This statement of work describes a solicitation to renovate employee restrooms and expand a law enforcement dispatch space at Everglades National Park in Homestead, Florida. The scope of work includes demolishing existing structures and systems, constructing new partitions and ceilings, and installing new plumbing fixtures, mechanical and electrical systems. Bids are due within 180 days of award on a firm fixed-price basis. The base bid includes restroom renovations at two buildings, while an additive includes expanding the dispatch center. Interested parties must visit the site and follow all quality control, safety, and environmental standards during construction to minimize impacts to park operations, visitors, and protected species. The National Park Service is the contracting agency seeking these cyclic maintenance services.

View the file

Other files for this federal contract opportunity

Other files attached to PERFORM CYCLIC MAINT ON FOUR RESTROOMS, newest first.
File Type Posted
Questions_Answers_0002.pdf PDF
Sol_140P5422R0020_Amd_0002.pdf PDF
A06_PI_Restrooms_HQ_VC_09_CD_220111_Final_Issue_0001.pdf PDF
Sol_140P5422R0020_Amd_0001.pdf PDF
B09_QUESTIONNAIRE.pdf PDF
B03_SOL_WAGE_RATES.pdf PDF
Sol_140P5422R0020.pdf PDF
A04_PI_Restrooms_HQ_VC_P_Specs.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EVERGLADES NATIONAL PARK

HOMESTEAD, FLORIDA

REHABILITATION OF HEADQUARTERS &

COE VISITOR CENTER EMPLOYEE

RESTROOMS

AND

EXPANSION OF LE DISPATCH SPACE

PINE ISLAND COMMUNITY

STATEMENT OF WORK

NATIONAL PARK SERVICE

EVERGLADES NATIONAL PARK

PART 1

PROJECT DESCRIPTION

1.0 BACKGROUND

The employee restrooms at the Everglades National Park headquarters building and the Coe Visitor Center both in Homestead, Florida do not currently meet ADA standards and have not been renovated in roughly 20 years. The fixtures and partitions are outdated, the ceilings and floors are stained and in poor condition, and the mechanical and electrical systems are functioning poorly. This includes the employee restroom at the current LE Dispatch Center located within the Headquarters Building. There has also been a need to have a fully accessible ADA shower room and an updated janitor closet. Current LE Dispatch requirements have also outgrown the existing Dispatch Center space with crowding of workstations and supporting equipment.

1.1 OBJECTIVE

It is the objective and intent of this Work to fully renovate the employee restrooms at the Headquarters Building and the Coe Visitor Center and to expand the existing LE Dispatch Center into the existing Conference Room. All Work is to be done as indicated in the Drawings and Project Specifications and as otherwise required to bring the employee restrooms and the Dispatch Center space to a like new appearance and to meet current and future operational requirements.

1.2 SCOPE OF WORK

The scope of the work shall include renovations to all interior surfaces, openings, floors and ceilings, and mechanical, electrical, and plumbing systems as further detailed below and as indicated in the Drawings, and Specifications. Drawings and Specifications are integral to this Statement of Work. All work shall comply with current governing policies regarding accessibility and sustainability including plumbing fixtures that are water sense and low flow as specified further in these documents.

1.3 SPECIFIC TASKS

1.3.1 Protect all adjacent work and visitor spaces from damage during Work.

1.3.2 Minimize construction noise during working hours.

1.3.3 Provide temporary restroom facilities for NPS employees during Work.

1.3.4 Provide a temporary workspace for LE Dispatch operations during Work.

1.3.5 Demolish existing interior walls as required for new plan layout and as indicated in the Drawings.

1.3.6 Demolish all interior wall and ceiling sheathing at restrooms and Dispatch Center as required for new Work.

1.3.7 Demolish concrete slab floor as required for placement of plumbing fixtures per the new plan layout and patch to original condition.

1.3.8 Demolish all mechanical, electrical, and plumbing fixtures, circuits, ducts, and lines as required for new plan and as may interfere with the Work.

1.3.9 Construct new metal stud interior partitions as indicated in the plan per the new layout and provide and install new gypsum board sheathing. Sheathing at humid locations to be moisture resistant.

1.3.10 Provide and install new suspended ceiling at restrooms and Dispatch Center as indicated in the Drawings.

1.3.11 Provide and install new wall and floor tile at restrooms and repaint all surfaces affected by the Work as indicated in the Drawings.

1.3.12 Provide and install new plumbing fixtures to include floor mounted water closets, wall hung sinks, and urinals as indicated in the Drawings.

