Shoreline Stabilization Statement of Work
View the file
Other files
| File | Type | Posted |
|---|---|---|
| D01_Attachment_2_SOW_COLO_221757B.pdf | ||
| D01_Contract_140P2019C0062.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Colonial National Historical Park Yorktown, Virginia
SOLICITATION 140P2019R0069
Repair and Stabilize York River Shoreline
COLO 253093B
DESIGN-BUILD (DB) PROJECT SCOPE
(DB Request for Proposal (RFP))
05/22/2019
NATIONAL PARK SERVICE
DENVER SERVICE CENTER
COLO 253093B | Page 2 of 35
Table of Contents
1.0.............................................................................................................................................................. PROJECT
INTRODUCTION
1.1 SCOPE
1.2 NPS/DSC SHAREPOINT PROJECT WEBSITE
1.3 LOCATION
1.4 BACKGROUND
1.5 DESCRIPTION
1.6 SCHEDULE
1.7 INFORMATION
1.8 DATA AND MATERIALS TO BE PROVIDED BY THE NPS
2.0.............................................................................................................................................................. PROJECT
REQUIREMENTS
2.1 GENERAL REQUIREMENTS
2.2 DESIGN REQUIREMENTS
2.3 CONSTRUCTION REQUIREMENTS
2.4 FORMS
TIRES ............................................................................. ERROR! BOOKMARK NOT DEFINED.
3.0................................................................................................................................................. PERFORMANCE
REQUIREMENTS
3.1 DESIGN IMPERATIVES
3.2 SUSTAINABILITY
3.3 INTEGRATED DESIGN PRINCIPLES
4.0........................................................................................................................................................ TECHNICAL
REQUIREMENTS
5.0................................................................................................................................................ ATTACHMENTS
COLO 253093B | Page 3 of 35
1.0 PROJECT INTRODUCTION
Park Alpha and PMIS Number: COLO 253093B
Project Title: Repair and Stabilize York River Shoreline at Indian Field Creek
Project Drawing Number: 333/152586
1.1 Scope
In accordance with the terms and conditions of the Contract, the Design-Build Contractor (DBC) shall perform the work of this Request for Proposal (RFP) for the National Park Service (NPS) as described below.
All Architect/Engineer (A/E) Services required in this RFP shall be performed by licensed Architects and
Engineers registered in the State of Virginia.
The work of this RFP shall be performed in accordance with the Denver Service Center (DSC) Design-
Build (DB) Workflows website, https://www.nps.gov/dscw/designbuild.htm.
Listed on the DB homepage are links to the design phases which describe the required workflow process from Predesign (PD) through Construction Documents (CD). Each design phase webpage contains hypertext links to definitions, forms, templates, samples and guidelines.
The DB homepage also includes links to the Design Standards and Design Deliverables sections which provide design requirements and criteria that shall be used for completing the work of this contract:
Design Standards (https://www.nps.gov/dscw/dstandards.htm): Design Standards arranged by discipline and/or specialty.
DB Design Deliverables – Content and Format Requirements (https://www.nps.gov/dscw/del_designbuild.htm):
o Design phase submission requirements for:
Technical content
Submission format (hard-copy and electronic)
In addition, there is an Information section (https://www.nps.gov/dscw/information.htm) with links directly to the following sections:
Definitions (https://www.nps.gov/dscw/definitions.htm): A list of terms relevant to design and construction in national parks.
Forms/Templates/Samples/Guidelines (https://www.nps.gov/dscw/publicforms.htm): A listing of forms/templates/samples/guidelines used for a typical project.
Laws/Regulations/Policies/Guidance (https://www.nps.gov/dscw/laws-policies.htm): A listing of sources for retrieving laws/regulations/policies/guidance applicable to NPS projects.
Quality Assurance Guideline & Review Checklists
(https://www.nps.gov/dscw/qaguideline.htm): Overview of the DSC Quality Assurance (QA)
Process for reviewing Design Documents.
https://www.nps.gov/dscw/designbuild.htm https://www.nps.gov/dscw/dstandards.htm https://www.nps.gov/dscw/del_designbuild.htm https://www.nps.gov/dscw/information.htm https://www.nps.gov/dscw/definitions.htm https://www.nps.gov/dscw/publicforms.htm https://www.nps.gov/dscw/laws-policies.htm https://www.nps.gov/dscw/qaguideline.htm
COLO 253093B | Page 4 of 35
In case of conflict between this RFP and the DSC DB Workflows website, https://www.nps.gov/dscw/designbuild.htm, this RFP will take precedence over and will be used in lieu of such conflicting portions.
The A/E remains fully responsible for determining if the standards or provisions cited on the DSC DB
Workflows website, https://www.nps.gov/dscw/designbuild.htm, have been revised or updated. Any such conflicts between the website and the identified standard or provisions shall be brought to the attention of the Contracting Officer (CO) requesting direction.
