2020.06.01 CURE Elk Creek VC SPECIFICATIONS.pdf
PDF 42 MB Posted
- Attached to
- Curecanti National Recreation Area Rehabilitate
- Solicitation number
- 140P2020R0048
About this file
This document provides details for a federal solicitation to rehabilitate the Elk Creek Visitor Center at Curecanti National Recreation Area in Colorado. Solicitation number 140P2020R0048 seeks to address visitor safety, accessibility, and operational needs through renovations to the center. The National Park Service is the contracting agency, with proposals due by June 1, 2020. The scope of work involves rehabilitating building infrastructure and grounds to improve the visitor experience in accordance with accessibility standards. This project falls under the Department of the Interior and represents an opportunity for contractors to provide construction and design services for critical facility upgrades at a national recreation area.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P2020R0048_Amd_0004.pdf | ||
| Q16 - Gas Piping Isometric Sketch_0003.pdf | ||
| 0003-Q and A Rehabilitate Elk Creek Visitor Center_0003.docx | DOCX document | |
| Sol_140P2020R0048_Amd_0003.pdf | ||
| B08_Solit_Equals_0003.doc | DOC document | |
| 0002-QA Rehabilitate Elk Creek Visitor Center_0002.docx | DOCX document | |
| Sol_140P2020R0048_Amd_0002.pdf | ||
| Pre-Proposal Site Visit_0001.pdf | ||
| 0001-Q and A Rehabilitate Elk Creek Visitor Center_0001.docx | DOCX document | |
| Sol_140P2020R0048_Amd_0001.pdf | ||
| 2020.06.02 - Elk Creek VC Rehabilitation - Final CD - Stamped Drawings.pdf | ||
| 140P2020R0048.pdf | ||
| Sol_140P2020R0048.pdf | ||
| Past_Performance_Questionnaire.docx | DOCX document | |
| WD CO20200001 1-24-2020.pdf | ||
| Project_Experience_Questionnaire.docx | DOCX document |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Curecanti National Recreation Area
Rehabilitate Elk Creek Visitor Center
Photo courtesy of NPS, ca. 1968
FINAL Construction Documents Project Specifications
June 1, 2020
PMIS 187989
CURE - 187989 TOC
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 – Summary of Work
01 26 01 – Contract Modification Procedures
01 27 00 – Definition of Contract Line Items
01 31 00 – Project Management & Coordination
01 32 16 – Construction Schedule
01 32 33 – Photo Documentation for Historic Preservation Projects
01 33 23 – Submittal Procedures
01 35 13.22 – Archeological Protection
01 35 23 – Safety Requirements
01 35 91 – Historic Preservation Treatment Procedures
01 40 00 – Quality Requirements
01 42 00 – Reference Standards
01 50 00 – Temporary Facilities and Controls
01 56 39 – Tree Protection
01 57 19.11 – Indoor Air Quality Management
01 57 19.12 – Noise & Acoustics Management
01 57 23 – Temporary Storm Water Pollution Prevention
01 67 00 – Product Requirements
01 73 29 – Cutting and Patching
01 73 40 – Execution
01 74 19 – Construction Waste Management and Disposal
01 77 00 – Closeout Procedures
01 78 23 – Operation and Maintenance Data
01 79 00 – Demonstration and Training
01 81 13 – Sustainable Design Requirements
01 91 14 – Total Building Commissioning
DIVISION 02 – EXISTING CONDITIONS
02 41 00 – Site Demolition
02 41 91 – Selective Historic Demolition
DIVISION 03 – CONCRETE
03 20 00 – Concrete Reinforcing
03 30 00 – Cast-in-Place Concrete
DIVISION 04 – MASONRY
04 20 00 – Unit Masonry
DIVISION 05 – METALS
05 12 00 – Structural Steel Framing
05 52 13 – Pipe and Tube Railings
DIVISION 06 – WOOD & PLASTICS
06 01 40.19 – Architectural Woodwork Restoration
06 10 00 – Rough Carpentry
06 20 00 – Finish Carpentry
06 41 00 – Architectural Wood Casework
06 83 16 – Fiberglass Reinforced Paneling
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
07 18 13 – Liquid Applied Pedestrian Traffic Waterproofing
07 21 00 – Thermal Insulation
07 31 29 – Wood Shakes
07 62 00 – Sheet Metal Flashing and Trim
