Atch_1_to_Am_1_QandAs_0001.pdf
PDF 54 KB Posted
- Attached to
- ReWire Boat Dock-Fort Matanzas NM
- Solicitation number
- 140P5423Q0025
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P5423Q0025_Amd_0001.pdf | ||
| Atch_1_SOW.pdf | ||
| Atch_2_Photos.pdf | ||
| Sol_140P5423Q0025.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
140P5423Q0025 Amendment 1 Attachment 1
Page 1 of 1 Page
Question #1: Do you have a spec for the new lights?
Answer: Preferably use Vapor Tight Fixture, 150W Max, 120V, A23 or LED equivalent. Fixture to meet or exceed set Hazardous Locations install. (3) fixtures on dock.
Question #2: How many GFCI outlets are on the dock now?
Answer: There is only one GFCI receptacle on the dock.
Question #3: What is the amperage for the boat lift?
Answer: The circuit for the boat lift is a 2P, 20A, 240V.
Question #4: How many circuits are coming to dock now from the visitors center?
Answer: Currently there are (4) circuits going out to the boat dock.
1. GFCI Receptacle
2. (2) circuits for the boat lift
3. Light circuit for (3) lamps
Question # 5: The inspection portion of the solicitation mentions a “vessel”. Please clarify.
Answer: That is a typo. It should have said dock.
Question #6: Will any work for the Fuel System/Fuel Pump rewire or re-pipe be involved?
Answer: No. Fuel System electrical meets current code requirements and is a separate system.
Question #7: Who is responsible for temporary power and permanent power to the fuel pump?
Answer: The government is responsible for turning the power on and off when fuel is needed. The government also coordinates any required inspections.
Question #8: Is there a completion date given after the start of the project?
Answer: The solicitation states that the anticipated performance period is 30 days, however, you are instructed to provide your best realistic completion time with your quote.
Question #9: Is there a bid bond required to be turned in with the package?
Answer: No
Question # 10: The synopsis page references security and fire alarm systems at Cumberland National Seashore, which I believe is a different project (In a paragraph on page 2 and again on page 7 when discussing the types of projects to include for past performance).
Answer: Those are typos and they should BOTH read Fort Matanzas and the project is to rewire a dock
Question #11: The SF18 states it is due on 19 July at 10:00 a.m., but the synopsis says 18 July at 10 a.m.
Answer: That is also a typo. Quotes are due on 19 July @10am.
Question # 12: SAM is showing this opportunity as “closed”. Is this still open?
Answer: Yes, SAM is experiencing multiple glitches. The archive date has been adjusted again.