This is a Questions and Answers document for SAFR 319315 – Dock Project, a National Park Service contract for the removal of floating docks at Hyde Street Pier.

The document clarifies three key points regarding project scope and regulatory requirements. First, there are three aluminum gangways at the small boat dock facility, but only two are included in the scope of removal; the third gangway connecting the "long dock" to the "Alma Dock" will be relocated by park staff prior to contractor arrival. Second, contrary to language in the original Scope of Services, removal of the floating docks is permitted under the park's current operational authorities, therefore no permits are required for the removal itself. The contractor is responsible only for procuring permits necessary for the transport and recycling or disposal of materials. Third, the NPS has not obtained a Bay Conservation and Development Commission Federal Consistency Determination, U.S. Army Corps of Engineers Letter of Permission, or Regional Water Board certification, as these are not required. The NPS intends to proceed with notifications rather than permissions from relevant agencies. The work involves only removal of floating appurtenances—the docks float free from the sea bottom and will be unfastened from pilings and removed without any structural modifications or piling removals. No adverse effects are anticipated under National Historic Preservation Act Section 106 requirements, as the small boat dock is not historic.

View the file

Other files

File Type Posted
Sol_140P2026Q0004_Amd_0001.pdf PDF
Sol_140P2026Q0004.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SAFR 319315 – Dock Project

Questions and Answers

Q1. There are actually three aluminum gangways at the small boat dock facility. The 3rd gangway that was not mentioned in the Scope of Services (SOS) connects the “long dock” to the “Alma Dock”. Is that gangway to be removed with the other two gangways?

A1. No. This gangway is not part of the scope of removals. Part staff will move this gangway to the Alma dock prior to the contractor’s arrival to conduct the removals.

Q2. The Regulatory Requirements (SOS page 3 of 4) and the contractor’s responsibility for procuring all necessary project permits. The permitting process can take 6–9 months and typically requires consultants to help navigate coordination with the regulatory agencies. This makes the item difficult to price, particularly on a Lump Sum basis, and the timeline for obtaining all permits is highly uncertain. Would it be possible for the National Park Service to remove the requirement that the contractor secure all permits from the SOS and instead have the NPS take the lead on this item?

A2. This requirement is misstated in the scope of services. Removal of the floating docks is allowed under the parks current operational authorities, therefore, no permits are required. The contractor shall procure any permit(s) required for the transport and recycling / disposal of the materials.

Q3. Has the NPS already received a BCDC Federal Consistency Determination for this work because that would be a likely requirement as well as an U.S. Army Corps of Engineers Letter of Permission and Regional Water Board certification including USACE fish and wildlife consultations.

A3. This requirement is misstated in the scope of services. Removal of the floating docks is allowed under the parks current operational authorities, therefore, no permits are required. The contractor shall procure any permit(s) required for the transport and recycling / disposal of the materials.

The NPS is operating under the assumption that this work can proceed with notifications to, rather than permissions from, agencies with jurisdiction.

The request for services is only for removal of the floating appurtenances attached to Hyde Street Pier, no structural modifications or removals are proposed. The docks float free from the sea bottom and can simply be unfastened from the pilings and removed. It is not proposed to remove any pilings, which penetrate bay mud and habitat, thus we anticipate water quality and habitat monitoring agencies will not be concerned. The NPS has not yet contacted the Bay Conservation and Development Commission however we believe they will be in support of the project as it eliminates shadow over the bay floor, which as you know is an environmental benefit to aquatic habitat. The Port of San Francisco owns the Hyde Street Pier, but not the floating docks, so notification of activity rather than permission from that agency is the likely approach. The small boat dock is not historic thus no adverse effect is anticipated under NPS requirements for NHPA / Section 106 review.