Sol_140P4226R0025_Amd_0003.pdf
PDF 243 KB Posted
- Attached to
- REPLACE HVAC SYSTEMS AND CONTROLS
- Solicitation number
- 140P4226R0025
About this file
This is Amendment 0003 to a solicitation for the Replacement of HVAC Systems at Richmond National Battlefield Park (RICH), issued by the Department of Interior, National Park Service, Northeast Regional Contracting office (South/Philadelphia MABO) located in Philadelphia, PA. The solicitation number is 140P4226R0025, with an effective date of 09/17/2026. The amendment is issued to answer additional questions received from contractors. The period of performance extends from 10/01/2026 to 05/31/2027. Contractors must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation, either by completing the form and returning it, acknowledging receipt on each copy of the offer submitted, or by separate letter or electronic communication that references the solicitation and amendment numbers. Failure to timely acknowledge may result in rejection of the offer. The contracting officer is Wendy De Leon.
The Questions and Answers clarify key terms and conditions for the HVAC replacement project, including that the 10 feet of new ductwork is an estimate only and additional ductwork replacement requires modification; the Trane Concierge System is the basis of design to be furnished by the HVAC Contractor, though other manufacturers are acceptable if meeting performance requirements; balancing dampers and electrical service upgrades are not confirmed as base bid items and will require modification if necessary; DALT testing must be performed on 100 percent of ductwork, with new ductwork deficiencies corrected by the Contractor at no additional cost; and pre-insulated copper refrigerant line sets smaller than 1" OD are acceptable.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7.ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
Wendy De Leon
See continuation page
DOI, NPS, NERO & NER SOUTH MABO
National Park Service Northeast Regional Contracting South/Philadelphia MABO 1234 Market Street, 20th Floor Philadelphia PA 19107
PNC
140P4226R0025
09/17/2026
08/19/2026
1 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140P4226R0025/0003
Replacement of HVAC Systems at Richmond
National Battlefield Park (RICH), PMIS 313918
Amendment 0003 is issued to answer additional question received.
Period of Performance: 10/01/2026 to
05/31/2027
140P4226R0025 Q&A Replacement of HVAC Systems at RICH Page 1 of 2
1. The drawings direct contractors to "Clean all existing ductwork" and "Assume 10' of new ductwork". Is 10 feet intended to be a hard allowance per system or merely an estimate?
The 10 feet of new ductwork is an estimate and is not intended as a hard allowance per system. If additional ductwork replacement is determined to be necessary based on the Contractor's site evaluation, the Contractor shall bring the condition to the COR's attention. Additional ductwork replacement will require a modification.
2. If duct leakage, damaged insulation, or internal contamination exceeds the assumed quantity of duct to be replaced, how will the additional duct replacement be compensated?
The Contractor shall bring any additional ductwork replacement required due to duct leakage, damaged insulation, or internal contamination to the COR's attention.
Additional work will require a modification.
3. Specifications call for test and balance of existing ductwork. Has it been confirmed that dampers are installed at each supply branch duct, and if not, how would that be handled? Is pre-testing required and if so, can you provide airflow requirements?
It has not been confirmed whether balancing dampers are installed at each supply branch duct. If dampers are determined to be missing where required, the Contractor shall bring the condition to the COR's attention. Additional damper installation will require a modification.
Pre-testing of the existing ductwork is not required. Test and balance shall be performed in accordance with the contract documents.
4. Several properties for the project reference attic installations and existing access hatches. Can the owner confirm existing access openings are sufficient to install all specified VAV boxes, air handlers, and heat pumps?
It is believed that the existing access openings are sufficient for installation of the specified equipment. The existing hatches are meet the size of the current equipment installed. Any change in size/configuration of the new equipment may require resizing the opening to install equipment.
5. For refrigerant lines smaller than 1" OD, are pre-insulated copper lines sets acceptable?
Yes
6. Is the Trane Concierge System to be furnished and installed by the HVAC contractor or by a controls subcontractor? The drawings reference the Trane Concierge, but the specifications call for an open cloud-based control system. Please clarify the basis of design and acceptable manufacturers.
The Trane Concierge System shall be furnished and installed by the HVAC Contractor.
Trane Concierge is the basis of design, as the basis-of-design air-handling unit is a
140P4226R0025 Q&A Replacement of HVAC Systems at RICH Page 2 of 2
Trane unit. Other manufacturers are acceptable provided their systems meet the performance and functionality.
7. If deficiencies are found in existing electrical service capacity, is electrical service upgrade work considered:
1. Base Bid
2. Owner Contingency
3. Future Change Order?
Electrical service upgrade work required due to deficiencies in the existing electrical service capacity is considered future change order work and is not included in the Base Bid.
8. For DALT testing of duct systems, what % of ductwork is to be tested and what are acceptable tolerances? How are they to be handled?
1. Base Bid
2. Owner Contingency
3. Future Change Order?
DALT testing shall be performed on 100 percent of the ductwork. Leakage deficiencies in existing ductwork shall be brought to the COR's attention and will require a modification if additional repair or replacement is necessary. Leakage deficiencies in new ductwork installed under this contract shall be corrected by the Contractor at no additional cost to the Government and are included in the Base Bid.
9. At the Watt House Location, we were unable to see equipment installed on the 2nd floor because the doors were locked with no access. Can you please provide photos of areas not available during the site-visit?
The access hatch is ~28" x 28", with a ceiling height of ~72 inches from the top of the ceiling joists to the bottom of the ridge. I currently have no photos of the area available.
| Amendment of solicitation/modification of contract |
| Contract ID code |
| Amendment/modification number |
| Effective date |
| Requisition/purchase requisition number |
| Project number |
| Issued by |
| Code |
| Administered by |
| Code |
| Name and address of contractor |
| Code |
| Facility code |
| Amendment of solicitation number |
| Dated |
| Modification of contract/order number |
| Dated |
| This item only applies to amendments of solicitations |
| Accounting and appropriation data |
| This item applies only to modifications of contracts/orders. |
| This change order is issued pursuant to: |
| The above numbered contract/order is modified to reflect the administrative changes |
| This supplemental agreement is entered into pursuant to authority of: |
| Other |
| Important: |
| Description of amendment/modification |
| Name and title of signer |
| Contractor/offeror |
| Date signed |
| Name and title of contracting officer |
| Signature of Contracting Officer |
| Date signed |
| Previous edition unusable |
| Standard form 30 (rev. 11/2016) |
| Continuation sheet |
| Reference Number |
| Name of Offeror or Contractor |
| OPTIONAL FORM 336 (4-86)) |
Sponsored by GSA FAR (48 CFR) 53.110
File details come from the government source that posted it. Updated .