07 92 00 – Joint Sealants
DIVISION 08 – OPENINGS
08 01 52.91 – Wood Window Restoration
08 11 13 – Hollow Metal Doors and Frames
08 14 16 – Flush Wood Doors
08 43 13 – Aluminum Framed Storefronts
08 71 00 – Door Hardware
08 80 00 - Glazing
DIVISION 09 – FINISHES
09 21 16 – Gypsum Board Assemblies
09 24 23 – Portland Cement Stucco
09 30 00 – Tiling
09 51 00 – Acoustical Ceilings
09 65 00 – Resilient Flooring
09 68 13 – Tile Carpeting
09 90 00 – Painting and Coating
DIVISION 10 – SPECIALTIES
10 14 00 – Signage
10 14 26 – Post and Panel Signage
10 28 00 – Toilet, Bath, and Laundry Accessories
10 44 00 – Fire Protection Specialties
10 81 19 – Rodent Control
DIVISION 11 – EQUIPMENT
Not Used
DIVISION 12 – FURNISHINGS
12 24 00 – Window Shades
12 36 00 – Countertops
DIVISION 13 – SPECIAL CONSTRUCTION
Not Used
DIVISION 14– CONVEYING EQUIPMENT
14 20 10 – Passenger Elevators
DIVISION 21 – FIRE SUPPRESSION
21 00 00 – Fire Suppression Basic Requirements
21 05 00 – Common Work Results For Fire Suppression
21 13 00 – Fire Suppression Sprinkler Systems
DIVISION 22 – PLUMBING
22 05 00 - Common Work Results for Plumbing
22 05 19 - Meters and Gages for Plumbing Piping
22 05 23 - General-Duty Valves for Plumbing Piping
22 05 29 - Hangers and Supports for Plumbing Piping and Equipment
22 05 48.13 - Vibration Controls for Plumbing Piping and Equipment
22 07 19 - Plumbing Piping Insulation
22 08 00 - Commissioning of Plumbing
22 11 16 - Domestic Water Piping
22 11 19 - Domestic Water Piping Specialties
22 11 23.21 - Inline, Domestic-Water Pumps
22 13 16 - Sanitary Waste and Vent Piping
22 13 19 - Sanitary Waste Piping Specialties
22 13 23 - Sanitary Waste Interceptors
22 14 29 - Sump Pumps
22 33 00 - Electric, Domestic-Water Heaters
22 41 00 - Plumbing Fixtures
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING
23 05 00 - Common Work Results for HVAC
23 05 13 - Common Motor Requirements for HVAC Equipment
23 05 29 - Hangers and Supports for HVAC Piping and Equipment
23 05 48.13 - Vibration Controls for HVAC
23 05 93 - Testing, Adjusting, and Balancing for HVAC
23 07 13 - Duct Insulation
23 07 19 - HVAC Piping Insulation
23 08 00 - Commissioning of HVAC
23 11 26 - Facility Liquefied-Petroleum Gas Piping
23 23 00 - Refrigerant Piping
23 31 13 - Metal Ducts
23 33 00 - Air Duct Accessories
23 34 16 - Centrifugal HVAC Fans
23 37 13.13 - Air Diffusers
23 37 13.23 - Registers and Grilles
23 54 16.13 - Gas-Fired Furnaces
23 82 39.19 - Wall and Ceiling Unit Heaters
DIVISION 26 – ELECTRICAL
26 05 00 – Common Work Results for Electrical
26 05 19 – Low-Voltage Electrical Power Conductors and Cables
26 05 26 – Grounding and Bonding for Electrical Systems
26 05 29 – Hangers and Supports for Electrical Systems 26 05 33 – Raceway and Boxes for Electrical Systems
26 05 44 – Sleeves and Sleeve Seals for Electrical Raceways and Cabling
26 05 53 – Identification for Electrical Systems
26 05 73 – Electrical Systems Studies
26 08 00 – Commissioning of Electrical Systems
26 09 23 – Lighting Control Devices
26 09 43 – Network Lighting Controls
26 24 14 - Panelboards
26 27 13 – Electricity Metering
26 27 26 – Wiring Devices
26 28 16 – Enclosed Switches and Circuit Breakers
26 43 13 – Transient-Voltage Suppression for Low-Voltage Electrical
26 51 00 – Lighting Fixtures
DIVISION 27 – COMMUNICATIONS
27 05 26 – Grounding and Bonding for Communications Systems
27 05 28 – Pathways for Communications Systems
27 05 44 – Sleeves and Sleeve Seals for Communication Pathways and Cabling
27 10 00 – Communications Equipment Room Fittings
27 15 13 – Communications Copper Horizontal Cabling
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 00 01 – Electronic Safety Basic Requirements
28 31 00 – Fire Detection and Alarm
DIVISION 31 – EARTHWORK
31 10 00 – Site Clearing
31 20 00 – Earth Moving
31 22 19 - Topsoil
31 23 33 – Trenching and Backfilling
