This document is an amendment to Solicitation Number 140P2124R0072 for wayside exhibit planning, design, and fabrication services for Hot Springs National Park. The purpose of this amendment is to respond to questions received regarding the solicitation requirements.
The key details are:
- The solicitation is for 27 wayside exhibits that will completely replace and redesign the existing exhibits at the park. Exhibit styles, sizes, and mounting methods will be determined during the pre-proposal stage.
- The solicitation includes requirements for three custom tactile relief maps, as well as illustrations, which will also be further defined during pre-proposal.
- There are specific requirements regarding the acquisition of use rights and production quality images, with the contractor to budget 3.5% of the planning and design budget for this purpose.
- The solicitation specifies the use of double-sided, direct-printed aluminum panels for the exhibit structures, which the government will not accept alternatives for despite potential heat concerns.
- Proposals are due by 10:00 AM ET on August 22, 2024.
View the file
Other files for this federal contract opportunity
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140P2124R0072 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PHF
Harpers Ferry WV 25425 IDC Building 67 Mather Place DOI, NPS, HFC - Acquisition Managem
PWA
Denver CO 80225 P.O.Box 25287 MS WCP NPS, WASO - WCP Contracting
08/03/20240001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
07/15/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PROPOSALS DUE BY 10:00 AM ET - 08/22/24
The purpose of this amendment is to respond to questions received by the date and time specified in the solicitation, in according to the attached Description of Amendment consisting of three pages.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Sheila Spring
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Solicitation Number 140P2124R0072 Amendment 0001
DESCRIPTION OF AMENDMENT
WAYSIDE EXHIBIT PLANNING, DESIGN, AND FABRICATION FOR
HOT SPRINGS NATIONAL PARK
QUESTION: RESPONSE:
1. Does the NPS have an estimated size for the requested three (3) tactile maps? The custom elements budget seems low for three tactile maps. This budget would probably also eliminate bronze as an option, and not leave any room for illustrations or audio elements.
Size to be determined during pre-proposal. Custom elements budget is only plan and design.
2. Not a question, but it looks like the shipping section 5.1 is leftover from KATM proposal.
The second paragraph is replaced with the following:
Contractor to keep COR updated on shipping and arrival dates of panels, bases, and custom elements.
3. Section 1.0 Project Background - The project background states that this project will “replace existing exhibits and create some new exhibits.”
o In terms of the replacement portion of this job, what all is being replaced? Are you simply looking to update the style and graphics or are you looking to have them completely rewritten and redesigned?
o Can you provide any sample photos of the existing waysides you are looking to replace?
Existing waysides exhibits are being replaced.
Exhibits will be completely rewritten and redesigned.
Two photos are attached to this amendment.
HOSP wayside exhibit 1.jpg HOSP wayside exhibit 2.jpg
4. Section 2.0 General Requirements - The project is specified for (27) wayside exhibits, but nowhere does the solicitation give a breakdown of the exhibit styles, sizes, mounting styles, etc.
o Can the park provide a breakdown of exhibits in order for the offeror to provide more accurate pricing?
o Or is the offeror to create a breakdown themselves showing what the park would be able to do?
o What size are you anticipating the tactile relief maps to be?
o The solicitation states “The contractor shall acquire illustrations.” It does not appear
Offeror to propose approach. Wayside exhibit and tactile map styles and sizes to be determined during pre-proposal. Mounting style shall be in-ground for most exhibits, with a couple base-plate or masonry mounted.
Illustrations are part of custom elements. Specific details about illustrations to be determined during pre-proposal.
there is a section regarding illustrations throughout the rest of the document. Are illustrations a part of this bid at all? How many? Full color/Full size? How detailed?
What is the park looking to depict in these illustrations? What kind of style of illustration is the park looking for?
5. 2.8.1 Use Rights
a. The contractor shall budget 3.5% of the overall planning and design budget for acquisition of use rights and production quality images and other intellectual property used in the exhibits.
b. The contractor shall budget 0.75% of the overall planning and design budget for acquisition of use rights and production quality images and other intellectual property used in the exhibits.
o The two statements above are the exact same statement except for the percentage the contractor should budget. Is it 3.5% or 0.75% of the overall planning and design budget?
Paragraph 2.8.1 is revised to read as follows:
The contractor shall acquire use rights and production-quality copies of all third-party images and other intellectual property required to produce the graphic layouts in wayside exhibits as specified in Attachment A, National Park Service Wayside Exhibit Planning, Design, Fabrication, and Installation Specifications. All images, custom artwork, and other intellectual property shall be able to be displayed by the government in other media to promote or display the wayside exhibit. Any new photography, custom artwork, or intellectual property created under this requirement shall be considered US government works in the public domain and be able to be reproduced based on government need.
All images shall be able to be displayed by the government in other media to promote or display the wayside exhibit. The contractor shall budget 3.5% of the overall planning and design budget for acquisition of use rights and production quality images and other intellectual property used in the exhibits.
The contractor shall budget 0.75% of the overall planning and design budget for acquisition of use rights and production quality images and other intellectual property used in the exhibits. This will be a not-to-exceed (NTE) contract line item (CLIN) for the acquisition of images and usage rights, not including labor. All costs associated with this work will be reimbursed on an actual cost basis. Back up information will be required with invoices requesting payment for this work.
6. Section 4.2.2 Panel Fabrication spec’s double-sided, direct-printed aluminum panels. Section
4.4 Custom Elements states tactiles to be made
out of a material that will “withstand heat and humidity, constant touching, potential theft, and do not become too hot to the touch”.
Shouldn’t this also be a consideration for the panel material? Aluminum panels in the sun and heat of the day get incredibly hot and pose a danger to viewers who may touch the panel.
Can an alternative material be suggested for the panel that would not get as hot as aluminum?
Alternate materials will not be accepted. The panels shall be fabricated as double-sided, direct-printed aluminum panels for outdoor use.
7. Section 5.1 Shipping and Destination Point - The shipping information is listed as the location that was in the bid for Katmai National Park - King Salmon, Alaska. Can you please update with the correct shipping location so freight can be accurately quoted?
The second paragraph is replaced with the following:
Contractor to keep COR updated on shipping and arrival dates of panels, bases, and custom elements.
See 5.2.2 & 5.2.3 for the shipping address.