This document is an Additional Questions and Answers amendment (Amendment 2) for Solicitation 140P5325Q0043, related to fabricated steel closure gates for the Blue Ridge Parkway. The document addresses 17 specific vendor questions about gate specifications, including details about road closed signs, paint requirements, gate configuration, and installation parameters. Key clarifications include confirmation that the solicitation covers 19 pairs of gates, signage must be through-bolted to gates, all base plates must be 1" thick, gates require a white finish for corrosion resistance, and signs/reflective tape must be applied before delivery. The gates are to be delivered to 51 Ranger Drive, Asheville, NC, and are part of a 100% small business set-aside contract using NAICS code 332312 for Fabricated Structural Metal Manufacturing. The response deadline remains 7/22/2025 at 5 PM EDT.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P5325Q0043_Amd_0002.pdf | ||
| SPECS_BLRI_Road_Gates_REVISED_2025_0001.pdf | ||
| A4_-_mutcd11thedition_0001.pdf | ||
| Sol_140P5325Q0043_Amd_0001.pdf | ||
| Questions_and_Answers_140P5325Q0043_0001.pdf | ||
| A3_-_Price_Schedule.docx | DOCX document | |
| Sol_140P5325Q0043.pdf | ||
| A1_-_Scope_of_Work.pdf | ||
| A2_-_Specifications.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Additional Questions and Answers
140P5325Q0043
Amendment 2
1. Question: Road closed sign like the one on page G1 in the drawing. Is there a supplier that sells them?
Answer: The signs would be available at any vendor that sells road signs that meet
MUTCD spec. I have included an example of the sign and barricade boards that we use when assembling.
Red/White Driveway Barricade Boards | Movable Barricades
Temporary Traffic Control Road Closed Sign | CPC Signs
PRODUCT ID: S (XXXX)R112 (X) (S) Size of this Road Closed Sign
(XXXX): (4830) 48" x 30" for Conventional^ Single/Multi-Lane Roads
NOTES: ^ Conventional Roads include Single and Multi-Lane Roads. * Denotes there is a different minimum size required for multi-lane roads from Table 2B-1.
+ Denotes sizes from Table 2B-1 not listed for road types in Table 6F-1. | view table 2B.1 Reflective Sheeting ...
www.cpcsigns.com
PRODUCT ID: S (XXXX)R112 (X) (S) Size of this Road Closed Sign
(XXXX): (4830) 48" x 30" for Conventional^ Single/Multi-Lane Roads
NOTES: ^ Conventional Roads include Single and Multi-Lane Roads. * Denotes there is a different minimum size required for multi-lane roads from Table 2B-1.
+ Denotes sizes from Table 2B-1 not listed for road types in Table 6F-1. | view table 2B.1 Reflective Sheeting ...
www.cpcsigns.com
2. Question: The paint callout is for high white rustproof paint. Does this mean wet-coat or powder coat?
a. Answer: No preference for the paint used as long as it is intended for rust prevention on steel in an outdoor setting.
3. Question: Is the Signage included in this bid? The signs are not listed on the Bill of
Materials list.
a. Answer: Signage is included in the bid.
https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.cpcsigns.com%2Fproddetail.php%3Fprod%3DRed%252FWhite-Barricade-Boards&data=05%7C02%7Cashley_warcewicz%40nps.gov%7C1d8e28ae1e4841b6af7408ddc2ce2b68%7C0693b5ba4b184d7b9341f32f400a5494%7C0%7C0%7C638880912925577516%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=cjwROYwkio2b1ZoS%2BFutsCry%2BYcL2Mj%2FnU8MBvvxXR0%3D&reserved=0 https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.cpcsigns.com%2Fproddetail.php%3Fprod%3DRoad-Closed-Sign-for-Temporary-Traffic-Control-%2528Crashworthy-Barricade-Signs%2529&data=05%7C02%7Cashley_warcewicz%40nps.gov%7C1d8e28ae1e4841b6af7408ddc2ce2b68%7C0693b5ba4b184d7b9341f32f400a5494%7C0%7C0%7C638880912925599063%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=StodL77abE4VhGOcDk43mWg%2F5vBhZkNXDgVekTDQais%3D&reserved=0 https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.cpcsigns.com%2Fproddetail.php%3Fprod%3DRoad-Closed-Sign-for-Temporary-Traffic-Control-%2528Crashworthy-Barricade-Signs%2529&data=05%7C02%7Cashley_warcewicz%40nps.gov%7C1d8e28ae1e4841b6af7408ddc2ce2b68%7C0693b5ba4b184d7b9341f32f400a5494%7C0%7C0%7C638880912925626125%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=5hSfIqUWGJGlsBeI6d4Ml5XC%2BtIfFzhI%2F%2Bu2ZUxGaCI%3D&reserved=0 http://www.cpcsigns.com/ https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.cpcsigns.com%2Fproddetail.php%3Fprod%3DRoad-Closed-Sign-for-Temporary-Traffic-Control-%2528Crashworthy-Barricade-Signs%2529&data=05%7C02%7Cashley_warcewicz%40nps.gov%7C1d8e28ae1e4841b6af7408ddc2ce2b68%7C0693b5ba4b184d7b9341f32f400a5494%7C0%7C0%7C638880912925653963%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=8a0aJTdYoFDiLl7h9tPgsI%2FCt1Y6%2FvebKbj7sc1NkZ0%3D&reserved=0 