31 31 50 - Watering
31 37 19 – Boulders
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 12 16 – Asphalt Paving
32 13 13 – Concrete Paving
32 13 73 – Concrete Paving Joint Sealants
32 17 23 – Pavement Markings
32 33 00 – Site Furnishings
32 84 00 – Irrigation
32 91 13 – Soil Preparation
32 92 19 – Seeding and Mulching
32 93 00 – Planting
DIVISION 33 – UTILITES
33 05 27 – Tracer Wire Systems
33 11 00 – Water Utility Distribution Piping
33 31 00 – Sanitary Utility Sewerage Piping
APPENDIX
1. Appendix A: Geotechnical Engineering Report – Proposed Elk Creek Visitor Center Improvements, dated September 17, 2019, prepared by Yeh and Associates, Inc.
2. Appendix B: Asbestos and Hazmat Survey and Assessment, Curecanti National Recreation Area, dated February 2016, prepared by Michael Baker International.
THIS PAGE INTENTIONALLY LEFT BLANK
CURE 187989 00 01 07 - 1
SEALS PAGE
SECTION 00 01 07 - SEALS PAGE
PART 1 - GENERAL
1.1 SUMMARY
A. Professional seals by Design Professionals and others responsible for preparing Construction
Documents:
1. Civil Engineer:
2. Landscape Architect:
3. Architect:
PA
TR
IC
IA J. SULLIVAN
P R
O
F ESS IONA L ENGIN
EE
R
C O
LO
RA DO L ICENSE
D
33931
05/26/2020
01 57 23 31 10 00 31 20 00 31 23 33 32 12 16 32 13 73 32 17 23 33 05 27 33 11 00 33 31 00
6/1/2020
CURE 187989 00 01 07 - 2
4. Structural Engineer
5. Mechanical Engineer:
6. Electrical Engineer:
6/1/2020
CURE 187989 00 01 07 - 3
7. Fire Protection
6.1.2020
CURE 187989 00 01 07 - 4
CURE - 187989 01 11 00 - 1
091015 SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Government Furnished Materials.
3. Contractor use of site.
4. Public use of site.
5. Occupancy requirements for buildings.
6. Conduct of Operations.
7. Work Restrictions.
8. Special Construction Requirements.
9. Soils Investigation Report.
10. Additional Reports.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Curecanti National Recreation Area, Elk Creek Visitor Center. Located approximately 20 miles west of Gunnison, Colorado. The Visitor Center is located to the south of
Highway 50 and accessed via an entrance road that connects the Elk Creek Visitor Center to Highway
50.
B. The Work consists of the following:
1. The Work includes the rehabilitation of the Visitor Center, including site and parking lot related improvements to provide outdoor accessibility (ABAAS) upgrades. All existing building systems will be replaced with new systems (HVAC equipment, electrical equipment and branch wiring, light fixtures, plumbing fixtures, cold water, hot water, wastewater and vent piping all to be replaced.) Additionally, a new fire suppression system is being added to the building. Selective demolition to occur (interior and exterior) to accommodate the proposed modifications. Exterior building repair/rehabilitation work will include a new roof to match the original (cedar shakes), replacement of existing weathered/worn cedar shakes at the observation deck and ramp guardwalls, repairs to exterior stucco (where failing), and improvements to the observation deck and ramp walking surface. Interior rehabilitation consists of spatial modifications to support staff needs as well as meet functional requirements of a modern visitor center. A new interior elevator will be installed to provide ABAAS access to the Main Level. Existing restrooms will undergo modifications to provide compliance with ABAAS. Exterior site related improvements consist of providing (2) accessible parking spaces adjacent to the Visitor
Center and regrading a portion of the existing parking lot to provide oversize vehicle
ABAAS parking spaces. The site walk/approach to the building will be replaced and regraded to allow for an ABAAS approach. The existing courtyard will be improved to provide more opportunities for park programming and visitor interpretation/education.