1.2 NPS/DSC SharePoint Project Website
Use the NPS/DSC SharePoint Project website for purposes of hosting and managing project communication and documentation until Final Completion. The NPS/DSC SharePoint Project website will be used for the following functions:
Project directory
Project correspondence
Meeting agendas and minutes
Contract modifications documentation and logs
RFI form and processing
Task and issue management
Photo documentation
Baseline schedule, schedule updates and calendar management
Submittal form and processing
Drawing and specification document hosting, viewing, and updating
Online document collaboration
Reminder and tracking functions
Archiving functions
Notification of submittal and RFI statuses and current responsible party
Submit to the CO a list of all employees who will need access to the website. The users will receive an invitation to register from the Department of Interior (DOI). Once the user is registered on the DOI website, they will be given access to the project website. For login procedures and other SharePoint information, refer to the DSC Workflows website at https://www.nps.gov/dscw/precon_spproj.htm.
All users will be required to have Internet Explorer version 7 or later and Adobe Acrobat Pro version 9 or later.
1.3 Location
This project is located along the York River shoreline parallel to Colonial National Historical Parkway in Colonial National Historical Park. The work is in York County Virginia. The segment of work for this project is between the Indian Field Creek Bridge and the Felgate’s Creek Bridge. Exact stations for the project will be identified during the pre-bid meeting.
1.4 Background
https://www.nps.gov/dscw/precon_spproj.htm
COLO 253093B | Page 5 of 35
The York River shoreline parallels the Colonial National Historical Parkway for approximately 4.5 miles. Sections of the shoreline were altered during the original construction of the parkway and the flow in the river has deteriorated those areas. This project is a continuation of the first phase of work completed in 2013. There are 100% design drawings and specifications for the first phase of construction that has been completed. These documents include appropriate details, construction notes and stationing that can be used for this project. In addition the specifications would apply to the work in this segment and can be used to reduce the amount of work required by the design-build contractor.
There are 50% drawings completed for the section of work included in this contract. In addition, a new topographic survey is underway and should be completed and available for the contractors use by June
1, 2019. Some additional geotechnical borings have been completed, and additional work is scheduled for May of 2019. This information will also be available to the design build contractor. The work in this contract should only include treatments covered by the 2012 Environmental Assessment in accordance with the FONSI signed by the park superintendent.
1.5 Description
The contractor shall rehabilitate revetments and provide shoreline protection for approximately 1,000 linear feet between Indian Field Creek and Felgate’s Creek. Work shall be done in accordance with the
50% design drawings and specifications provided. Exact location of work will be determined during the pre-bid meeting. Exact quantity of work will be determined based on the attached schedule of values.
1.6 Schedule
The work in this RFP shall be completed in accordance with the following schedule:
DB Design Development (DD) Documents:
DB Design Development Documents (70%) submitted no later than 30 calendar days after award.
NPS Review completed no later than 15 calendar days after submission of DB Design Development
Documents.
100% Draft DB Construction Documents (CD):
Work on 100% Draft DB Construction Documents shall continue during the DB Design
Development Documents review. Once DB Design Development review comments are received they shall be addressed and incorporated in the 100% Draft DB Construction Documents.
100% Draft DB Construction Documents and written responses to the NPS DB Design
Development Document Review Comments submitted no later than 60 calendar days after submission of DB Design Development Documents.
NPS Review completed no later than 15 calendar days after receipt of 100% Draft DB Construction
Documents.
100% Complete DB Construction Documents (CD):
100% Complete DB Construction Documents and written responses to the NPS 100% Draft DB
Construction Documents Review Comments submitted no later than 30 calendar days after submission of 100% Draft DB Construction Documents.
COLO 253093B | Page 6 of 35
NPS Review completed no later than 8 calendar days after receipt of 100% Complete DB
Construction Documents
Complete Stamped and Signed DB Construction Documents (CD):
Complete Stamped and Signed DB Construction Documents and written responses to the NPS
100% Complete DB Construction Document review comments submitted no later than 15 calendar days after receipt of NPS 100% Complete DB Construction Document review comments.
Construction:
Construction shall not begin until the Contracting Officer (CO) has issued the DB Start Work
Notice.
Construction completed no later than 240 calendar days after award of the contract.
As-Constructed Drawings:
As-Constructed Drawings completed no later than 30 calendar days after Substantial Completion.
All DB Design Development, DB Construction Documents and As-Constructed Drawings shall be submitted to the NPS Project Manager (PM).
1.7 Information
NPS Points of Contact:
Contractual:
Contracting Officer (CO): Pamela Mault, 303-969-2982, pamela_mault@nps.gov
Contract Specialist (CS): Michael Smith, 303-969-2031, michael_smith@contractor.nps.gov
Technical:
Project Manager (PM) and Contracting Officer’s Representative (COR): Lilly Hardin, 303-987-
6670, lilly_hardin@nps.gov
Project Specialist (PS) and Alternate Contracting Officer’s Representative (COR): Mary Devine, 303-969-2175, mary_devine@nps.gov
Address:
National Park Service – Denver Service Center
12795 West Alameda Parkway
P.O. Box 25287
Denver, CO 80225
1.8 Data and Materials to be provided by the NPS
mailto:michael_smith@contractor.nps.gov
COLO 253093B | Page 7 of 35
The following data and materials will be provided to the DBC and are included in Section 5 of this RFP:
Project Program
Basis of Design Report (BDR)
PS Project Sustainability Checklist
Existing Drawings 50% complete (includes all segments of shoreline adjacent to Colonial Parkway)
Existing Drawings and Specifications 100% complete (includes a small segment of work)
Current topographical Survey
Geotechnical Reports
Cultural Resource Reports (CLRs)
Landscape revegetation Plan
Historic Photographs
Environmental Assessment (EA)
Finding of No Significant Impact (FONSI)
2.0 PROJECT REQUIREMENTS
The project must comply with NPS guidelines for recycling and use of recycled materials. The contractor must submit a waste management plan for approval prior to start of construction activities.
