This solicitation is for pressure washing, repairing, painting, and caulking services for the exterior of the Oregon Inlet Fishing Center Comfort Station located at 98 NC-12 Nags Head, NC 27959. The National Park Service is seeking these services through a firm fixed price small business set-aside contract valued between $25,000 to $100,000. The period of performance is approximately September 15, 2024 through April 15, 2025. An optional site visit is scheduled for March 19, 2024 and questions regarding the solicitation are due by March 21, 2024. Responses to the solicitation are due by April 5, 2024. Registration in the System for Award Management is required to be eligible for award.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| site_visit_sign_in_sheet_0002.pdf | ||
| Sol_140P5324R0018_Amd_0002.pdf | ||
| Q_and_A_0002.pdf | ||
| Sol_140P5324R0018_Amd_0001.pdf | ||
| Construction_Contract_Administration.docx | DOCX document | |
| DOL_Wage_Determination.pdf | ||
| Sol_140P5324R0018.pdf | ||
| RFP_-_UNDER_SAT_CONST_clauses_FEB_2024.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pressure Wash, Paint and Caulk Exterior of OIFC comfort Station
CAPE HATTERAS NATIONAL SEASHORE
Outer Banks Group
Scope of Work
1.0 INTRODUCTION
The National Park Service (NPS) Cape Hatteras National Seashore (CAHA) has a requirement to
Pressure wash, repair, paint, and caulk exterior of the Oregon Inlet Fishing Center Comfort
Station.
2.0 CONSTRUCTION SITE LOCATION
The Oregon Inlet Fishing Center Comfort Station is located at 98 NC-12 Nags Head, NC 27959
3.0 BACKGROUND AND EXISTING CONDITIONS
The Comfort Station was constructed circa 1960. The structure is a wood frame building constructed on CMU block foundation wall. The building is approximately 30 ft long x 28 ft wide with an additional 6 ft wide porch on the west end and the entrance on the west end. The site gradually rises from the west to the east end. The structure consists of a CMU foundation wall with crawl space and CMU block walls beneath the floor, painted T1-11 style cement board siding on insulated wood stud walls and wooden A-frame roof with asphalt shingles. The exterior finish on this building is failing due to the age, high winds and beach environment. The exterior of this building needs to be lightly scraped, pressure washed, 1x3 PVC batten boards installed along each joint in the siding, The exterior corners need to be removed and replaced with 1x3 PVC caps and a 1x6 sill trim around the entire base of the siding, all exterior surfaces of the building repainted and all seams sealed with silicone-based caulking. The railing around the Deck, Handicap ramp and stairway need the pickets and all fasteners removed and replaced with 2x6 pressure treated lumber placed horizontally 5 rows with equal spacing in-between and pressure washed in entirety. Replace approximately 12 Sq. Ft. of shingles and roof paper in
Northwest corner of roof along the drip edge. All fasteners will be Stainless Steel grade 316 or higher.
4.0 MAJOR WORK COMPONENTS
The contractor will provide all technical support, materials, tools, equipment, and manpower required complete the project.
The major work components are not meant to be an all-inclusive to do list for the project, but a list of the main items involved in the project. The contractor is responsible for verifying existing conditions. The contractor can use this list to assist with the bid process for this project. The major project components are listed below but are not limited to the following:
BID REQUIREMENTS:
A. Remove existing corner board, any signage attached to building and any old caulking from joints and seams, scrape and pressure wash building and deck.
B. Install new 1x3 PVC corners approximately 64 lin. ft, new1x6 sill trim approximately
64 lin. Ft., install new 1x3 PVC batten boards approximately 275 lin. Ft. to panel joints.
C. Remove 1x6 facia trim from west side of building over deck area, cutout and replace damaged siding approximately 10” high by 24’ wide, reinstall facia trim to cover repair seam.
D. Repaint entire exterior of building and doors existing color approximately 1124 sq.
ft., include windows, doors, siding with one coat of primer and two coats of high-quality exterior breathable latex paint, primer and topcoat combined is acceptable, color shall match existing color.
E. Apply white silicone-based caulk to all seams along trim.
F. Remove all railing 2x2 pickets including all fasteners and replace with 2x6 pressure treated lumber, 5 rows with equally spaced.
G. Remove damaged shingles along the northwest corner of the roof, renew roof paper and install approximately 12 sq. ft. of shingles.
H. Supply and install new restroom signs. Signs shall be identical to existing signs in color, design, and size.
I. Supply and install new soffit vents (4) conditions and from a normal viewing position. See PDCA P1. At PDCA-Standards-
May28-2019.pdf (pcapainted.org) https://pcapainted.org/wp-content/uploads/2019/05/PDCA-Standards-May28-2019.pdf https://pcapainted.org/wp-content/uploads/2019/05/PDCA-Standards-May28-2019.pdf
NOTES:
1. All carpentry work required to install the batten boards, sill trim, railing, signs, vents and shingles is included in this project.
2. The NPS follows the International Building Code (IBC). This project must meet the
IBC, and all federal, state, and local codes.
3. During construction the building shall be kept open for public for use.
4. The painting contractor will produce a “properly painted surface.” A “properly painted surface” is defined as uniform in appearance, color, texture, hiding and sheen.
It is also free of foreign material, lumps, skins, runs, sags, holidays, misses, or insufficient coverage. It is also a surface free of drips, spatters, spills, or overspray caused by the painting contractor’s workforce. To determine whether a surface has been “properly painted” it shall be examined without magnification at thirty-nine (39) inches or one (1) meter, or more, under finished lighting.
5.0 SUBMITTALS
A. Product Data. The Contractor shall submit written documentation or color/product samples for materials identified in the Scope of Work.
1. Color Selection Sheet for Paint and Caulk
2. PVC trim and batten material
3. Fasteners\ system for trim and railings.
4. Shingle type and color
B. Manufacturer requirements for Installer Qualifications
C. All manufacturer operation and maintenance manuals, warranties, and cleaning instructions shall be submitted before final payment is made.