About this file

This is Amendment 003 to Solicitation 140P2126Q0060, issued by the National Park Service (NPS), Washington Support Office (WASO) – Wetlands, Coastal and Parks (WCP) Contracting on February 27, 2026. The amendment addresses six questions received from offerors regarding a landscape irrigation and sodding project at 1 Memorial Avenue, Arlington, Virginia 22211, located on NPS property adjacent to Arlington National Cemetery.

The amendment clarifies project specifics: the irrigation tie-in locations are approximately 100 feet west of the Metro Plazas (Areas C and D) along the ANC/NPS property line; the project area extends from the ANC/NPS property line eastward along both sides of Memorial Avenue to Boundary Channel Bridge as outlined in the Statement of Work; no plans or shop drawings are available; and the project limits are defined in the SOW rather than through design documents. Additional clarifications include that Davis-Bacon wage rates apply to this Arlington, Virginia project, and construction cannot begin until the week of July 6th at the earliest due to America 250 celebrations restrictions on Memorial Avenue from May 15 through July 4. Offerors must acknowledge receipt of this amendment prior to the hour and date specified in the original solicitation by completing items 8 and 15 on the form, by acknowledging receipt on each copy of the offer submitted, or by separate letter or electronic communication referencing the solicitation and amendment numbers. Failure to acknowledge receipt at the designated location prior to the specified deadline may result in offer rejection.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: is not is required copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7.ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

PAGESOF

Contractor

The hour and date specified for receipt of Offers to sign this document and return

TIMOTHY WIND

See continuation page

NPS, WASO - WCP Contracting P.O.Box 25287 MS WCP Denver CO 80225

PWA

140P2126Q0060

02/27/2026

02/27/2026

1 2

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140P2126Q0060/0003

Amendment 03 is to:

A) Answer questions received.

1)Could you mark the irrigation tie-in location on satellite imagery (such as Google Earth) or provide a reference point for its exact location?

The irrigation tie-in locations area approximately 100 feet west of the Metro Plazas

(Areas C and D on the attached field map), along the ANC/NPS property line.

2) Can you confirm that the area to be irrigated and sodded terminates where the concrete begins at the Military Women¿s

Memorial?

The Women's Military Memorial (at the western terminus of Memorial Avenue) is not on NPS property, rather part of Arlington National

Cemetery. The project area extends from the

ANC/NPS property line, eastward along both sides of Memorial Avenue to Boundary Channel

Bridge (as outlined in the SOW).

3) Are there any plans or shop drawings for this project?

No, plans or shop drawings are not available for this project; the project limits are spelled out the SOW.

4) What is the address for this project?

The project address is 1 Memorial Avenue, Arlington, VA 22211.

5) Is there an estimated time for work to begin or project start date?

Due to the America 250 celebrations, construction is not permitted along Memorial

Avenue from May 15th through July 4th; at this point, I suspect construction couldn't start until the week of July 6th at the earliest.

6) Do Davis Bacon wages apply to this project?

Yes, current Davis-Bacon wage rates apply (and the project is located in Arlington, VA).

Amendment of solicitation/modification of contract
Contract ID code
Amendment/modification number
Effective date
Requisition/purchase requisition number
Project number
Issued by
Code
Administered by
Code
Name and address of contractor
Code
Facility code
Amendment of solicitation number
Dated
Modification of contract/order number
Dated
This item only applies to amendments of solicitations
Accounting and appropriation data
This item applies only to modifications of contracts/orders.
This change order is issued pursuant to:
The above numbered contract/order is modified to reflect the administrative changes
This supplemental agreement is entered into pursuant to authority of:
Other
Important:
Description of amendment/modification
Name and title of signer
Contractor/offeror
Date signed
Name and title of contracting officer
Signature of Contracting Officer
Date signed
Previous edition unusable
Standard form 30 (rev. 11/2016)
Continuation sheet
Reference Number
Name of Offeror or Contractor
OPTIONAL FORM 336 (4-86))

Sponsored by GSA FAR (48 CFR) 53.110

File details come from the government source that posted it. Updated .