This document is an amendment to Solicitation 140P2124Q0199 for the procurement of Western Red Cedar wood siding and window units for the HPTC Cane Barracks project.
The key details are as follows:
- The solicitation close date has been changed from August 27, 2024 to August 15, 2024 by 2:00 PM CST.
- The delivery time for all materials has been changed from 45 days after award to 15 days after award.
- Two RFI questions were answered: the required window grid pattern is 6 over 6, and the Western Red Cedar is to be clear and unfinished.
- The contract line items were updated with the new delivery timeframe and obligated amounts for the Western Red Cedar boards and window units.
- No other changes were made to the solicitation.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P2124Q0199_Amd_0002.pdf | ||
| Sol_140P2124Q0199.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140P2124Q0199 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PWA
Denver CO 80225 P.O.Box 25287 MS WCP NPS, WASO - WCP Contracting
08/08/20240001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
07/29/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this amendment is to answer RFI's, change the solicitation close date and change the period of performance/delivery date.
1. The following RFI's are hereby answered:
Q: What grid pattern are you looking for on the windows? A: 6 over 6
Q: Is the Western Red Cedar a clear untreated finish? A: Yes, clear and unfinished.
2. The solicitation due date is hereby changed from 27 August 2024 to 15 August 2024 by
1400 CST.
3. The delivery time for all materials is hereby changed from 45 days after award to 15
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Brian Thornton
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140P2124Q0199/0001 days after award.
No further changes.
Change Item 00010 to read as follows(amount shown is the obligated amount):
00010 Western Red Cedar 1"x10" Boards 400 EA
Product/Service Code: 5650
Product/Service Description: ROOFING AND SIDING
MATERIALS
Period of Performance: 08/19/2024 to 09/02/2024
Change Item 00020 to read as follows(amount shown is the obligated amount):
00020 Western Red Cedar 1"x6" Boards (Batons) 200 EA
Product/Service Code: 5650
Product/Service Description: ROOFING AND SIDING
MATERIALS
Period of Performance: 08/19/2024 to 09/02/2024
Change Item 00030 to read as follows(amount shown is the obligated amount):
00030 Window Units 10 EA
Product/Service Code: 5650
Product/Service Description: ROOFING AND SIDING
MATERIALS
Period of Performance: 08/19/2024 to 09/02/2024