2.1 General Requirements
2.1.1 Scope of Work and Project Summary/Requirements
The project will consist of the design and construction of approximately 1,000 Linear Feet of shoreline revetment restoration along the York River in the vicinity of the Indian Field Creek Bridge.
Work must comply with 50% design and completed environmental compliance.
The project will include, but not be limited to, the following:
Review the 50% design, 100% design and construction specifications provided in the RFP package.
Review the 2019 topographical survey and geotechnical site data.
Upon award, determine and provide design schedule of work.
Perform geotechnical analysis.
Submit list of required permits. Determine if VA consolidated permit application can be completed using existing information.
Submit DB Design Development and DB Construction Documents for review and approval, as required.
Provide schedule of construction work.
Secure work area and provide for continued access to the facility.
Construct project
Provide as-constructed drawings.
2.1.2 Definition of Contract Line Items
The intent of this section is to explain, in general, what is included in each contract line item, limits or cut-off points where one item ends and another begins. If no item exists for a portion of the work, include the costs in a related line item.
CONTRACT LINE ITEM NO. 1 – DESIGN: This item consists of
COLO 253093B | Page 8 of 35 review 50% design documents, partial 100% design documents, specifications and other documents provided prepare design development documents (70%) for the segment of work included in this contract prepare construction documents for the segment of work included in this contract
CONTRACT LINE ITEM NO. 2 – CONSTRUCTION:
Base Contract: 800 linear feet of revetment rehabilitation
This item consists of: providing all materials, labor equipment and supervision necessary to complete the revetment rehabilitation for 1000 continuous linear feet as detailed in the approved design drawings and specifications.
CONTRACT LINE ITEM NO. 3 – OPTION A – 100 linear feet of revetment rehabilitation
This item consists of: providing all materials, labor equipment and supervision necessary to complete the revetment rehabilitation of an additional 100 linear feet as detailed in the approved
CONTRACT LINE ITEM NO. 4 – OPTION B – 100 linear feet of revetment rehabilitation
CONTRACT LINE ITEM NO. 5 – OPTION C – 100 linear feet of revetment rehabilitation
CONTRACT LINE ITEM NO. 6 – OPTION D – 100 linear feet of revetment rehabilitation
2.1.3 Progress Payments
Design Phase - Progress payments during the design phase of the work will be based on submission, review, and acceptance of design deliverables.
Construction Phase - Progress payments during construction will be based on the percentage of work completed on items listed on the approved schedule of values. Actual construction completed and in place will form the basis for payment. Verification of the % complete shall be initiated by the
Contractor under the direction of a representative of the Contracting Officer, unless the Contracting
Officer waives this requirement in a specific instance. The Contractor shall make the computations for payment based on the governments verification of work completed and in place for any periods for which progress payments are requested.
The Contractor shall furnish the originals of all field notes and all other records relating to the basis for payment, to the Contracting Officer, who shall use them as necessary to determine the final amount of progress payments. The Contractor shall retain copies of all such material furnished to the Contracting Officer.
COLO 253093B | Page 9 of 35
2.1.4 Project Meetings
Design Meeting
After the award of the contract and acceptance of the Performance and Payment bonds, the CO will arrange a design meeting with the DBC. The meeting agenda shall include the following as a minimum:
Review and emphasize the Park needs and design objectives.
Environmental and sustainability requirements
Commissioning (review requirements in ASHRAE 0-2005 paragraphs 6 and 7)
Schedule of Values
Design schedule (provide minimum of two color hard copies).
Modifications during design
Submittals during design
Areas available for use by the DBC
Access requirements of the Park
Natural and Cultural Resource Protection
Payments to the DBC
Preconstruction Meeting
The following Part 2 Project Requirement deliverables shall be submitted a minimum of one week prior to the Preconstruction Meeting.
Letter designating your Project Superintendent
Project Schedule with construction portion fully developed
Schedule of Values
Accident Prevention Program
A list of subcontractors for this project (must be same as in your proposal)
Written statements from subcontractors certifying compliance with applicable labor standard clauses
Evidence of liability insurance coverage and workmen’s compensation for the contractor and all subcontractors
Waste Management and Recycling Plan
Quality Control Plan
Storm Water Pollution Prevention Plan Submittal process
List of required permits
After 100% Complete DB Construction Documents are approved (or completed portions of DB CDs necessary for fast tracking the project), and prior to the start of construction, the CO will arrange an on-site Preconstruction meeting with the DBC. The meeting agenda will include the following as a minimum:
Correspondence procedures
Jobsite safety
Roles and responsibilities
Lines of Authority
Schedule of Values
Progress Payments
COLO 253093B | Page 10 of 35
Submittal process
Resolution to comments provided by NPS on the Part 2 Project Requirements
NPS/DSC SharePoint Project website
Construction schedule (Provide a minimum of two color hard copies and electronic copy in software it was created in.)
