This document is an amendment (Amendment 0001) to Solicitation 140P1525R0012 for the Phantom Ranch Percolation/Evaporation Area Cyclic Repairs project at Grand Canyon National Park. The amendment extends the proposal due date to 7/17/2025 and incorporates answers to questions received, including updated graphics, Statement of Work (SOW), and specifications. The project involves repairing the percolation area that was constructed in 2022/2023 to replace the failing wastewater treatment plant effluent discharge system. Key repairs include installing an HDPE liner on interior sidewall perimeters, removing 2 inches of native soil, placing #57 gravel, bedding effluent distribution piping, installing a weed barrier, and addressing infiltration and plant growth issues. The work will be performed on one cell at a time to allow the wastewater treatment plant to continue operating, with an eight-week period of performance.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P1525R0012.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140P1525R0012 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PIA
Flagstaff AZ 86001-2694 1824 S Thompson St, Ste 200 NPS, IMR - Arizona MABO
06/05/20250001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
06/05/2025
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of amendment 0001 is to:
1. Incorporate answers to questions received to include updated graphic, SOW, and specifications.
2. Extend the due date for proposals to 7/17/2025.
All other terms and conditions of the solicitation remain unchanged.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Jessica Owens
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
United States Department of the Interior
NATIONAL PARK SERVICE
CONTRACTING OPERATIONS - CENTRAL
1849 C Street
NW Washington, DC 20240
June 24, 2025
Questions and Answers
GRCA Phantom Ranch Per Area Cyclic Repairs
Solicitation 140P1525R0012
1 Is there some graphics missing from this, I see two drawings attached herein?
Graphics are missing from the original solicitation and have been attached to amendment 01
2 Will the #57 rock need to be imported?
Yes, the #57 rock will need to be imported
3 Is there a small excavator for use on site or will this need to be flown in? If yes one is onsite, what type is on site?
There is not a small excavator on-site to use, machine will have to be flown in.
4 The submittal register shows items that seem to not apply to this contract. Please advise.
The submittal register in the specifications has been corrected, see amended specifications.
5 Will the galvanized edge be 6" or 8" as I see a mention for both sizes.
Metal edging will be 6". Project SOW, graphic, and specifications have been amended.
6 There is a mention of a bid option to use our own helicopter transport services, will we need to add a separate price sheet for this request for bid purposes?
Contractor will need to provide their own helicopter operation. A separate price sheet for the helicopter operation would be helpful.
7 How many workers can we house in the onsite housing?
See specification section 1.7 I. Contractor will have use of one bedroom in the bunkhouse and that bedroom can sleep 6 workers.
8 Is there potable water on site or do we need to fly in our own?
There is potable water onsite.
9 In regards to small excavator, do we need to fly in our own fuel or will this be provided?
Contractor will need to fly in fuel for excavator.
Table of Contents Slide #1: Project Description Slide #2: Perc Area Original Drawing, for Reference Slide #3: Perc Area Plan View Slide #4: Perc Area Section View Slide #5: Perc Area Wall Section Close-up Slide #6: #57 Gravel cut sheet Slide #7: AGTEC Reinforced Polyethylene Liner cut sheet Slide #8: Commercial Weed Barrier cut sheet Slide #9: Simplified Section of project actions
Phantom Ranch Percolation Evaporation Area – Cyclic Repairs 2025 Lou Rogers, GRCA Civil Eng., March 10th, 2025
Background and Existing Condition The Phantom Ranch percolation/evaporation area (perc area) was constructed in 2022/2023 as part of the PMIS project #229035, Rehabilitate Phantom Ranch Wastewater [Treatment]
Plant (PR WWTP) Tertiary Treatment, Equalization Tank, and Headworks. The project was reviewed by the Park, PEPC #106345, and is closed complete. The perc area was constructed to replace the failing PR WWTP effluent discharge irrigation bubbler system and was brought online in January 2024. The existing emergency effluent discharge overflow trench was rehabilitated in 2020/2021 and remains in service if needed.
