Atch_1_to_Am_1-Q&As.pdf
PDF 49 KB Posted
- Attached to
- Loggerhead-CUIS
- Solicitation number
- 140P5419R0014
About this file
Atch 1 to Am 1-Q&As
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P5419R0014_Amd_0001.pdf | ||
| Sol_140P5419R0014.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
140P5419R0014 Amendment 1 Attachment 1
Question #1: Concerning the base year #20. Is this meant to be reinstall the shafts or reinstall and check the alignment of the transmission to the shaft?
Answer: When the shafts are removed and reinstalled, they should be aligned for proper fit and function. So it is to install and check for alignment.
Question #2: Concerning the base year #21. It states to recondition props. Then in year 2 it states to replace with new and the same for years 3 and 4. Just to clarify you are looking for a total of 3 new sets of props and just a recondition of the props the initial year? Correct?
Answer: No, In Option Year 2, which is year 3 it states to replace the props. Year 3 and 4 is referring to the second year of the contract which is Option Year 1. So only one new set of props in Option Year 2 and reconditioning of props all other times.
Question #3: Base year one #34 states to replace the generator. Is this just the just the generator portion of the sled unit correct?
Answer: No, replace the entire unit.
Question #4: Where it states Option year #2 the first bullet point states “complete all items the same as year 2.” Is this supposed to be year one or base year?
Answer: It is written to mean the second year of the contract, which is Option Year 1. So Option Year 1 is referring to the base year and Option Year 2, 3 and 4 are referring to Option Year 1.
Question # 5: Will you be posting an updated Performance Work Statement (PWS)?
Answer: Not with this amendment. Any answers or clarifications that add to or change any information currently in the performance work statement will be incorporated before award. Acknowledgement of these answers demonstrates offeror’s receipt of updated info.