140P2018R0002_Amendment_0001.pdf
PDF 449 KB Posted
- Attached to
- LOWE 189650 - Cotton Mills Museum for Fire Safety Code Compliance Lowell National Historic Park
- Solicitation number
- 140P2018R0002
About this file
Amendment 001 to Solicitation 140P2018R0002 -- package includes SF 30, site visit sign-in sheet, and answers to contractor questions
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140P2018R0002 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PDS
Denver CO 80225-0287 P.O. Box 25287 12795 W. Alameda Pkwy NPS, DSC Contracting Services Div
02/06/20180001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
02/06/2018
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of Amendment 0001 is to modify the period of performance to 365 days, extend the due date to 3/16/17, provide the sign-in sheet from the pre-bid meeting, and provide questions & answers.
Legacy Doc #: NPS
Period of Performance: 05/15/2018 to 05/14/2019
Contracting Officer (CO): Aaron Adams (303)969-2789 aaron_adams@nps.gov
Contract Specialist (CS): Philip Robinson (303)969-2137 philip_robinson@nps.gov
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Aaron Adams
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Questions and Answers
1. Can the Superintendent act as the QC Representative on the project? No.
2. May I ask how the proposal will be submitted? Hard copy (if so how many) or email. Also, will a bid bond be necessary for this project? (I understand that, upon award, the contractor will require a performance bond.)
3. Is the existing roof under warranty? What warranty is required at the completion of new roof work?
The Roof is not under warranty.
4. What is the permit requirement for a. building permit, b. fire sprinkler permit, c. fire alarm permit, d. Sheetmetal ductwork permit, e. hot work permits, and fire watch with Lowell Fire Department requirement?
The Park follows all State and Local codes requiring permits. Contractor shall follow and acquire any permits required through the city of Lowell (City Hall). All welding in the building requires a fire watch by trained personal on fire watch requirements, or the Fire Department.
5. What is the procedure for utility outages? Fire alarm, Sprinkler, Electrical and Plumbing/Heating.
How much notice is required? Can this work be done during normal working hours?
All work can be completed during regular hours. Any outages needed are to be coordinated with the COR. Park will require 48 hours for notification of any outages that are needed and approved by the COR.
6. How is noisy work handled? Demolition, steel work, ductwork etc.?
The Park is expecting regular construction noise. Any heavy noise that may interfere with the Parks regular day to day operations (more than normal construction noise) should be coordinated with the COR. Park will require 48 hour notification and approval by COR for work to be completed.
7. Will the performance period change per site meeting? The period of performance has changed to 365 days.
8. Will the bid due date be changed to allow more time, after questions are answered, for sending proposals to Colorado? The due date has been amended to 3/16/17
| 140P2018R0002 Amendment 0001 |
| Amendment 0001 |
| Pre Bid Sign In Sheet |
| LOWE 189650 Questions and Answers |
| 2018-02-26T07:11:11-0700 | |
| AARON ADAMS |