CURE - 187989 01 11 00 - 2
a. Work associated with regrading of the parking lot to provide accessibility oversize vehicle parking spots and modifications to existing islands to provide an accessible path from the parking spots to the Visitor Center shall be scheduled to occur toward the beginning of the project. All related parking lot work shall be substantially complete, such that the contractor may re-allocate the staging area as shown on sheet
G0.8 for “high season” by June 30th, 2021.
C. Project will be constructed under a single prime contract.
1.3 WORK PHASES
A. The Work shall be conducted in one phase – however, work related to the regrading of the parking lot shall be substantially complete by June 30th, 2021 (as noted above in 1.2, B, a) so that the parking lot can be expanded to accommodate park visitors during the busy season at Elk Creek.
1.4 WORK UNDER OTHER CONTRACTS
A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate the Work of this Contract with work performed under separate contracts.
B. Preceding Work: Government will award separate contract(s) for the following construction operations at Project site. Those contracts may be in progress when the work of this contract is underway.
1. CURE Temporary Trailers for Visitor Contact and Staff Offices: A separate contract will be awarded to the successful bidder (contractor TBD) for the procurement, installation, maintenance, and removal of the temporary Visitor Contact and Staff Office trailers (shown on the staging plans in this contract).
1.5 CONTRACTOR USE OF SITE
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits: Confine constructions operations to the area as indicated on the Staging Plan included in the drawings.
2. Limit site disturbance, including earthwork and clearing of vegetation, to 20 feet beyond building perimeter; 10 feet beyond surface walkways, patios, surface parking, and utilities less than 12 inches in diameter; 15 feet beyond primary roadway curbs and main utility branch trenches; and 25 feet beyond constructed areas with permeable surfaces (such as pervious paving areas, storm water detention facilities, and fields) that require additional staging areas in order to limit compaction in the constructed area.
a. Please note that the landscaped area immediately east of the Visitor Center
(beginning at the exterior face of the building) is in an archeologically sensitive zone. Absolutely no site/ground disturbance is allowed in this area.
CURE - 187989 01 11 00 - 3
B. Storage of Materials: Confine storage of materials to the area indicated on the Staging Plan included in the drawings.
C. Protection of Historic Fabric/Features:
1. Contractor is required to attend a briefing with CURE historic preservation staff prior to commencing construction work onsite. Contractor superintendent will be provided information regarding allowable behaviors onsite as it relates to impact on historic fabric and features.
2. Contractor is required to brief each contractor and subcontractor staff member of the same information immediately upon arrival at the jobsite.
3. Contractor is required to keep a log of contractor/subcontractor employees who have been briefed including name, company, position, and briefing date. Records shall be updated and provided to the Contracting Officer bi-weekly.
D. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with
Contracting Officer and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
6. Please note that the landscaped area immediately east of the Visitor Center (beginning at the exterior face of the building) is in an archeologically sensitive zone. Absolutely no site/ground disturbance is allowed in this area.
E. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to
Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
F. Construction Camp: Establishment of a camp within the park will not be permitted.
G. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
CURE - 187989 01 11 00 - 4
1.6 PUBLIC USE OF SITE
A. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public.
Road closures will be permitted, when required, upon specific approval of Contracting Officer for a maximum of 1-hour.
1.7 OCCUPANCY REQUIRMENTS FOR BUILIDINGS
A. Existing Buildings
1. Partial Government Occupancy: Government will occupy the premises during entire construction period, with the exception of areas under construction. Cooperate with
Government during construction operations to minimize conflicts and facilitate
Government usage. Perform the Work so as not to interfere with Government’s operations.
a. The northern portion of the parking lot will be closed to the public during construction. Contractor shall maintain access to the parking lot from the south entrance drive. Refer to the contractor staging plans within the drawings. The
Headquarters building on the south side of the parking lot will remain in operation.
