B09_Amend_04_Contractor_Q_and_A_0004.pdf
PDF 173 KB Posted
- Attached to
- GATE 291651 - Rehab Sewer System at Gateway NRA
- Solicitation number
- 140P2022R0053
About this file
This document provides answers to questions regarding solicitation number 140P2022R0053 for the rehabilitation of the wastewater system at Floyd Bennett Field in Gateway National Recreation Area, New York. The solicitation is for a design-build contract issued by the National Park Service National Office within the Department of the Interior. A bid bond is not required for Phase 1 submissions but is required as part of the Phase 2 price proposal. The document also clarifies that the onsite quality control specialist and onsite safety specialist roles may be fulfilled by the same individual.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GATE 291651
Solicitation Number 140P2022R0053
Question Response
Amendment 04 For Phase 1, is a bond required with this submission?
In accordance with Section L, provision Instructions For The Submission of Offers and Other Information – Competitive Source Selection, paragraph E, bid bonds are not required for Phase I. Bid bonds are required as a component of the Phase 2 Price Proposal per paragraph G.3.
and 4.
Can the On‐Site QC Specialist and the On‐Site Safety Specialist be the same person completing a combined role?
Yes this would be acceptable.