Labor standards
Payroll reports
Modifications
Accident reporting
Park Rules and Regulations
Medical emergency processes, availability, emergency numbers, and contacts.
Rules of the road, alcohol use, housekeeping, firearms, pets, natural and cultural resource concerns.
Bridge, access road and site constraints.
Visitation and public relations.
Environmental and sustainability requirements for the Project, required tracking for sustainability (related submittals), use of the NPS Project Sustainability Checklist.
Archeological Resources Protection Requirements
Saturdays, Sundays, holidays and night work.
Traffic control
Progress Meetings
The DBC shall participate in weekly telephone conference calls with the Contracting Officer, and other project team members to update them on the following meeting agenda items:
Approval of minutes of previous meetings
Submittal status
Review of off-site fabrication and delivery
Requests for Information (RFI’s) and issues
Modifications
Safety
Work in progress and projected
Schedule update (provide updated CPM schedule)
Status of Project Record Drawings and O&M Manuals
Other business relating to work
2.1.5 Project Schedule
General: The Contractor shall upload the project schedule to the NPS/DSC SharePoint Project website and provide two (2) color copies after award and before the design meeting. The schedule shall include a detailed design phase with design deliverable submission dates, review periods as well as a summary construction schedule with important milestones included for both phases.
Fully develop the construction portion of the schedule and submit to the Contracting Officer on the
NPS/DSC SharePoint Project website before the Preconstruction meeting or any construction begins.
The project schedule shall be updated on a monthly basis throughout the entire contract period and until
COLO 253093B | Page 11 of 35 project substantial completion. The status date of each schedule update shall be 10 days before the progress payment request date.
Construction work cannot begin until government approval is obtained for either:
The entire set of 100% Complete DB Construction documents.
For fast track construction, the 100% Complete DB Construction documents affecting the work to be constructed.
Purpose: The purpose of the project schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of design and construction activities of the DBC. The project schedule will assist the DBC and the Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the DBC's monthly progress payment requests.
Software: The software shall be the latest version of Microsoft Project, Primavera Project Planner, SureTrak, or approved equal.
Schedule Development: The project schedule shall cover the entire contract period. The late finish date of the project schedule shall be the same date as the established completion date of the contract.
The DBC shall use the Critical Path Method (CPM) with limited use of lead or lag durations between schedule activities. The DBC's project schedule shall consist of procurement activities (including mobilization, submittal, and the fabrication and delivery of key and long-lead procurement items) and construction activities.
The DBC's project schedule shall consist of, but not be limited to, the following for each activity:
Identify each and every activity number with numerical designations (maximum 5-digit).
Numbering of activities shall be in increments of 10.
Concise description of the work represented by the activity (maximum 48 characters). Avoid the use of non-standard abbreviations. The work related to each activity shall be limited to one work trade.
Activity duration in whole working days with a maximum duration of 15 work days each, unless otherwise approved by the Contracting Officer, except for non-construction activities including mobilization, shop drawing and sample submittals, fabrication of materials, delivery of materials and equipment, and concrete curing.
In developing the project schedule, the DBC shall be responsible for ensuring that subcontractor work at all tiers, as well as its own work, is included in the project schedule.
The project schedule shall show the sequence and interdependence of activities required for complete performance of the work. It shall be cost and resource loaded. The DBC shall be responsible for ensuring all work sequences are logical and the project schedule shows a coordinated work plan.
Proposed durations assigned to each activity shall be the DBC's best estimate of time required to complete the activity considering the scope and resources planned for the activity. Resource loading of each activity shall list all personnel by labor category and equipment type and capacity proposed to complete the activity in the duration shown. Include permit requirements and constraints. Seasonal weather conditions shall be considered and included in the planning and scheduling of all work influenced by high or low ambient temperatures, wind and/or precipitation to ensure completion of all work within the contract time.
COLO 253093B | Page 12 of 35
Project Schedule Updates
Monthly updates: The monthly updating of the project schedule shall be an integral part and basic element of the estimate upon which progress payments shall be made under this contract. If, in the judgment of the Contracting Officer, the DBC fails or refuses to provide a schedule of values and a complete schedule update or revision as specified hereinafter, the DBC shall be deemed to have not provided the required information upon which the progress payment may be made, and shall be subject to retainage of a portion of the payment.
Narrative: The report shall include a brief description of the actual progress made during the update period; actual and potential delaying activities; any impediments to progress; issues related to inclement weather; progress toward established milestones and project float. The report shall include a brief description of the work anticipated to be performed in the next month. Any minor revisions to the schedule should be identified so they can be evaluated and accepted or rejected.
As the Work progresses, indicate Actual Completion percentage for each activity.
If the schedule update shows a late finish date after the contract completion date, at a minimum, include the following in the narrative with your submission:
Any known delays.