Maintain walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the Contracting Officer (CO).
b. The existing telecommunication equipment in the Lower Level of the Visitor Center needs to stay online during construction activities. Temporary partitions shall be included to keep the existing equipment clean, safe and in operation. Access for park staff shall be provided.
1.8 CONDUCT OF OPERATIONS
A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests 72 hours in advance of the work to the
Contracting Officer for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.9 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of
7:00 a.m. to 5:00 p.m., Monday through Friday, except when otherwise indicated.
1. Weekend Hours: Not allowed unless approved in advance by Contracting Officer. Submit requests 72 hours in advance to Contracting Officer for approval.
CURE - 187989 01 11 00 - 5
2. Early Morning Hours: Not allowed unless approved in advance by Contracting Officer.
Submit requests 72 hours in advance to Contracting Officer for approval.
3. Hours for Core Drilling or other noisy activity: No restrictions
B. Existing Utilities
1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than two days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
3. Hours for Utility Shutdowns: 8-hours maximum for water and wastewater service. 1-hour maximum for electrical service.
D. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes.
1.10 SPECIAL CONSTRUCTION REQUIREMENTS
A. Project Website: A project website administered by the NPS will be used for purposes of managing communication and documents during the construction stage.
1. See Section 01 31 00 “Project Management and Coordination” for requirements on using the Project Website.
1.11 SOILS INVESTIGATION REPORT
A. A soils investigation report entitled Geotechnical Engineering Report, Proposed Elk Creek Visitor
Center Improvements, September 17, 2019 has been prepared by Yeh and Associates, Inc.
B. A copy of the report is available to all plan holders with this package.
C. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.
1.12 ADDITIONAL REPORTS
A. A report entitled Asbestos and Hazmat Survey and Assessment, dated February 2016 has been prepared by Michael Baker International.
CURE - 187989 01 11 00 - 6
B. A copy of the report is available to all plan holders with this package.
C. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
CURE - 187989 01 26 01 - 1
031414 CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. The work of this section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager, Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
CURE - 187989 01 26 01 - 2
6. Scheduling
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating
General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: This is the hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:
1) Social Security
2) Medicare
3) Workers Compensation– Policy and company calculation to be made available.
4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.
5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.
CURE - 187989 01 26 01 - 3
6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General
Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement.
Contractor may utilize the government provided Contractor Estimate Form, or their http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank http://www.nps.gov/dscw/publicforms.htm#ct
CURE - 187989 01 26 01 - 4
own form, provided that it contains the same information and level of detail as the Gov’t provided form.
3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction
Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.
Contractor’s failure to submit within the specified time frame will be construed as the
Contractor waiving the right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.
5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.
Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. The labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by the NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for the work being performed.
2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.
3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region)
b. Construction Blue Book
CURE - 187989 01 26 01 - 5
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals.
Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.
6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the
US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.
8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead………………10%
Profit…………………...7.35%
2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
CURE - 187989 01 26 01 - 6
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 012601
CURE - 187989 01 27 00 - 1
082714 DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item No.01: Base Project – Visitor Center Rehabilitation – Building Elements
1. This item consists of the base project/building related work as illustrated in the CURE
187989 Contract Documents. Work includes but is not limited to complete replacement of the existing mechanical, electrical and plumbing systems, including the installation of a new hybrid wet/dry pipe fire suppression system. Architectural upgrades include the installation of a new elevator, reconfigured entry at the lower level, installation of new storefront window framing systems, reconfigured staff and work area, reconfigured restrooms to provide ABAAS compliance, and new finishes throughout. Exterior stucco will be patched and repaired where damaged, the existing roofing material will be removed and replaced with historically appropriate material (cedar shakes), the existing exterior ramp and observation deck will be repaired, and the entire Visitor Center exterior will be repainted/recoated.