The perc area functioned nominally until late March of 2024 when the effluent discharge started to pond in the perc area rather than infiltrate quickly into the native soil as the design predicted. Two reasons for the inhibited percolation were identified by the plant operators:
one, there was heavy unpredicted plant growth in the perc area and two, there appeared to be an organic biomass growing in the top 2” of the native soil.
Ponding in the perc area also caused effluent ‘blowouts’ through the sidewalls.
The PR WWTP operators have been removing the plant growth and roto-tilling the native soil to increase the percolation rate and prevent ponding, plant growth, and blowouts. It is their belief that these actions appear sufficient in the low flow season but will not function as intended in the high flow season.
Project Description This project proposes the following cyclic repairs to address the inhibited infiltration, excessive plant growth, and the sidewall blowouts: installation of HDPE liner on the inside of the perimeter walls, remove 2” of the top native soil, place 3” of #57 gravel and bed effluent discharge piping in the 3” of gravel, install weed barrier, and place 1” of #57 gravel on top of the weed barrier. Please note, none of the proposed repairs changes the existing footprint or affect the look of the perc area. All work will be done inside the perc area fence. Work will be done on one cell at a time to allow the PR WWTP to continue operating.
Work Plan
* Work to be done on one cell at a time. This allows the PR WWTP to remain operational.
1) Remove bird netting
2) Remove section of exterior wall to allow small excavator to enter perc area cell.
3) Remove effluent distribution piping within the cell.
4) Excavate interior of cell perimeter wall to facilitate the installation of the HDPE perimeter liner (see slides 4 & 5 for liner details and slide #7 for liner material cut sheet).
Install liner and backfill.
5) Remove top 2” of native soil throughout perc cell infiltrative area and distribute along the interior perimeter of the perc area wall at 1:1 slope (see slides 4 & 5 for details)
6) Place 3” of #57 ( see slide #6 for gravel cut sheet) gravel over entire infiltrative area and bed effluent distribution piping in the 3” of gravel.
7) Place weed barrier fabric (see slide 3 for plan view and slide # 8 for material cut sheet) over 3” of gravel and cover with 1” of #57 concrete gravel over weed barrier.
8) Reinstall fence section that was removed in step 2.
9) Install bird netting
REPEAT ON REMAINING CELL
Slide 1
Slide 2
Perc Area Plan View
Perc Area
Yellow: HDPE Liner and 2” of native soil removed from perc area placed around entire perimeter at a 1:1 slope, 18” vertical, 18” horizontal
Light blue is: 3” of #57 concrete gravel, placed over native soil, effluent distribution piping bedded in the 3” of gravel, weed barrier fabric covering the 3” of gravel, and 1” of gravel covering the weed barrier fabric..
1.5” perforated polyethylene effluent distribution piping bedded in 3” of #57 gravel.
Slide 3
Phantom Ranch Perc Area Plan View
Perc Area Section View
Phantom Ranch Perc Area Section View
Slide 4
Excavate the interior perimeter to facilitate installation of the HDPE liner.
Liner vertical leg to be 2’-6”, horizizontal leg to be 1’ -6”. Horizontal leg to be buried at a minimum of 1’ 0” below the infiltrative surface.
2” of native soil removed from perc area placed around perimeter interior at a 1:1 slope, 18” vertical, 18” horizontal
2” of native soil removed from perc area placed around perimeter interior at a 1:1 slope, 18” vertical, 18” horizontal.
3” of #57 concrete gravel placed directly on the native soil. Effluent distribution piping bedded in the 3” of gravel.
Weed barrier fabric placed over 3” of gravel and covered by another 1” of #57 gravel
2” of native soil removed from perc area placed around perimeter interior at a 1:1 slope, 18” vertical, 18” horizontal Weed barrier fabric placed over 3” of gravel and covered by another 1” of #57 gravel.
Phantom Ranch Perc Area Redwood Wall Section *Detail Applies to Both Perc Area Cells
Infiltrative Surface
Slide 5
Excavate the interior perimeter to facilitate installation of the HDPE liner.