1.3.13 Provide and install new shower and stall enclosures as indicated in the Drawings.

1.3.14 Provide and install new restroom accessories including hand dryers, paper dispensers, and mirrors.

1.3.15 Provide and install ADA water fountain as indicated in the Drawings.

1.3.16 Provide and install new lighting fixtures per Lighting Plan and Schedule.

1.3.17 Provide and install all new mechanical, electrical, and plumbing systems as required for new Work.

1.3.18 Provide and install all server and security systems required for new work at Dispatch Center. Coordinate all server and security system installation with Park IT and LE as required.

PART 2

CONTRACT & BIDDING

2.0 CONTRACTING

The Work shall be performed under a single firm fixed-price contract.

2.1 PERIOD OF PERFORMANCE

The Work shall be performed within 180 days of contract award.

2.2 CONSTRUCTION DOCUMENTS

The Construction Documents consist of this Statement of Work, the Construction

Drawings, and the Project Specifications. All documents are integral to the project.

Contract Drawings and Project Specifications are available to contractors for bidding and construction. The Contractor is responsible for reviewing and becoming familiar with all the information in these documents. Failure to review and understand the information that is shown in these documents does not relieve the Contractor of his obligations to perform the work as otherwise described under the Contract. Missing or unclear information should be brought to the attention of the Contracting Officer as soon as it is discovered. Addendum will be issued to all bidders to address any missing or unclear information found in the drawings and project specifications.

2.3 DISCREPTANCIES

Project Specifications have precedence over the Construction Drawings and are intended to describe the Work more fully. If there is a discrepancy between the two, the Contractor shall immediately inform the Contracting Officer of the discrepancy prior to continuing with the Work. Work shall only proceed once the discrepancy has been reviewed and clarified.

2.4 DEFINITION OF BID ITEMS

All bids shall be itemized per the Master Format of the CSI for the work described.

2.4.1 Base Bid: The base bid shall include all work associated with the renovation of the restrooms at the headquarters and Coe Visitor center buildings.

2.4.2 Bid Additive: The bid additive shall include all work associated with the renovation and expansion of the LE Dispatch center in the headquarters building.

2.5 PRE-BID SITE VISITS

The Contractor is strongly encouraged to conduct a site visit prior to bid submittal. GAO cases have indicated that not visiting a site does not necessarily justify the Contracting Officer from rejecting a bid, however, GOA has also held that if a Contractor does not attend a site visit, the Contractor may still be treated as if they should have known the condition of the site. This means that the Government may not pay a claim for what the Contractor should have known by conducting a site visit.

PART 3

QUALITY CONTROL & ASSURANCE

3.0 QUALITY CONTROL PLAN

After contract award and before the Pre-Construction conference, the Contractor shall submit a written Contractor Quality Control (CQC) plan. If plan requires revisions or corrections, Contractor shall resubmit plan within 10 days. The Government reserves the right to require changes in plan during contract period as necessary to obtain the quality specified. No change in the approved plan may be made without written concurrence by Contracting Officer.

3.1 QUALITY CONTROL

All work shall conform to the International, Florida, Energy and local Building Codes and their amendments, the American with Disabilities Act Accessibility Guidelines, and NPS regulations. If compliance with two or more standards is specified and standards establish different or conflicting requirements for minimum quality levels, the Contractor shall comply with most stringent requirement. The Contractor shall refer uncertainties and requirements that are different, but apparently equal, to Contracting Officer before proceeding with the Work. Permitting for this project is not required.

3.2 QUALITY ASSURANCE

The Contractor shall provide daily reports of construction activity. The form of the report is up to the Contractor, but the report shall include the following information:

3.2.1 Date

3.2.2 Project Title and Contract Number

3.2.3 Contractor’s name and On-site Superintendent’s name

3.2.4 General description of weather and ground conditions

3.2.5 Number of employees (including sub-contractors) working on-site. Employees shall be listed by job categories.

3.2.6 List of equipment working on-site

3.2.7 Description of work performed

3.2.8 Any issues arising including disputes, unforeseen circumstances, differing site conditions, delays, accidents, etc.

3.2.9 Reports shall be e-mailed to the Contracting Officer on a weekly basis.

3.3 PRECONSTRUCTION CONFERENCE

Before start of construction, the Contracting Officer will arrange a meeting with the Contractor. The meeting agenda will include the following as a minimum:

correspondence procedures, designation of responsible personnel, payments to the Contractor, park rules and regulations, construction schedule, submittals, and project closeout requirements.