Actions that will be taken to get back on schedule.
Pending modifications.
Impediments or constraints affecting progress.
Progress Payments: The monthly updating of the currently accepted Construction Schedule shall be an integral part of the process upon which progress payments will be made under this contract. If the
Contractor fails to provide schedule updates or revisions, then a portion of the monthly payment may be retained until such corrections have been made.
Time Impact Analysis for Contract Modifications, Changes, Delays, and Contractor Requests
Requirements: When contract modifications or changes are initiated, delays are experienced, or the
DBC desires to revise the project schedule, the DBC shall submit to the Contracting Officer a written time impact analysis illustrating the influence of each modification, change, delay, or DBC request on the contract time.
Time Extensions: Activity delays shall not automatically mean that an extension of the contract time is warranted or due the DBC. It is possible that a modification, change, or delay will not affect existing critical activities or cause non-critical activities to become critical. A modification, change, or delay may result in only absorbing a part of the available total float that may exist within an activity chain of the project schedule, thereby not causing any effect on the contract time. Time extensions will be granted in accordance with the terms of the contract.
Float: Float is not for the exclusive use or benefit of either the National Park Service or the DBC.
Extension of the contract time will be granted only to the extent the equitable time adjustments to the activity or activities affected by the modification, change, or delay exceeds the total (positive or zero) float available on a particular activity.
2.2 Design Requirements
COLO 253093B | Page 13 of 35
2.2.1 DB Design Development (DD) and Construction Documents (CD)
This element of work shall consist of the preparation of the DB Design Development Documents and DB
Construction Documents. All documents shall be prepared using the English System of Weights and
Measurements, and shall be prepared in accordance with the DSC Design Standards, https://www.nps.gov/dscw/dstandards.htm.
DB Design Development Documents and DB Construction Documents shall be prepared per the Design
Deliverable Content and Format Requirements for DB Design Development Documents, https://www.nps.gov/dscw/del_designdevelopdb.htm, and DB Construction Documents, https://www.nps.gov/dscw/del_constructiondb.htm.
Salient characteristics shall be listed for products and materials specified. Refer to the Guide for Specifiers, https://www.nps.gov/dscw/publicforms.htm#gfs.
Deliverables
The following deliverables are required (refer to Section 1.6 for schedule):
DB Design Development
DB Design Development Documents:
Documents for NPS Review:
Submit 8 hard copies of the following DB Design Development Documents for review:
o DB Design Development Drawings o Divisions 2 through 49 Outline Specifications (USACE specification format is acceptable) o Product File o NPS Project Sustainability Checklist (DD portion completed)
Submit one electronic copy of the Draft DB Design Development Drawings and the NPS
Project Sustainability Checklist in both native formats and PDF formatted files.
DB Construction Documents
100% Draft DB Construction Documents
Submit 8 hard copies of the following 100% Draft DB Construction Documents for review:
o DB Construction Drawings o Divisions 2 through 49 Construction Specifications (Construction Specifications
Institute (CSI) Master Format 04 Edition or USACE format). A/E shall utilize and modify Divisions 2 through 49 Construction Specifications templates to fit this particular project.
https://www.nps.gov/dscw/dstandards.htm https://www.nps.gov/dscw/del_designdevelopdb.htm https://www.nps.gov/dscw/del_constructiondb.htm https://www.nps.gov/dscw/publicforms.htm#gfs
COLO 253093B | Page 14 of 35 o Product File o NPS Project Sustainability Checklist (CD Portion completed) o Design Calculations o Written responses to the DB Design Development Documents Review Comments
(Utilize NPS Review Form)
Submit one electronic copy of the 100% Draft DB Construction Drawings and written responses/resolutions to all DB Design Development Documents Review Comments in both native formats and PDF formatted files.
100% Complete DB Construction Documents
Submit 8 hard copies of the following 100% Complete DB Construction Documents for review and final approval:
o DB Construction Drawings o Final Construction Specifications o Product File o NPS Project Sustainability Checklist (CD Portion completed and updated) o Design Calculations o Written responses to the 100% Draft DB Construction Documents review comments
(Utilize NPS Review Form)
Submit in native formats (no PDF formatted files) one electronic copy of the 100%
Complete DB Construction Drawings and written responses/resolutions to all 100% Draft
DB Construction Documents Review Comments.
Complete Stamped and Signed DB Construction Documents
Upon final approval of the 100% Complete DB Construction Documents, submit per the following table, the Complete Stamped and Signed DB Construction Documents for construction, NPS archiving and general use (see the DSC DB Workflows website “Submittal
Formats” portion of the “Design Deliverables – Content and Format Requirements” for format and media submission requirements.)
COLO 253093B | Page 15 of 35
COMPLETE STAMPED AND SIGNED DB
CONSTRUCTION DOCUMENTS
ELECTRONIC
FORMATS *
HARD COPY
FORMATS
DB Construction Drawings ** AutoCAD Full-Size Paper
(ANSI D)
Divisions 2 through 49 Construction Specifications PDF & MS-Word N/A
Product File PDF N/A
NPS Project Sustainability Checklist PDF & MS-Excel N/A
Design Calculations PDF N/A
Written responses to the 100% Complete DB Construction
Documents review comments PDF & MS-Excel N/A
* The recipient of the electronic files is TIC.