Liner vertical leg to be 2’-6”, horizizontal leg to be 1’ -6”. Horizontal leg to be buried at a minimum of 1’ 0” below the infiltrative surface.
HDPE Liner
3” of #57 concrete gravel placed directly on the native soil.
Effluent distribution piping bedded in the 3” of gravel.
Original Infiltrative Surface Elevation
6” Galvanized edging to retain sloped native soil
Slide 6
Slide 7
Slide 8
Slide 9
Remove 2” of native soil containing organic biomass, replace with 3” of #57 gravel and bed the 2” OD distribution piping in the 3” of gravel
Native soil 2” OD effluent distribution piping buried in the gravel
Place 1” of ¾ -gravel over weed barrier
Weed barrier cloth over 3” of gravel and the buried distribution piping
Simplified Section through Perc Area
Statement of Work
Phantom Ranch Percolation/Evaporation Area
Cyclic Repairs 2025
Grand Canyon National Park
PMIS 349488
April 15, 2025
Revised June 12, 2025
Background:
1. EXISTING CONDITIONS
The Phantom Ranch percolation/evaporation area (perc area) was constructed in 2022/2023 as part of the project PMIS
229035, Rehabilitate Phantom Ranch Wastewater [Treatment] Plant (PR WWTP) Tertiary Treatment, Equalization Tank, and Headworks. The perc area was constructed to replace the failing PR WWTP effluent discharge to the Phantom Ranch
Delta irrigation bubbler system and was brought online in January 2024. The existing emergency effluent discharge overflow trench was rehabilitated in 2020/2021 and remains in service if needed.
The perc area functioned nominally until late March of 2024 when the effluent discharge started to pond in the perc area rather than infiltrate quickly into the native soil as the design predicted. Two reasons for the inhibited percolation were identified by the plant operators, one, there was heavy unpredicted plant growth in the perc area and two, there appeared to be an organic biomass growing to a depth of 2 inches in the native soil. Another result of the ponding of the effluent is effluent leakage out the sidewall of the perc area.
2. PROJECT DESCRIPTION
The Phantom Ranch Percolation/Evaporation Area, designed to infiltrate effluent discharge from the Phantom Ranch
Wastewater Treatment Plant (PR WWTP) quickly into the native soil, is not infiltrating properly and the effluent is ponding in the infiltration area.
To stop the ponding, increase the infiltration rate, and prevent effluent leakage through the sidewalls, this project proposes to:
1) Work to be done on one percolation area cell at a time. This will allow the PR WWTP to continue to operate.
2) Remove bird netting from current cell being worked on.
3) Remove one section of sidewall planks to allow small excavator access.
4) Excavate the interior sidewall perimeter of percolation area cell and install HDPE liner (see graphic slide #4, #5, & #7) and backfill.
5) Remove the top 2 inches of native soil from the cell being worked on. The removed native soil will be placed against the interior of the sidewall perimeter at 1:1 slope (see graphic slide #5). Install 6” metal landscape edging to retain slope of native soil placed at perimeter.
6) Place 3 inches of #57 gravel over surface of the percolation area using the previously installed landscape edging to define the limit of the gravel. Bed the effluent distribution piping in the 3 inches of gravel (see graphic slide #4
& #6).
7) Cover the 3 inches of gravel with weed barrier cloth (see graphic slide #8).
8) Place another 1 inch of gravel over weed barrier cloth. This will hold the weed cloth in place and prevent solar degradation.
9) Reinstall sidewall planks and bird netting. Repeat process on adjacent percolation area cell.
3. PRODUCT SPECIFICATIONS
See attached graphic
4. ADDITIONAL INFORMATION
A) Phantom Ranch Delta, 36° 05’ 55.98” N, 112° 05’ 34.63 W, Elev. 2455’
B) Grand Canyon will provide Park staff as a point of contact (POC) while performing work in the Park.
C) Upon completion of project, contractor will furnish GRCA with a report containing the following:
a. A summary of work performed
b. A list of any additional recommended repairs
c. Cost estimate for repairs identified in b. above
D) Contractor to provide material submittals to the assigned Park Contracting Officers Representative (COR) for Park approval.
