Revised_Statement_of_Work_0001.pdf

PDF 2 MB Posted

Attached to
PAINT EXTERIOR OF DUNGENESS DORM
Solicitation number
140P5423R0002
Issued by

View the file

Other files

File Type Posted
Questions_and_Answers_Dorm_Paint_Project_0001.pdf PDF
Sol_140P5423R0002_Amd_0001.pdf PDF
SCA_Wage_Rates.pdf PDF
Dungeness_Dorm_Paint_Analysis_2022.pdf PDF
Sol_140P5423R0002.pdf PDF
Statement_of_Work.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of the Interior

NATIONAL PARK SERVICE

Cumberland Islands National Seashore 101 Wheeler St IN REPLY REFER TO: St Marys, GA 31558

October 20, 2022

STATEMENT OF WORK

Pressure Wash, Repair and Paint the Exterior Surface of two structures on Cumberland Island National Seashore

The contractor is to supply all supervision, material, and labor, to pressure wash, replace approximately 10% of the wood siding, decking, and stairs, rebuild and hang 6 window screens, replace approximately 40% of all window glazing, repair less than 25% of the existing screens and prime and paint the entire structures. There is approximately 5400 square feet of wood, lap siding, porch rafters and overhang surface, 44 - 43” x 62’’ double hung, wood windows, 6 over 6 pane, 4 – 33”x 62” double hung windows, 4 over 4 pane, 3 - 36” x 43” single hung, 3 over 3 pane, 4. exterior wood doors, 34” x 94”(2), 36”x 85”(1), and 32”x 80”(1), 3 screen doors, 34” x 94”(2) and 36” x 85”(1), approximately 2010 square feet of wood porch ceiling and decking, 1000 square feet of wood hand railing and posts. All surfaces to be painted shall be scrapped and sanded as needed. The painting will consist of one coat of latex primer to all bare spots and two (2) finish coats of high gloss, latex paint. Paint is to be a Low VOC. All work shall be done in accordance with generally accepted practices for the trade.

Contractor Responsibilities on structures:

• Pressure wash entire buildings with an environmentally friendly, high quality, exterior, siding cleaner/concentrate.

• Ensure water does not enter building while pressure washing.

• Inspect and immediately dry any water that does enter the building.

• Place painter’s tarp on ground prior to scrapping walls and soffits, to catch paint chips from being scattered around the landscape or waterway.

• Apply one coat of latex primer to bare spots and two finish coats of high gloss, latex paint. Paint will be applied with a thick nap roller and brushed. No paint sprayers are to be used.

• The exterior and interior of the doors and exterior only of windows are to be painted.

• Paint both sides of window and door screens.

• All glass panes are to be scraped of all paint and entire pane will be cleaned with glass cleaner.

Dormitory

• Pressure washes all exterior surfaces, approximately 4364 square feet. Scrape and caulk as needed.

• Prime and paint wood surfaces, approximately 4364 square feet of wood lap siding and overhang.

• Prime and paint the trim on 43 wood, double hung, 6 over 6 windows 43’’x 62’’, 4 wood, double hung, 4 over 4 windows 33” x 62”. The square footage for the windows is included with the wall total.

• Paint the 1”x 2” wood, window and door screens.

• Paint 2- 34” x 94” exterior and interior, wood doors and 1- 36” x 85” exterior and interior, wood door (to include frames). The square footage for the doors is included with the wall total.

• Paint 2- 34” x 94” exterior and interior, screen doors and 1- 36” x 85” exterior and interior, screen door.

• Clean, prime and paint porch benches, supports, railings and posts, approximately 900 square feet.

Dormitory Wash House

• Scrape loose, peeling, paint from walls, windows, doors, ceiling and decking.

• Pressure wash approximately 1036 square feet of wall, roof overhang. Scrape and caulk as needed.

• Prime all bare surfaces with 1 coat of latex primer and paint all surfaces with 2 coats of high-quality, high gloss paint.

• Paint 1 exterior, wood door and trim, 1- 32 x 80”. The square footage for the doors is included with the wall total.

• Paint all windows and trim. 1 wood, double hung, 6 over 6 window 43” x 62” and 3 wood, single hung, 3 over 3 windows 36” x 43”. The square footage for the windows is included with the wall total.

• Clean, prime and paint porch benches, supports, railings and posts, approximately 100 square feet.

Special Considerations:

• Project is located on Cumberland Island not the mainland. The distance from the mainland to the dock on the island is approximately 7 miles.

• The contractor is responsible for all transportation of equipment, materials and daily transport of personnel to and from the island.

• The contractor is responsible for island transportation from the floating dock to the work site.

Driving is only permitted from the dock to the jobsite. No driving anywhere else on the island.

• The contractor will be provided docking space on the island and possibly on the mainland if space is available for a maximum boat size of 25’. If no space is available on the mainland the contractor’s boat will have to be pulled from the water daily but can be stored at a designated park location.

• Approximate square footages for walls includes the doors, windows and trim.

• A very low pressure from a water hose will be used to wash around all doors and windows.

• Replacement material will be like in kind.

• Paint colors are: Walls- Sherwin Williams, Superpaint, Exterior Gloss Ultra, A84W1151 (Custom

L4), Trim- Sherwin Williams, Super Paint, Exterior Gloss Ultra, A84T154 (Custom 34-63721).

• Hinges and door knobs are to be removed or taped to prevent paint getting on them.

• Contractor will comply with all OSHA, Federal, State, and local regulations.

• Job site will be cleaned up at the end of each day.

• Disposal of all construction debris is the responsibility of the contractor.

• Work hours are Monday through Friday, 7am-5pm.

• No work on government holidays.

• Work on the weekend must be approved by the COR and must be requested at least 72 hours in advance.

• The area will remain open to visitors while the work of this contract is executed. Visitors are the park’s primary customers. Daily contact with visitors by the contractor is likely. As all resources and operations of the NPS are ultimately paid for by the U.S taxpayer, any visitors that the contractor comes into contact with while accomplishing this work should be considered a customer and be accorded all reasonable courtesy.