3.4 FIELD VERIFICATION

The Contractor shall field verify all new and existing dimensions affecting the work of this Contract before ordering products. Any discrepancies between construction drawings, project specifications, and field conditions shall be brought to the attention of the Contracting Officer before work is to be performed. Any work that is performed without notifying the Contracting Officer will be done at the Contractor's own expense.

3.5 SUBMITTALS

All submittals shall be transmitted electronically in PDF or MS Word format.

3.5.1 Pre-Construction Submittals

3.5.1.1 Progress Schedule (normally in bar chart form) showing estimated starting and completion dates for each part of the work.

3.5.1.2 Schedule of Values showing the breakdown of the Contract amount into appropriate units of work. Include general condition costs, overhead, and profit in each part of the work and not as separate items. The Schedule of Values will form the basis for progress payments as provided for in the General Provisions.

3.5.1.3 Accident Prevention Plan

3.5.1.4 Quality Control Plan

3.5.1.5 Hurricane Response Plan

3.5.1.6 Waste Management Plan

3.5.2 Material Submittals

All material submittals shall be transmitted using National Park Service form DSC- 1(CS). No action will be taken on a submittal item unless accompanied by the transmittal form. As specified in the individual sections, forward submittals to the Contracting Officer at least 21 days before need for approval. The Government will return the submittals either approved, approved with notations, or disapproved.

3.5.3 Post Construction Submittals:

Project Record Drawings: Maintain one complete set of contract drawings. Clearly mark changes, deletions, and additions to show actual construction conditions. Show additions in red, deletions in green, and special instructions in blue.

3.6 SUBSTANTIAL COMPLETION AND FINAL INSPECTION

3.6.1 Before scheduling the final inspection, remove all tools, equipment, surplus materials, and rubbish. At time of final inspection, project shall be thoroughly clean and ready for use.

3.6.2 Submit written certification that project, or designated portion of project, is substantially complete, and request in writing a final inspection. Contracting Officer will make an inspection within 10 days of receipt of request.

3.6.3 If the project is determined to be substantially complete, the Contracting Officer will prepare a list of deficiencies to be corrected before final acceptance and issue a Letter of Substantial Completion.

3.6.4 After all deficiencies have been corrected, a Letter of Acceptance will be issued.

PART 4

USE OF PREMISES AND WORK RESTRICTIONS

4.0 GOVERNMENT OPERATIONS

4.0.1 The Headquarters building, and the Coe Visitor Center have employees and visitors present during daytime hours. Construction activities shall be performed in such a manner as to minimize any disturbing noise to employees and visitors and to also shield all spaces not included in the Work from damage.

4.0.2 The Headquarters building, and Coe Visitor Center also need to have functioning men and women’s restrooms for employees during the Work. Additionally, the LE Dispatch Center must remain operational.

4.0.3 The Everglades National Park has a trailer that can be used for both temporary employee restrooms and LE Dispatch operations during the Work. The Contractor shall coordinate the use and establishment of these temporary facilities with Park officials prior to starting any work.

4.0.4 The Government shall provide electrical power. The Contractor shall instruct employees in utility conservation practices. The Contractor shall be responsible for operating under conditions that preclude the waste of utilities, which include turning off the water faucets or valves after use.

4.1 PRESERVATION OF NATURAL FEATURES

The Contractor shall prevent damage to natural surroundings and restore damaged areas, repairing or replacing damaged trees and plants to pre-construction condition at no additional expense to the Government.

4.2 PRESERVATION OF CULTURAL FEATURES

4.2.1 Archeological Resources: There are no known archeological resources that are in the area of this construction. If previously unknown archeological resources are discovered during the work of this project, the Contractor will immediately stop work in the area of discovery and notify the Contracting Officer. An equitable adjustment will be made in accordance with the Changes clause of the Contract.

4.2.2 Historic Preservation: There are no known historic preservation features to this Work. If any historic features are discovered during the work of this project, it is the responsibility of the Contractor to follow all guidance as set forth by the Everglades National Park regarding work under this effort. The Contractor assumes responsibility for knowing and following these guidelines and understanding that adherence to these rules can affect project schedules and scope. An equitable adjustment will be made in accordance with the Changes clause of the Contract.

4.3 START OF WORK NOTIFICATION

At least two weeks prior to the start of on-site work, the Contractor shall notify the Contracting Officer of the intended start date. This will allow government personnel to conduct a final review of the work site for any resource issues prior to the start of construction.

4.4 THREATENED AND ENDANGERED SPECIES

4.4.1 The following threatened or endangered species could be encountered in the project area: Wood Storks, Eastern Indigo Snakes, Bonneted Bats, Florida Panthers, and American Crocodiles. All sightings of these species shall be reported to the Contracting Officer immediately. When an endangered species is present or observed on the work site, work shall be postponed until the individuals leave the area.

