Attachment_1_-_Amendment_0003_-_140P4225B0002__0003.pdf

PDF 179 KB Posted

Attached to
INDE LBC GLAZING MAINT. & REPAIRS Federal contract opportunity
Solicitation number
140P4225B0002
Issued by
Department of the Interior National Park Service Northeast Region

About this file

This document is an Amendment (0003) to a federal solicitation for Glazing Maintenance and Repairs at the Liberty Bell Complex for Independence National Historical Park. The amendment introduces a Special Clause 1 - Economic Price Adjustment for Materials Costs, which applies to firm-fixed-price construction contracts where significant contract costs are subject to market price fluctuations.

Key details include extending the Bid Opening to Tuesday, July 22, 2025 at 3:30 PM Eastern, with a Microsoft Teams meeting (ID: 279 943 204 970 6, Passcode: d7UW94X5). The economic price adjustment clause allows for contract price adjustments based on documented increases or decreases in designated materials costs (including steel, aluminum, copper, asphalt, cement, lumber, and fuel), with adjustments only applying when unit price changes exceed ±10% from the base price. The contractor must submit written adjustment requests within 30 calendar days after the adjustment period, providing supporting documentation, and all adjustments will be reviewed and approved by the Contracting Officer.

View the file

Other files for this federal contract opportunity

Other files attached to INDE LBC GLAZING MAINT. & REPAIRS, newest first.
File Type Posted
Sol_140P4225B0002_Amd_0003.pdf PDF
Sol_140P4225B0002_Amd_0002.pdf PDF
Amendmend_1__Attch_3__Drawings_Rev_0001.pdf PDF
Amendment_1__Attch_2__011000_SummaryOfWork_Rev_0001.pdf PDF
Sol_140P4225B0002_Amd_0001.pdf PDF
Amendment_1__Attch_1__Q_A_0001.pdf PDF
B03_Attch_3_WD_PA20250003_30May25.pdf PDF
Sol_140P4225B0002.pdf PDF
B08_Attch_4_Limitations_on_Subcontracting_Report.xlsx XLSX spreadsheet
B08_Attch_1_Specs.pdf PDF
B08_Attch_2_Drawings.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment 0003 – 140P4225B0002

Updated Meeting Invite

Microsoft Teams Need help?

Join the meeting now

Meeting ID: 279 943 204 970 6

Passcode: d7UW94X5

Dial in by phone

+1 360-970-9446,,767501958# United States, Olympia

(833) 436-1163,,767501958# United States (Toll-free)

Find a local number

Phone conference ID: 767 501 958#

Additional Clause – will be incorporated in Section H of the Award

SPECIAL CLAUSE 1 – Economic Price Adjustment – Materials Costs

1. Applicability

This clause applies to firm-fixed-price construction contracts when it is determined that a significant portion of the contract cost is subject to market price fluctuations for designated materials.

2. Definitions

Base Price: The price per unit of material established as of the date of contract award.

Adjustment Period: A specified timeframe (e.g., quarterly) for reviewing and applying potential price adjustments.

Designated Materials: Materials subject to adjustment under this clause. These may include, but are not limited to: steel, aluminum, copper, asphalt, cement, lumber, building materials not otherwise stated and fuel.

3. Price Adjustment Conditions

• The contract price shall be adjusted (upward or downward) to reflect documented increases or decreases in the cost of designated materials, subject to the following:

o Adjustments will only apply if the change in unit price exceeds ±10% from the Base

Price.

• Price changes must be supported by published indices (e.g., commodity indexes, Consumer Price

Index, etc.) or supplier invoices.

• Adjustments apply only to quantities not yet delivered or installed.

• Contractor must keep and retain dated documentation (e.g. quotes/proposals from suppliers, distributors, etc.) that precede date of original proposal that was used in the development of their original proposal used for award of contract that can be used in support of 5) below.

4. Calculation Method

• Adjustment Amount = (Actual Price – Base Price) × Quantity Required, that have not been delivered.

https://aka.ms/JoinTeamsMeeting?omkt=en-US https://teams.microsoft.com/l/meetup-join/19%3ameeting_MmFiNDBhZTgtMGU4ZS00YTNmLWJmNzUtNjA2NWRjMjlkNTQx%40thread.v2/0?context=%7b%22Tid%22%3a%220693b5ba-4b18-4d7b-9341-f32f400a5494%22%2c%22Oid%22%3a%22cf081e91-bc1c-4d2f-9535-0ba9dc4498ba%22%7d tel:+13609709446,,767501958 tel:8334361163,,767501958 https://dialin.teams.microsoft.com/4c997179-2249-4e53-b877-e71d83c10c7a?id=767501958

• If there is a price change, and part of the delivery was received/installed prior to any proposed price change, but the remaining amount was delivered after the price change, the Adjustment

Amount = (Actual Price – Base Price) x (Quantity Required – Quantity Delivered prior to Price

Change).

• Actual Price is determined using an agreed-upon index or invoice dated within the adjustment period.

• No markup for overhead or profit shall be applied to adjustment amounts unless specifically allowed elsewhere in the contract.

5. Notification and Documentation

• The Contractor must:

o Submit a written request for adjustment within 30 calendar days after the end of the adjustment period.

o Provide sufficient documentation (e.g., original invoices, current invoices, supplier letters, index data) to support the claimed price change.

o Failure to provide timely or adequate documentation may result in denial of the adjustment and not subject to future claims under FAR 52.233-1 – Disputes.

6. Government Review and Approval

• The Contracting Officer will verify the accuracy and applicability of the adjustment request.

• Approved adjustments shall be incorporated via a unilateral or bilateral contract modification.

7. Exclusions

This clause does not apply to:

• Labor cost fluctuations.

• Equipment rental or usage charges.

• Delay costs or schedule impacts resulting from material shortages (unless otherwise provided).

• Differing Site Conditions under FAR 52.236-2

• Changes applicable to any other Changes Clause included in Contract as prescribed

• Errors, omissions, conclusions, interpretations in original proposal under FAR 52.236-3 – Site

Investigation and Conditions Affecting the Work

8. Final Adjustments

• Adjustments under this clause constitute the Contractor’s sole remedy for material cost changes during the contract period. No further equitable adjustment or claim shall be entertained under other clauses (e.g., Changes, Differing Site Conditions) for the same cost elements.