2. No separate measurement for payment will be made.
3. Payment will be made at the contract lump sum price.
B. Contract Line Item No.02: Base Project – Visitor Center Rehabilitation – Site Elements
1. This item consists of the base project/site related work as illustrated in the CURE 187989
Contract Documents. Site work includes, but is not limited to, providing accessible parking adjacent to the Visitor Center as well as regrading and resurfacing of the approach to connect the accessible parking to the Visitor Center with an accessible route. Regrading at the parking lot will be conducted to provide accessible oversize vehicle parking spots.
The courtyard will receive upgrades to further support park educational programming.
2. No separate measurement for payment will be made.
3. Payment will be made at the contract lump sum price.
C. Contract Line Item No. 3: Unit Cost #1 – Unit Cost to Remove Bedrock
CURE - 187989 01 27 00 - 2
082714 DEFINITION OF CONTRACT LINE ITEMS
1. This item consists of the removal of bedrock, in the existing unexcavated portion of the crawl space where the future Water Entry Room (Room 113) will be located.
2. No separate measurement for payment will be made.
3. Payment will be made at the contract unit price per square foot for concrete repair. Assume
5 CY of bedrock removal.
END OF SECTION
CURE - 187989 01 31 00 - 1
091015 PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative provisions for coordinating construction operations on
Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination.
3. Submittals/Coordination Drawings.
4. Requests for Information (RFIs).
5. CMR provided file sharing platform.
6. Project meetings.
7. Environmental Coordination.
8. Permits
B. Related Requirements:
1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.
4. Section 01 91 14 “Total Building Commissioning” for coordinating the work with Owner’s
Commissioning Authority.
1.2 DEFINITIONS
A. Agency with Jurisdiction
B. Construction Permits – Contractor Provided
C. Government Furnished Permits
1.3 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the
Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
http://www.nps.gov/dscw/definitionsdc_a.htm#awj http://www.nps.gov/dscw/definitionsdc_c.htm#cpcp http://www.nps.gov/dscw/definitionsdc_g.htm#gfperm
CURE - 187989 01 31 00 - 2
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Permit requirements.
7. Pre-installation conferences.
8. Project closeout activities.
9. Commissioning activities.
1.4 SUBMITTALS
A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.
1. Content: Project-specific information, drawn accurately to scale. Do not base
Coordination Drawings on reproductions of the Contract Documents or standard printed data. Include the following information, as applicable:
a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.
b. Indicate dimensions shown on the Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to the Contracting Officer (CO) for resolution of such conflicts.
c. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.
d. Show location and size of access doors required for access to concealed dampers, valves, and other controls.
e. Indicate required installation sequences.
2. Sheet Size: At least 8-1/2 by 11 inches (215 by 280 mm) but no larger than 30 by 40 inches
(750 by 1000 mm).
CURE - 187989 01 31 00 - 3
3. Number of Copies: Submit two opaque copies of each submittal. Contracting Officer will return one copy
4. Refer to individual Sections for Coordination Drawing requirements for Work in those
Section
B. Coordination Drawing Organization: Organize coordination drawings as follows:
1. Floor Plans and Reflected Ceiling Plans: Show architectural and structural elements, and mechanical, plumbing, fire-protection, fire-alarm, and electrical Work. Show locations of visible ceiling-mounted devices relative to acoustical ceiling grid. Supplement plan drawings with section drawings where required to adequately represent the Work.
2. Plenum Space: Indicate subframing for support of ceiling and wall systems, mechanical and electrical equipment, and related Work. Locate components within ceiling plenum to accommodate layout of light fixtures indicated on Drawings. Indicate areas of conflict between light fixtures and other components.
3. Mechanical Rooms: Provide coordination drawings for mechanical rooms showing plans and elevations of mechanical, plumbing, fire-protection, fire-alarm, and electrical equipment.
4. Structural Penetrations: Indicate penetrations and openings required for all disciplines.
5. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, door floor closers, slab depressions for floor finishes, curbs and housekeeping pads, and similar items.
6. Mechanical and Plumbing Work: Show the following:
a. Sizes and bottom elevations of ductwork, piping, and conduit runs, including insulation, bracing, flanges, and support systems.
b. Dimensions of major components, such as dampers, valves, diffusers, access doors, cleanouts and electrical distribution equipment.
c. Fire-rated enclosures around ductwork.
