Q_As_0001.pdf

PDF 107 KB Posted

Attached to
CACO SPVC WASTEWATER SYSTEM SERVICE Federal contract opportunity
Solicitation number
140P4323Q0051
Issued by
Department of the Interior National Park Service Northeast Region

View the file

Other files for this federal contract opportunity

Other files attached to CACO SPVC WASTEWATER SYSTEM SERVICE, newest first.
File Type Posted
Sol_140P4323Q0051_Amd_0001.pdf PDF
Combined_Synopsis_Solicitation_(CACO_Wastewater).pdf PDF
Attachment_2_-_Salt_Pond_As-Builts.pdf PDF
Attachment_1_-_PWS_SPVC_Wastewater_Testing_Service.pdf PDF
Attachment_3_-_WD_2015-4045_Rev_25_05-11-2023.pdf PDF
Sol_140P4323Q0051.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Cape Cod National Seashore

Salt Pond Visitor Center Wastewater Treatment System Service Testing and Maintenance

50 Nauset Road, Eastham, MA.

June 22, 2023

Questions and Answers:

1) How big is recirculation tank? The recirculation tank is the third tank and is 8,000 gallons.

The first septic tank is 9,000 gallons and the second septic tank is 6,640 gallons.

2) Do you test influent wastewater in addition to effluent? Yes, we sample influent.

3) How often is the septic tank pumped? Twice per year.

4) Is there pumped or passive venting? Passive.

5) What is the frequency of additions to the sodium bicarbonate dosing tank?

Currently the sodium bicarbonate is added to the tank twice per week the dosing is 24 hours per day at a steady pace, but we are looking for guidance from the service contractor on how much to add, how often, and proper dosing levels.