** DB Construction Drawings shall be printed from the native software (e.g. AutoCAD .dwg or Revit .rvt). DB
Construction Drawings printed from secondary software (e.g. Adobe .pdf) are not acceptable as they often result in off-scale product.
2.2.2 Environmental and Sustainability Requirements for Design
The National Park Service has established environmental and sustainability requirements for the project.
Notify the CO if conflicts arise between performance of the work and environmental and sustainability requirements. The National Park Service does not intend to limit alternative means of achieving these requirements.
Specific sustainability requirements for design may be found in Part 3, Performance Requirements, of this document and the NPS Project Sustainability Checklist, https://www.nps.gov/dscw/publicforms.htm#psc. Complete this checklist by concisely explaining how each credit/requirement will be met.
2.3 Construction Requirements
2.3.1 Environmental and Sustainability Requirements
Specific sustainability requirements generated in design will dictate more stringent environmental requirements for this project. Refer to part 3, Performance Requirements, of this document and the NPS
Project Sustainability Checklist. The following are general requirements:
Site Disturbance: Minimize the construction limits of the project to reduce the project’s impact on the site.
Toxic Chemicals: Avoid materials that can leach toxic chemicals into the ground water. Do not allow toxic chemicals to enter sewers or storm drains or contaminate land or any body of water.
Refer to NPS Project Sustainability Checklist for additional requirements.
Soil Erosion: Protect against erosion and topsoil depletion in accordance with the Stormwater
Pollution Prevention Plan.
Habitats: Protect natural habitats and ecological systems on facility site (as identified in the
Environmental Assessment and the supplemental section 7 consultations).
Noise: Minimize noise generation during construction. Operate power equipment in accordance with local noise restrictions.
https://www.nps.gov/dscw/publicforms.htm#psc
COLO 253093B | Page 16 of 35
Waste Management: Employ processes that ensure the generation of as little waste as possible.
Waste disposal in landfills shall be minimized. Recycling is a requirement of this project.
Specific recycling goals were established in the NPS Project Sustainability Checklist. All material unsuitable for recycling must be disposed of, in a legal manner, at public or private dumping areas outside the park.
The DBC shall designate an on-site party (or parties) responsible for instructing workers and overseeing the environmental and sustainability requirements of this project. Distribute copies of the environmental and sustainability requirements to the Job Site Foreman and each Subcontractor.
Waste Management Plan: Prior to the scheduled Preconstruction meeting, the Contractor shall submit a draft Waste Management Plan to the Contracting Officer for approval. Develop and implement in accordance with ASTM E1609 and as required in the contract documents. The plan shall include (but not be limited to) the following:
List of the recycling facilities, reuse facilities, municipal solid waste landfills, and other disposal area(s) to be used. Include name, location, and phone number.
List of proposed materials to be reused or recycled.
List of materials that cannot be recycled or reused with explanation or justification.
Storage and collection methods of waste and recyclables, handling procedures, and means of keeping recyclables free of contamination.
Description of the means of transportation of the recyclable materials and an estimate of how often bins will need to be emptied.
Identity person or persons responsible for ensuring project recycling goals are achieved.
Revise and resubmit Plan as required by the Contracting Officer. Approval of the Contractor’s
Plan will not relieve the Contractor of responsibility for compliance with applicable environmental regulations.
Progress Documentation: Supplemental to the Waste Management Plan, document solid waste disposal, diversion, and cost/revenue analysis and submit a completed worksheet on a monthly basis. Use
Appendix A - Project Waste Management Plan Worksheet, and report totals to date for all column headings. Use Appendix B for solid waste volume to weight conversions.
Prior to the commencement of the Work, schedule and conduct a meeting with the Contracting Officer to discuss the proposed Waste Management Plan and to develop mutual understanding relative to details of environmental protection.
Minimize Construction Impacts
The following mitigation measures shall be implemented to minimize the impacts of construction activities:
Construction Access: Materials and heavy equipment shall be delivered by barge. Potential barge access areas are identified on the 50% design drawings. These areas have been identified based on water depth and minimization of resource impacts. Final barge access points shall be identified by the contractor and confirmed by park staff.
Soil Erosion: Protect against erosion and topsoil depletion. Storm Water Pollution Prevention
Plan required.
COLO 253093B | Page 17 of 35
Exotic Vegetation and Noxious Weeds: Prevent the introduction and minimize the spread of exotic vegetation and noxious weeds. Incorporate the following procedures:
Any fill, rock, or additional topsoil needed shall be obtained from a Government approved source. All areas disturbed by construction shall be re-vegetated using approved native seed and/or plants.
Vegetation Salvage and Re-vegetation Plan: A revegetation plan is being prepared, in accordance with the cultural landscape report, for the project by NPS. Plantings will be installed by the contractor. Assume revegetation will restore the area to current type and quantity of vegetation. Any re-vegetation efforts shall use approved native species and/or native seed, and comply with Park policies regarding vegetation and site restoration. Policy related to re-vegetation will be referenced in NPS Management Policies 2006 (Section 9.1.3.2).