7. Electrical Work: Show the following:
a. Runs of vertical and horizontal conduit 1-1/4 inches (32 mm) in diameter and larger.
b. Light fixture, exit light, emergency battery pack, smoke detector, and other fire-alarm locations.
c. Panel board, switch board, switchgear, transformer, busway, generator, and motor control center locations.
d. Location of pull boxes and junction boxes, dimensioned from column center lines.
8. Fire-Protection System: Show the following:
a. Locations of standpipes, mains piping, branch lines, pipe drops, and sprinkler heads.
9. Review: Contracting Officer (CO) will review coordination drawings to confirm that the
Work is being coordinated, but not for the details of the coordination, which are
Contractor's responsibility. If CO determines that coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, CO will so inform
Contractor, who shall make changes as directed and resubmit.
10. Coordination Drawing Prints: Prepare coordination drawing prints according to requirements in Section 01 33 23 "Submittal Procedures."
CURE - 187989 01 31 00 - 4
C. Coordination Digital Data Files: Prepare coordination digital data files according to the following requirements:
1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings.
2. File Preparation Format: AutoCad.dwg, Version 2010, operating in Microsoft Windows operating system.
3. File Submittal Format: Submit or post coordination drawing files using Portable Document
Format (PDF) file format.
4. Contracting Officer (CO) will furnish Contractor one set of digital data files
(AutoCad.dwg) of Drawings for use in preparing coordination digital data files.
a. CO makes no representations as to the accuracy or completeness of digital data files as they relate to Drawings.
b. Digital Data Software Program: Drawings are available in AutoCad.dwg.
D. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.
1. Letter designating Project Superintendent.
2. Construction Schedule.
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention Plan.
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.
7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the
Contactor and all subcontractors.
8. Waste Management Plan.
9. Quality Control Plan.
10. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP).
11. Indoor Air Quality (IAQ) Management Plan.
12. Contractors Commissioning Plan.
13. Historic Preservation Treatment Plan.
14. List of Required Construction Permits. Include the following information for each permit:
a. Name of Permit.
b. The Agency(ies) with Jurisdiction issuing the permit.
c. Information required from the Government to complete the permit application.
E. All items listed must be provided to the Contracting Officer before the Pre-Construction
Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
CURE - 187989 01 31 00 - 5
1.5 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of the
Contract Documents, Contractor shall prepare and submit an RFI utilizing the form created on the CMR provided file sharing program.
1. CO will not respond to RFIs submitted by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially.
2. Date.
3. RFI subject.
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
8. Contractor's signature.
9. Requested date for response.
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Form: Complete the RFI Form on the CMR provided file sharing website as follows:
1. Enter the general information at the top of the form.
2. Under the “Action” section at the bottom of the form, select “Question” then select “CMR” in the drop-down of the “Send to” box.
3. Enter the details of the question and attach related documents.
4. Select “Submit Form” at the bottom of the page.
D. Contracting Officer’s Action: CO will review each RFI, determine action required, and respond.
CO will determine the critical nature of each RFI and issue a response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
CURE - 187989 01 31 00 - 6
2. CO's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.
3. CO's action on RFIs may result in the need for a change to the Contract Time or the
Contract Sum. All contract changes will be processed following the terms and conditions of the contract.
1.6 PROJECT WEB SITE
A. Use the CMR provided file sharing website for communication throughout the contract period.
The CMR provided file sharing website will be used for the following functions:
1. Project directory.
2. Project correspondence.
3. Meeting agendas and minutes.
4. Contract modifications forms and logs.
5. RFI form and processing.
6. Task and issue management.
7. Photo documentation.
8. Baseline schedule, schedule updates and calendar management.
9. Submittal form and processing.
10. Payment coordination documentation.
11. Drawing and specification document hosting, viewing, and updating.
12. Online document collaboration.
13. Reminder and tracking functions.
14. Archiving functions.
15. Notification of submittal and RFI statuses and current responsible party.
16. Permits and addendums
B. Some documents however are not suitable to be shared using the CMR provided file sharing website. Documents containing Personal Identifying Information (PII) (i.e. certified payrolls) shall not be shared using the CMR provided file sharing website and shall be coordinated with the Project team as appropriate.
C. Submit to the CO a list of all employees who will need access to the website.