0001-Q and A Rehabilitate Elk Creek Visitor Center_0001.docx

DOCX document 13 KB Posted

Attached to
Curecanti National Recreation Area Rehabilitate
Solicitation number
140P2020R0048
Issued by

About this file

This document contains questions and answers related to solicitation number 140P2020R0048 from the National Park Service to rehabilitate the Elk Creek Visitor Center at Curecanti National Recreation Area in Gunnison, Colorado. The questions and answers provide clarification on aspects of the project, including confirmation that the architectural and engineering firm that developed the drawings and specifications will participate in the pre-bid conference, clarification that a separate contract exists for moving office furniture, and confirmation of separate trailer accommodations for government construction personnel on site. Uncertainty is noted regarding potential impacts to the scheduled Colorado Department of Transportation highway project near the site in 2021 due to COVID-19. Bidders are directed to rely only on information in the solicitation, drawings and specifications for their proposals.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Rehabilitate Elk Creek Visitor Center, CURE 187989 0001-Questions and Answers June 29, 2020

Q1: Will the A&E that developed the drawings and specifications be part of the pre-bid of this project?

A1: Yes.

Q2: Are the GC responsible for moving office furniture for the construction?

A2: No. There is a separate contract for the moving service.

Q3: There is a separate trailer for government construction personnel on site. Is that correct?

A3: Yes. Division 01-General requirement 01 50 00 - 3 2.2 TEMPORARY FACILITIES.

Q4: Is the CDOT highway project on Hwy 50 still on schedule for summer of 2021 with the COVID 19 situation?

A4: That information is unknown at this time. Please use only the information from the solicitation, drawings and specifications for your proposal. If unforeseen site condition arise after award, then Government will work with the Contractor to modify accordingly.