4.4.2 At the start of the project, all on-site employees shall receive training to identify threatened and endangered species which may be encountered on the site. At the beginning of each day, any open trenches or excavation shall be inspected for the presents of Eastern Indigo Snakes or other wildlife. The Contractor shall follow the Standard Protection Measures for the Eastern Indigo Snake published by the U.S. Fish and Wildlife Service, August 12, 2013.

4.5 NON-NATIVE SPECIES

To prevent the spread of non-native species into the Park, the Contractor shall clean any construction equipment brought to the site of any foreign material which could contain non-native plants, seeds, animals, or noxious weeks. All materials (including fill dirt and aggregates) shall be free of non-native invasive plants and animals, and noxious weeds.

4.6 CUTTING AND PATCHING

Where required to cut into existing construction to provide for the installation or performance of other work, the Contractor shall restore surfaces to their original condition or to the adjoining new surface. Except as otherwise indicated, or as directed by the Contracting Officer, the Contractor shall use materials for cutting and patching that are identical to existing materials. If identical materials are not available, or cannot be used, the Contractor shall use materials that fully match existing adjacent surfaces possible with regard to visual effect and in a manner which will eliminate evidence of patching and refinishing. The Contractor shall also patch existing systems which are altered or obstructed by the work, and in such a manner as to maintain proper system operation and performance. Any patch work to a building’s exterior or in its occupied spaces, shall not be such that would result in lessening the building's aesthetic qualities or in a manner that would result in substantial visual evidence of cut and patch work

4.7 EROSION AND SEDIMENT CONTROL

The Contractor shall provide and install silt fencing, straw bales, and other protections at the perimeter of the construction site prior to and during construction to prevent sediments from running off of the site. Where silt fencing or straw bales cannot be added due to vehicle trespass from the site, gravel beds or "speed bumps" shall be added to prevent soil from leaving the construction site location. Stockpiled topsoil shall be protected from erosion using tarps, filter fabric, moats, swales, or other methods as required to prevent leakage from the site.

4.8 PROTECTION OF THE PUBLIC

The Contractor shall ensure the safety of the public by providing fencing, barricading, or otherwise blocking off the immediate work area to prevent unauthorized entry. Banner Guard tape imprinted with “CAUTION: CONSTRUCTION AREA”, manufactured by Reef Industries, Inc., Houston, TX or approved equal shall be used for any cordoning of project work areas. The Contractor shall erect and maintain barricades, lights, danger signals, and warning signs in accordance with MUTCD.

4.9 ON-SITE WORK HOURS

The contractor shall schedule the work only during the hours of 7 am to 6 pm Monday through Friday. Requests for any work outside those hours, including weekends and holidays, must be submitted for approval at least 48 hours in advance.

4.10 GOVERNMENT HOLIDAYS

No services or deliveries shall be performed on Government legal holidays unless otherwise directed by the COTR. The following Government holidays are normally observed by Government personnel: New Year’s Day, Martin Luther King’s Birthday, Presidential Inauguration Day (Washington, DC Metropolitan Area only), President’s Day, Memorial Day, June 19th, Independence Day, Labor Day, Columbus Day, Veteran’s Day, Thanksgiving Day, Christmas Day, and any other day designated by Federal Statute, Executive Order, and/or Presidential Proclamation. Or any other kind of administrative leave such as acts of God (i.e., hurricanes, snowstorms, tornadoes, etc.)

Presidential funerals or any other unexpected government closures.

4.11 EXISTING SITE FEATURES

The Contractor shall protect existing site features, including walls, fences, paving, curbing and other construction, not scheduled for work, so as not to be damaged by the Contractor’s activity. Any damage that does occur to these areas shall be returned to the pre-contract condition as part of this contract at no additional cost to the Government. Local patching to correct damage will not be acceptable in cases where patching will be recognized. Entire regional replacement/restoration will be required.

4.12 EXISTING UTILITIES

The Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, the Contractor shall repair utility at no additional expense to the Government.

4.13 ACCIDENT PREVENTION

Before on-site work begins, the Contractor shall submit a written accident prevention plan containing the following:

4.13.1 Identification of personnel responsible for safety at both the corporate and project level including on-site personnel

4.13.2 An Emergency Response Plan including site specific emergency contact information and location of the nearest emergency room

4.13.3 An outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, National Park Service personnel, and Contractor's employees.