http://www.cpcsigns.com/ https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.cpcsigns.com%2Fproddetail.php%3Fprod%3DRoad-Closed-Sign-for-Temporary-Traffic-Control-%2528Crashworthy-Barricade-Signs%2529&data=05%7C02%7Cashley_warcewicz%40nps.gov%7C1d8e28ae1e4841b6af7408ddc2ce2b68%7C0693b5ba4b184d7b9341f32f400a5494%7C0%7C0%7C638880912925612688%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=1468pzjHhAhIv04P5EUH40mTtEYio%2FYDnxHc6lsh3uo%3D&reserved=0 https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.cpcsigns.com%2Fproddetail.php%3Fprod%3DRoad-Closed-Sign-for-Temporary-Traffic-Control-%2528Crashworthy-Barricade-Signs%2529&data=05%7C02%7Cashley_warcewicz%40nps.gov%7C1d8e28ae1e4841b6af7408ddc2ce2b68%7C0693b5ba4b184d7b9341f32f400a5494%7C0%7C0%7C638880912925640384%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=%2BWBMn%2BRL4foxZshcD9x2N%2BSagFSknJ815gHqS85xGKs%3D&reserved=0
4. Question: Is there any particular method requested for mounting the signs?
a. Answer: Signage will be through bolted to the gate.
5. Question: Can they be detached for shipping?
a. Answer: They do not need to be attached prior to shipping.
6. Question: Verify the round tubing (railing as listed in BOL) – is not required to be capped at either end?
a. Answer: All materials listed should be either square or rectangular tubing.
7. Question: Can it be done Hot Deep Galvanized rather to paint High options post fabricating for the best standing for corrosion resistant standing outdoor in all weather conditions. Or whether resistance White color is only required.
a. Answer: Galvanized metal would not be acceptable, only a white finish.
8. Question: Road Closer MUTCD Sign Marked, Object Marked (12" x 36") & Red High
Intensity Type 3 Tape, are they in the scope or work for us?
a. Answer: All signage and markings specifications are listed on the drawing or
MUTCD manual.
9. Question: What size of the LOCKING MECHANISUM PLATE (1/4) or (3/8)?
a. Answer: All thicknesses of metal are listed in the plan the tube is 1/8" tubing the three-sided box is 1/4" plate and the locking mechanism is listed as 1/4" plate
10. Question: Pg# 1 showing 21 & 21A shows in Post Bracket at Top & Bottom, while at PG#3
Elevation post assy. Showing different sizes, Please Confirm.
a. Answer: This is displaying two different post options. We will be using the 4x6 poste and the type a base/leveling plate detail.
11. Question: Do we need to add lock Sackel in our scope of work? As no details found in drawing
a. Answer: You do not need to provide any locks.
12. Question: Dia. 1" rod is the hinge pin in this case?
a. Answer: The 1" diameter rod is the Hinge Pin
13. Question: Quantity and Configuration of Gates
The bid references 19 sets of gates. Just to confirm—does this refer to 19 pairs of gates (i.e., 38 leaves total with a left and right leaf per set)?
a. Answer: Yes 19 pairs of gates and other smaller parts listed in the SOW.
14. Question: Main Gate Clarification & Visual Reference
The documentation mentions a "main gate." Is this gate included as one of the 19 sets, or is it considered a separate, 20th gate? Additionally, is there an image, diagram, or drawing available for the main gate that could help clarify its design?
a. Answer: The reference to the main gate sections is just the parts that swing on the hinges. This does not include posts or any of the other components.
15. Question: Corrosion-Resistant Requirements & Final Coating
Could you please clarify what is meant by “corrosion-resistant”? Are you requesting the gates to be galvanized, fabricated from stainless steel, or is this requirement limited to the primer and paint system? Is powder coating an option to prevent touch up after delivery?
a. Answer: Corrosion resistant refers only to the paint coatings we are not asking for any other treatments or materials
16. Question: Leveling Base Plates & Quantities
Are all leveling base plates required to be 1" thick? We noticed a mix of different plate sizes and are hoping to better understand the rationale behind the variation—especially if all the gates are intended to be uniform. Could you also confirm the quantity of 6"x6" square base plates being requested?
a. Answer: All bases must be 1" thick and use the base detail "type A" on attachment B
17. Question: Signage and Reflective Tape
Are we, as the fabricator, responsible for any signage or reflective safety tape on the gates?
Or will this be applied separately by the Park Service?
a. Answer: The gates must have the signs and the reflective tape applied before delivery. the Signs may be detached for easier transportation.
File details come from the government source that posted it. Updated .