and contract number.
3. Contractor’s name and on-site Superintendent’s name.
4. General description of weather and ground conditions.
5. Number of employees (including sub-contractors) working on-site. Employees shall be listed by job categories.
6. List of equipment working on-site.
7. Description of work performed.
8. Any issues arising including disputes, unforeseen circumstances, differing site conditions, delays, accidents, etc.

D. Reports shall be e-mailed to the Contracting Officer on a weekly basis.

1.7 PRECONSTRUCTION CONFERENCE:
A. Before start of construction, the Contracting Officer will arrange a meeting with the Contractor. The meeting agenda will include the following as a minimum: correspondence procedures, designation of responsible personnel, payments to the Contrac...
1.8 SUBMITTALS
A. All submittals shall be transmitted electronically in PDF or MS Word format.
B. Pre-Construction Submittals:
1. Submit a Progress Schedule (normally in bar chart form) showing estimated starting and completion dates for each part of the work.
2. Submit a Schedule of Values showing the breakdown of the Contract amount into appropriate units of work. Include general condition costs, overhead, and profit in each part of the work and not as separate items. The Schedule of Values will form th...
3. Submit a safety plan per the accident prevention paragraph of this scope of work.
B. Material Submittals:
1. All material submittals shall be transmitted using National Park Service form DSC-1(CS). No action will be taken on a submittal item unless accompanied by the transmittal form.
2. Material Submittals Required:
a. Cut sheet for marker poles, hardware, reflectors and signs.
b. List of major equipment to be used including all watercraft and power tools.
3. As specified in the individual sections, forward submittals to the Contracting Officer at least 21 days before need for approval.
4. The Government will return the submittals either approved, approved with notations, or disapproved.
C. Post Construction Submittals:
1. Submit the MRA report.
2. The Contractor shall provide the following installation records.
a. The Contractor shall maintain records for markers removed, installed or repaired (sign/reflector replacement) under this contract. For each sign site, these records shall include the type of work performed, the date of installation, the size and l...
b. The Contractor must provide the Government with the coordinates in decimal degrees to five decimal points (example 30.12345 N, 81.12345 W) of all markers demolished, installed, or repaired. These positions must be accurate to two (2) meters (6 feet...
c. The Contractor shall provide digital photographs of each installed major marker. Major markers include all markers/signs with 4x4 piles. Photos of the 2-inch diameter trail markers is not required. The photographs must be clear, legible, and ide...
1.9 ACCIDENT PREVENTION
A. Before on-site work begins, submit a written accident prevention plan containing the following:
1. Identification of personnel responsible for safety at and both corporate and project level including on-site personnel.
2. Emergency Response Plan including site specific emergency contact information and location of the nearest emergency room.
3. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, National Park Service personnel, and Contractor's employees.
B. The Contractor shall follow all federal, state, and local safety and health requirements
C. The Contractor shall report all accidents to the Contracting Officer as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.
1.10 CONSTRUCTION MATERIALS:
A. All materials shall be Contractor furnished from outside the park.
1.11 DISPOSAL
A. All removed marker material becomes the property of the Contractor and shall be disposed of outside the park.
B. Trimmed vegetation debris is to be scattered outside the footprint of the trail to not create debris piles, and should, to the extent practicable, be unnoticeable by the casual observer.
1.12 FIELD VERIFICATION:
A. Field verify all new and existing dimensions affecting the work of this contract before ordering products. Any discrepancies between construction drawings, construction specifications, and field conditions shall be brought to the attention of the C...
1.13 DELIVERY, STORAGE, AND HANDLING
A. The Contractor is responsible for all delivery, storage, and handling of all materials used. The Contractor may store materials at the NPS maintenance yard at Flamingo. The Contractor shall remain responsible for securing stored materials at NPS ...
1.14 WARRANTIES
A. All materials utilized shall be able to withstand the elements under outdoor marine conditions for a continuous period of not less than five (5) years.
PART 2 - PRODUCTS
2.1 FIRST AID FACILITIES
A. Provide adequate facilities for the number of employees and the type of construction at the site.
2.2 PERSONNEL PROTECTIVE EQUIPMENT
A. Meet requirements of OSHA and ANSI.
2.3 TRAIL MARKERS
A. 4x4 Wood Piles
1. American softwood lumber standard PS-20, No 2 grade or better.
2. Moisture content: 19 percent maximum (dry) at time of manufacture.
3. Surfacing: S4S, unless otherwise specified. All dimensions are nominal.
4. Treatment: Chromated Copper Arsenate (0.8 pcf).
2.4 WOODEN SIGNS
A. Sign with routed lettering approximately ¼ inch deep.
1. Materials: ¾-inch minimum thickness. Weather Resistant Wood or High Density Urethane. Weather resistant wood includes cedar, redwood, and teak.
2. Size: Two-inch lettering with 1-inch minimum margin between lettering and sign edges.
3. Colors: White lettering with NPS Brown (Pantone PMS 1615) background.
4. Coat sign with 3 coats of a clear spar varnish or spar urethane.
2.5 REFLECTORS
A. Retroreflectors, Three-inch minimum diameter, acrylic reflector, hermetically sealed with Center mounting hole. Shall meet Florida DOT Standard Specification 993-1.2.
2.6 HARDWARE
A. All hardware including bolts, nuts, screws, threaded rod, nails, and washers shall be 316L Stainless Steel.
2.7 MARKER PAINT
A. Alkyd primer and alkyd enamel topcoat made specifically for marine use. System shall be one coat of primer and two layers of topcoat. Topcoat to be the color White.
B. Rust-oleum Marine Coating Primer and Rust-oleum Topside Paint, Sherwin-Williams Pro-Line 45 primer and Proline 1000 topcoat, or approved equal.
PART 3 - EXECUTION
3.1 WATERCRAFT AND ACCESS METHODS
A. The Contractor shall abide by all NPS boating restrictions.
B. The trails to be cleared are intended for the use of paddling watercraft, but use of small, motorized watercraft is also permitted. Any watercraft used shall be small enough to pass through the trail when cleared to the minimum dimensions. Cleari...
3.2 TOOLS
A. Hand tools (e.g., machetes, loppers, pruning saws) shall be used whenever possible except as described below.
B. The Contractor shall use his best judgement and only employ approved motorized tools as needed and allowed. Motorized tools are allowed in the following situations:
1. Battery-powered chainsaw, pole saw, and/or reciprocating saw to cut complex (i.e. branch clusters where use of a hand saw is not practicable) or branches over 2 inches.
2. Gas-powered chainsaw and/or pole saw to cut branches over 10 inches. Combustion motors are only to be run during active use.
3. Generator to charge batteries shall of the inverter type, 2,000 watts or less, and produce less than 70 decibels of noise. If possible, generator is to be staged outside of wilderness, either near the trailhead or on a motorized vessel.
4. If motorized equipment is incorporated, battery-powered tools are to be used to the greatest extent possible in order to minimize noise and the potential impacts associated with petroleum leaks and spills.
5. Chipping Hammers or Hammer Drills can be used for the installation of markers into rock. Direct engine powered, electric with generator, pneumatic with engine driven compressor, or hydraulic with engine driven power unit can be used to drive piles...