Special Status Species: To protect any unknown or undiscovered threatened, endangered, or special status species, the construction contract will include provisions for the discovery of such.
The contractor should contact the park for direction for evaluation of any special species at the site. Known special status species include, the bald eagle, the Atlantic sturgeon, sea turtles and bats among others. The contractor shall employ BMPs that would prevent deleterious materials from entering the York River and nearby streams. Other mitigation measures such as turbidity curtains may be required by fish and wildlife officials.
Visitor Experience: The following mitigation measures shall be incorporated into the action alternatives to minimize the impacts of construction activities on the visitor experience:
Provide “No Fishing” signs and construction fencing to prevent visitor access to the area during construction and revegetation.
Air and Water Pollution Control: Air quality impacts are expected to be temporary and localized. To minimize these impacts, the following actions shall be taken:
To reduce tailpipe emissions, construction equipment shall not be left idling any longer than is necessary for safety and mechanical reasons.
To reduce construction dust, water shall be applied to problem areas. Equipment shall be limited to the fenced project area to minimize soil disturbance and dust generation.
Take all necessary reasonable measures to reduce air and water pollution by any material or equipment used during construction. Keep volatile wastes in covered containers.
Storm Water Pollution Prevention Plan (SWPPP): Submit a SWPPP according to the applicable State Water Resources Control Board's (SWRCB) requirements to the
Contracting Officer for approval. (See Technical Requirements) Before starting construction, the Contractor shall implement the approved SWPPP.
Cultural Resources: We do not anticipate a need for archeological monitoring. If needed, an archeological monitor will be provided by NPS. If archeological resources are discovered at the project site while the archeological monitor is absent, all work in the vicinity of the discovery must stop immediately, and the discovery must be reported to the CO.
COLO 253093B | Page 18 of 35
2.3.2 Schedule of Values
After contract award and before the Design Meeting, submit a schedule of dollar values based on the
Contract Price Schedule. Breakdown each lump-sum item into component parts of design deliverables or construction work for which progress payments may be requested. The total costs for the component parts of work shall equal the contract line item amount for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the component parts of work for each lump-sum item, as described below. Do not include mobilization, general condition costs, overhead or profit as a separate item.
Do not break down unit price items. Use only the contract line item amount for unit price items.
The total cost of all items shall equal the contract sum. The Schedule of Values will form the basis for progress payments.
An acceptable Schedule of Values shall be agreed upon by the Contractor and Contracting Officer before the first progress payment is processed. A cost loaded project schedule is an acceptable substitute for a schedule of values in some cases.
2.3.3 Construction Support
Staging Areas
Construction sites will be limited to the smallest feasible area. Ground disturbance and site management will be carefully controlled to prevent undue damage to vegetation, soils, and archeological resources and to minimize air, water, soil, and noise pollution.
Staging is available on paved pullouts at Indian Field creek and Felgate’s Creek. Securing materials and equipment is difficult on paved pullout/parking areas. An additional secure staging area is available at the Ringfield Picnic area approximately 2 kilometers from Felgate’s Creek Bridge. A space near the
Yorktown Maintenance area is available for a construction office or trailer. All vehicles must be parked on paved areas. Construction equipment and material storage shall be located in previously disturbed areas at the Ringfield Picnic area or as approved by the CO and Park staff. All staging areas shall be returned to pre-construction conditions once construction is complete. Standards for this, and methods for determining when the standards are met, shall be developed in consultation with the CO.
Structures: Trailers, Storage, Field Offices, Staging Area and Sheds: Location to be approved by the CO.
DBC's Field Office: Field office shall be structurally sound construction, and weather tight. The location will be determined by NPS prior to issuing a Start Work Notice.
Storage Sheds: If used, provide weather tight sheds or other covered facilities for storage of materials subject to weather damage.
If used, all temporary water, sewer, sanitary facilities and electric utilities, shall be completely removed upon project completion. Remove temporary utility connections.
The location of the Staging Area for construction equipment will require CO approval.
Construction Camp: Establishment of a construction camp will not be permitted.
Construction Zones
COLO 253093B | Page 19 of 35
Construction zones shall be fenced with CO approved construction barrier fencing, plastic or portable fencing, before any construction activity. The fencing shall define the construction zone and confine activity to the minimum area required for construction. All protection measures shall be clearly stated in the construction specifications, and workers will be instructed to avoid conducting activities beyond the construction zone as defined by the construction zone fencing.
Protection of Public: Fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry. Erect and maintain fencing, barricades, lights, signals, and warning signs in accordance with the most current version of the Manual on Uniform Traffic Control Devices (MUTCD).
The DBC shall protect tree trunks and root systems of trees in or adjacent to work areas.
Special Construction Requirements Weight limitations exist for Colonial Parkway and associated bridges. Check weight requirements prior to shipping materials on these roadways. It is assumed that rock and heavy equipment required to complete the work will be delivered via barge or other seaworthy vessel. Barge access points have been identified by the Army Corp of Engineers and are shown on the design drawings provided.
