QUESTIONS & ANSWERS REGARDING:
SOLICITATION/REQUEST FOR QUOTE NO. 140P3021Q0035
Amendment 0001
PRWI Non- Historic Building Demo
(AMENDMENT 0001)
QUESTIONS RECEIVED AS OF 07/22/2021:
1. Question: Is a bid bond required?
ANSWER: No. This requirement is being treated as a service contract, as there are no construction requirements. Big guarantees are only required when a performance bond and a payment bond are required, per FAR Part 28.
2. Question: What is the project magnitude?
ANSWER: Magnitudes are required per FAR Part 36.204 for Construction solicitations. A magnitude will not be disclosed, as this is being treated as a service.
3. Question: At the Lauber House, is the right side of perimeter fence to be removed?
ANSWER: Yes
4. Question: Is there any drawings that can be provided?
ANSWER: There are no drawings of the structures.
5. Question: Please provide all well and septic tanks locations.
ANSWER: The locations of the 4 wells were shown during the site visit. The exact location of the septic tanks are unknown and will need to be located by the contractor when the project begins.
6. Question: Are storm water and sediment erosion control permits required? If so, who is responsible for the permits?
ANSWER: Any and all permits required to do the described work shall be determined and obtained by the Contractor.
7. Question: Is the area of disturbance over 5,000 square feet?
ANSWER: Yes
8. Question: Is compaction testing required for backfill?
ANSWER: No
9. Question: Does backfill or topsoil dirt need to have a proctored test?
ANSWER: No
10. Question: What certifications are needed for the Superintendent?
ANSWER: The Superintendent does not need to hold any certifications. The superintendent shall be responsible for being onsite all times work is being performed. The superintendent shall be responsible for serving as the main POC to the government and shall direct the work of any and all subcontractors, and any work the prime contractor is performing.
11. Question: Is the superintendent required to be full time?
ANSWER: Yes, a superintendent must be on site anytime the contractor is performing work. If a superintendent cannot be on site for any period of time, an alternate superintendent shall be designated in place, and approved by the COR prior.