C. For use of battery-powered equipment, field crews are to obtain and carry as many fully charged batteries into the field as practicable to reduce or eliminate the need to run a generator which is to only be operated as necessary.

3.3 TRAIL CLEARING
A. The intent of clearing is to provide adequate space for the passage of Canoes and Kayaks. The existing trails naturally vary in width. No trimming is to be done on trail sections which already meet the trimming dimensions shown on the drawings.
B. Trim trails to the dimensions shown on the drawings.
C. Thinning cuts shall primarily be used when trimming back vegetation.
D. Trimming shall be done in a method to leave the existing vegetation as natural looking as possible.
E. Individual branches or fallen tree trunks that stick out should be trimmed back as far as practical to minimize leaving a stub sticking out from the surrounding vegetation.
3.4 MARKER LOCATION
A. The Contractor shall use global positioning system equipment (GPS) to locate marker locations from the latitude and longitude coordinates given. The GPS equipment must be accurate to two (2) meters (6 feet) resolution using DGPS or WAAS enabled wi...
B. The Contractor shall use his judgement to make minor field adjustment to the locations. Place the markers at logical locations for their intended purpose that are visible for paddlers on the trail.
3.5 MARKER REMOVAL, INSTALLATION AND REPLACEMENT
A. Remove existing markers by removing any remaining signage, reflectors, and hardware. The pile shall be pulled if possible. If the pile cannot be pulled, it can be cut off at the mud line.
3.6 MARKER PILE/POST INSTALLATION
A. Piles/posts for markers shall be installed within 3 of vertical. Minor adjustment (less than 3 to vertical) is allowed after pile installation; however, the Contractor is fully responsible to ensure soil has settled around the pile so that no li...
B. If rock is encountered, pre-punch the hole by driving and removing a steel pin or drilling.
C. Pilings shall not be connected or joined together to lengthen. The Contractor shall order piles of sufficient length and cut off excess not required.
D. Sign or pile assemblies not completed at the end of each work day must be marked and made visible to day and nighttime waterway traffic.
E. Piles shall have the top cutoff at a diagonal to provide drainage.
3.7 SIGN INSTALLATION
A. Bolt holes shall be bored 1/16” larger than the diameter of the bolt.
B. Install signs and reflectors as shown,
C. All fasteners shall be vandal proofed by deforming the exposed threads using a chisel or other tool to prevent the nuts from being unthreaded.
D. The tip of the bolt shall extend through the nut more than two threads but not more than 3/8 of an inch.
3.8 SUBSTANTIAL COMPLETION AND FINAL INSPECTION
A. Before scheduling the final inspection, remove all tools, equipment, surplus materials, and rubbish. At time of final inspection, project shall be thoroughly clean and ready for use.
B. Submit written certification that project, or designated portion of project, is substantially complete, and request in writing a final inspection. Contracting Officer will make an inspection within 10 days of receipt of request.
C. If the project is determined to be substantially complete, the Contracting Officer will prepare a list of deficiencies to be corrected before final acceptance and issue a Letter of Substantial Completion.
D. After all deficiencies have been corrected, a Letter of Acceptance will be issued.