Parking of Construction Vehicles
Parking of vehicles shall be limited to existing roads, in legally designated areas, and within approved staging area(s).
2.3.4 Submittals during construction
NPS Project Sustainability Checklist: Complete the construction column of the checklist by concisely explaining how each credit/requirement is met. Indicate what products or actions were installed or performed to comply with each credit or requirement.
Construction Submittals:
1. Accident Prevention Plan
2. Subcontractor plan
3. Quality Control Plan
4. Waste Management Plan
5. SWPP
6. List of required permits
7. Armor Stone
8. Geotextile
9. Plan Materials
10. Top Soil
11. Fill Material
Construction Submittal Types
Action Submittals: Written, graphic information, and physical samples that require Government’s responsive action.
Product Data: Collect information into a single submittal for each element of construction and type of product or equipment
COLO 253093B | Page 20 of 35
Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data
[unless submittal of CAD Drawings is otherwise permitted].
Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.
Construction Materials: The Contractor is encouraged to submit for approval products made out of recycled or environmentally responsible material. Every effort will be made by the
National Park Service to approve these materials
Informational Submittals: Written information that does not require Government’s responsive action. Submittals may be rejected for not complying with requirements.
General: Prepare and submit Informational Submittals required by individual Specification
Sections.
Informational submittals include but are not limited to Coordination Drawings LEED™
Submittals Product Data, Certificates, Test reports, Manufacturer’s instructions, Division 01
Management Plans, etc.
Contractors Review
Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions.
General Submittal Procedures
Prepare and submit submittals shown in Part 4.0, Technical Requirements. Details on the specific requirements for each can be found in the individual technical sections.
Contracting Officer reserves the right to require submittals in addition to those called for in individual sections.
Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Review them for legibility, accuracy, completeness, and compliance with
Contract Documents.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Partial submittals are not acceptable, will be considered non-responsive, and will be returned without review.
Processing Time: Allow enough time for submittal review, including time for re-submittals.
Time for review shall commence when an e-mail notification is received by the Contracting
Officer (or designee) indicating the submittal has been posted on the NPS/DSC SharePoint
Project website and is ready for review. When the Contracting Officer has completed their review, an e-mail notification will be sent to the Contractor indicating the submittal has been processed. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including re-submittals.
1. Action Submittals: Allow 30 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required.
COLO 253093B | Page 21 of 35
2. Informational submittals: Allow 10 days for review of each submittal.
Electronic Submittals: Identify and incorporate information in each electronic submittal file as follows:
1. CM-SPE Transmittal Form: All submittals shall be transmitted using National Park Service form CM-SPE form. The form is accessed and completed on the NPS/DSC SharePoint
Project website. No action will be taken on a submittal item unless accompanied by the CM-
SPE transmittal form.
a. Complete the general information at the top of the form.
b. Provide all required information based on the submittal type
c. Attach all related documents.
d. Sign the CM-SPE form in the contractor section at the bottom of the form, and select
“submit” when complete.
2. Physical samples: Complete the CM-SPE on the NPS/DSC SharePoint Project website as described above. Deliver the physical sample to the CO (or designee) on site for processing.
All comments and actions will be documented on the CM-SPE form on the NPS/DSC
SharePoint Project website.
Contracting Officer's Review
Action Submittals: Contracting Officer will review each submittal, generate comments on corrections or modifications required, and indicate the appropriate action on the CM-SPE Transmittal Form. The submittal will be marked in one of three ways as defined below:
1. Approved: Acceptable with no corrections.
2. Approved with Notations: Minor corrections or clarifications required. All comments are clear and no further review is required. The Contractor shall address all review comments when proceeding with the work.
3. Disapproved – Resubmit: Rejected as not in accordance with the contract or as requiring major corrections or clarifications. The Contracting Officer will identify the reasons for disapproval. The Contractor shall revise and resubmit with changes clearly identified.
Informational Submittals: Contracting Officer will review each submittal and will either accept or reject them.
Submittal List
An example of a Submittal List has been attached to the end of this section. (The latest version of the
Submittal List and Review Estimate template is on the DSC Workflows website, https://www.nps.gov/dscw/publicforms.htm#dt. The intent is to provide an overall summary of submittal requirements and not a comprehensive list. The technical requirements indicate the type and specify submittal requirements. The terms and conditions of the Contract still apply regardless of what is shown on the submittal list.
Use for Construction
Use only final submittals with mark indicating “Approved” or “Approved with notations”. Ensure all notations have been incorporated and, at a minimum, keep one copy of the final approved submittal on site for use during construction
2.3.5 Construction Coordination
https://www.nps.gov/dscw/publicforms.htm#dt
COLO 253093B | Page 22 of 35
Notification: The Contracting Officer (CO) will provide all necessary written notification and/or direction to the contractor. An on-site independent Construction Management Representative (CMR) will co-ordinate the contractor’s construction efforts with the park staff’s daily operations and will transmit and receive correspondence between the Denver Service Center and the DBC. However, the
CMR will have no authority to accept or reject work, or to authorize changes to the terms and conditions of the contracts, or to obligate the NPS for time or money.
2.3.6 Digital Images
Take appropriate digital images documenting construction progress and problems, such as…