B09_Questions_and_Answers_0001.docx
DOCX document 14 KB Posted
- Attached to
- CHOH HANCOCK MAINT. FACILITY RENOVATION Federal contract opportunity
- Solicitation number
- 140P3021R0020
About this file
This document contains questions and answers regarding Solicitation 140P3021R0020 for the CHOH HANCOCK MAINT. FACILITY RENOVATION project. The solicitation involves renovating the Hancock Maintenance Facility for the Chesapeake and Ohio Canal National Historical Park. Contractors may propose an alternate type of metal building given 12-month lead times for conventional steel structures. Stairs are only required for interior loft or storage access. The fence will be cleared of debris two weeks before demolition. Security cameras will be installed after completion by others and are not the contractor's responsibility.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B09_Attachment_3_B_-_Pathways_for_Comm_Systems_0001.docx | DOCX document | |
| B09_Attachment_3_A_-_Comm_Horizontal_Cabling_0001.docx | DOCX document | |
| Sol_140P3021R0020_Amd_0001.pdf | ||
| B09_Attachment_3_C_-_Hancock_T1_Drawing__0001.pdf | ||
| B08_Attachment_7_-_Gutters_Drawings.pdf | ||
| B08_Attachment_4_-_HVAC_Drawings.pdf | ||
| B08_Attachment_6_-_Fencing_Drawings_and_Photos.pdf | ||
| B08_Attachment_5_-_Metal_Building_Drawing_and_Photos.pdf | ||
| Sol_140P3021R0020.pdf | ||
| B08_Attachment_9_-_Proposal_Submission_Package.docx | DOCX document | |
| B08_Attachment_3_-_IT_and_Electrical_Drawings__Cust__Guide__Load__and_Photos.pdf | ||
| B08_Attachment_8_-__WD_MD20210036_Washington_effective_6-4-21.pdf | ||
| B08_Attachment_2_-_Plumbing_Drawings_and_Photos.pdf | ||
| B08_Attachment_1_-_Hancock_Facility_Aerial_View.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUESTIONS AND ANSWERS
Solicitation 140P3021R0020 – Hancock Renovation
1. Would you except an alternate type of metal building given lead times of 12 months for a conventional steel structure?
Answer: Yes.
2. Please specify the style and location of the stairs in the new building.
Answer: Stairs only as needed to access a framed loft or other interior storage space. Whatever works and keeps within scope.
3. Will the fence be cleared of all debris before demolition?
Answer: Yes, will need two weeks’ notice to allow for our staff to address.
4. There was mention of security cameras being installed on the walk, will this be the responsibility of the contractor or will they be installed after the work is performed by others?
Answer: Not the responsibility of contractor. Camera will be installed after work by others.