The Contractor shall follow all federal, state, and local safety and health requirements and shall report all accidents to the Contracting Officer as soon as possible and assist the Contracting Officer and other officials as required in the investigation of an accident.

4.14 FIRE PROTECTION

4.14.1 Responsible person: A capable and qualified person shall be placed in charge of fire protection. The responsibilities shall include locating and maintaining fire protective equipment and establishing and maintaining safe torch cutting and welding procedures.

4.14.2 Hazard Control: The Contractor shall take all necessary precautions to prevent fire during construction including but not limited to not storing flammable or combustible liquids within 50 feet of a structure and providing adequate ventilation during use of volatile or noxious substances.

4.14.3 Spark Arresters: The Contractor shall equip all gasoline or diesel-powered equipment used during periods of potential fire hazards or in potential forest and grass fire locations with spark arresters approved by the U. S. Forest Service.

4.14.4 Smoking: Smoking within buildings or temporary storage sheds is prohibited.

Smoking is prohibited near any combustible materials.

4.14.5 Welding: Cutting by torch or welding shall be performed only when adequate fire protection is provided.

4.14.6 Equipment: Fire protection equipment shall include but not be limited to a UL Class 2A, 2 1/2-gallon water type stored-pressure extinguisher and UL Class 10, Type I 15-pound B: C carbon dioxide extinguisher. Travel distance from any work station to the nearest extinguisher shall not exceed 75 feet.

4.15 CONSTRUCTION MATERIALS

All materials, including borrow and aggregates, shall be Contractor furnished from outside the Park.

4.16 RECYLABLE MATERIAL

The government’s goal in Waste management is to salvage and recycle as much nonhazardous construction waste as possible. Items and materials to be recycled shall be protected from contamination and shall be handled, stored, and transported in a manner that meets the requirements set by the designated facilities for acceptance.

4.17 DISPOSAL OF WASTE

Except for items or materials to be salvaged, recycled, or otherwise reused, all removed items or material including, soil and rock, becomes the property of the Contractor. The Contractor shall transport all items or material off government property and legally dispose of them in a landfill or incinerator acceptable to authorities having jurisdiction.

The Contractor shall remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas. Except as otherwise specified, the Contractor shall not allow waste materials that are to be disposed of to accumulate on-site or burn any waste materials.

4.18 HAZARDOUS WASTE

If any waste materials encountered during the deconstruction, demolition or construction phase are found to contain lead, asbestos, PCBs, (such as fluorescent lamp ballasts), or other harmful substances, they are to be handled and removed in accordance with local, state, and federal laws and requirements concerning hazardous waste.

4.19 TEMPORARY FACILITIES

4.19.1 First Aid Facilities: The Contractor shall provide adequate facilities for the number of employees and the type of construction at the site.

4.19.2 Sanitary Facilities: The Contractor shall provide sufficiently lighted and ventilated toilet facilities in weatherproof, sight proof, sturdy enclosures that are placed in approved locations secluded from public observation and convenient to work areas.

The Contractor shall not use the restroom facilities provided for the public.

4.20 PERSONNEL PROTECTIVE EQUIPMENT (PPE)

The Contractor shall provide adequate Personnel Protective Equipment that meets the requirements of NIOSH and ANSI.

4.21 SECURITY

4.21.1 Physical Security: The Contractor shall be responsible for safeguarding all government property provided for Contractor use. At the end of normal duty hours and/or after normal duty hours, all government facilities, equipment, and materials must be secured.

4.21.2 Key Controls: The Contractor shall establish and implement methods of making sure all keys issued to the Contractor by the government are not lost or misplaced and are not used by unauthorized persons. The Contractor shall not duplicate any keys issued by the government. The contractor shall immediately report to the Contracting Officer any occurrences of lost or duplicated keys. In the event keys, other than master keys, are lost or duplicated, the Contractor may be required, upon written direction of the Contracting Officer, to re-key or replace the affected lock or locks at no cost to the government.

4.22 HURRICANES

The government requires closing of operations between 72 and 48 hours of anticipated landfall of a tropical storm or hurricane as determined by the National Park Service. The Contractor shall maintain contact with Park officials and secure or removed all project materials from the site within that time frame.

PART 5

TECHNICAL DOCUMENT LISTING

6.1 Contract Drawings

6.2 Project Specifications*

6.3 Statement of Work

*Division 1 of the Project Specification provides additional information to this Statement of Work. Any discrepancies among these documents or questions regarding the Work shall be addressed to the Contracting Officer, prior to bidding or commencement of Work.

EVERGLADES NATIONAL PARK HOMESTEAD, FLORIDA
STATEMENT OF WORK