Amendment_1_Attachment_1_QnA_0001.docx

DOCX document 13 KB Posted

Attached to
GATE-CROSSWALKS & RUMBLE STRIPS MARKINGS Federal contract opportunity
Solicitation number
140P4522R0006
Issued by
Department of the Interior National Park Service

View the file

Other files for this federal contract opportunity

Other files attached to GATE-CROSSWALKS & RUMBLE STRIPS MARKINGS, newest first.
File Type Posted
Sol_140P4522R0006_Amd_0001.pdf PDF
B08_Solicitation_Clauses_and_Provisions.pdf PDF
B08_Attachment_1_Scope_of_Work.pdf PDF
B08_Attachment_2_Wage_Determination.pdf PDF
Sol_140P4522R0006.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment 1, Attachment 1 Questions and Answers

1. Can the government specify which markings are “old, unwanted” markings?

Yes, it will be all of the markings leading up to the crosswalk that is associated with the crossing. Not the Crosswalk itself. The only existing crosswalk to be grinded off (removed) is the crosswalk at the campsite. The new crosswalk will be angled differently.

The Park believes that the existing crosswalks can be painted over as described in the SOW, achieving the same goal without having to grind off the old crosswalk.

If vendors do not agree, the Park would like to know the appropriate means and methods.

2. Can the government confirm that the only crosswalk painting which needs to be removed using an asphalt grinder is the crosswalk at the campsite?

Yes. The only existing crosswalk to be grinded off (removed) is the crosswalk at the campsite. The new crosswalk will be angled differently.

3. Can the submission date be extended to a later date to address questions asked during the site visit?

Yes. The due date is extended to 5:00PM Eastern, Friday February 4, 2022.