E) All contractor communication concerning this contract will be through the assigned Park COR.
F) Construction activities will allow Park staff to continue their regular work schedule.
G) Work hours will be approved prior to commencement of project.
H) No weekend work will be authorized unless approved in advance.
5. PERIOD OF PERFORMANCE
A) (8) Weeks
5. ATTACHMENTS
A) Perc Area Cyclic Repairs Graphic Mod 1 Final 27Mar2025.PDF
B)
GRCA PMIS #327717 GENERAL REQUIREMENTS Page 1
Grand Canyon National Park
Phantom Ranch Percolation Area Cyclic Repairs
PMIS #349488
PROJECT SPECIFICATIONS
GENERAL REQUIREMENTS
By: Lou Rogers
Date: April 15, 2025
Revised: June 12, 2025
Table of Contents
SECTION 01 11 00 - SUMMARY OF WORK
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.2 REFERENCE DOCUMENTS / REPORTS
1.3 CODES, STANDARDS, & REGULATIONS
1.4 PERMITS
1.5 GOVERNMENT-FURNISHED ITEMS
1.6 PUBLIC / STAFF USE OF THE SITE
1.7 CONTRACTOR USE OF SITE
1.8 INNER CANYON BUNKHOUSE CODE OF CONDUCTS
SECTION 01 11 40 - WORK RESTRICTIONS
1.1 WORK RESTRICTIONS
SECTION 01 27 00 – DEFINITION OF ONTRACT LINE ITEMS (CLIN’s)
1.1 LIST OF CONTRACT LINE ITEMS
SECTION 01 31 00 - PROJECT MANAGEMENT
1.1 SUBMITTALS
1.2 PRECONSTRUCTION AND PROGRESS MEETINGS
1.3 REQUESTS FOR INFORMATION (RFI’s)
GRCA PMIS #327717 GENERAL REQUIREMENTS Page 2
SECTION 01 33 23 - SUBMITTAL PROCEDURES
1.1 SUBMITTAL PROCEDURES
SECTION 01 35 23 – SAFETY REQUIREMENTS (SECTION 01 35 23)
1.1 SAFETY REQUIREMENTS
SECTION 01 40 00 – QUALITY REQUIREMENTS
1.1 QUALITY REQUIREMENTS
SECTION 01 50 00 – TEMPORARY FACILITIES & CONTROLS
1.1 TEMPORARY FACILITIES & CONTROL
SECTION 01 65 50 – Product Delivery, Storage, and Handling
1.1 SUMMARY
A. Section includes
1. Scheduling and aviation plan development.
2. Load preparation and rigging responsibilities
3. Flight execution
4. Flight regulations and restrictions
5. Personnel transports
SECTION 01 73 40 - EXECUTION
1.1 EXECUTION
SECTION 01 73 00 – CLOSEOUT PROCEDURES
1.1 SUBSTANTIAL COMPLETION AND FINAL INSPECTION
1.2 CLOSEOUT SUBMITTALS
1.3 DEMONSTRATION AND TRAINING
SUBMITTAL REGISTER
SECTION 01 11 00 - SUMMARY OF WORK
GRCA PMIS #327717 GENERAL REQUIREMENTS Page 3
1.1 WORK COVERED BY CONTRACT DOCUMENTS
A. General: All work outlined below will be performed under a single contract.
B. Project Location: This project is located within Grand Canyon National Park:
Phantom Ranch 36° 0.06' 23.16" N, 112° 0.05' 38.60" W
C. Project Background:
The Phantom Ranch percolation/evaporation area (perc area) was constructed in 2022/2023 as part of the project
PMIS 229035, Rehabilitate Phantom Ranch Wastewater [Treatment] Plant (PR WWTP) Tertiary Treatment, Equalization Tank, and Headworks. The perc area was constructed to replace the failing PR WWTP effluent discharge to the Phantom Ranch Delta irrigation bubbler system and was brought online in January 2024. The existing emergency effluent discharge overflow trench was rehabilitated in 2020/2021 and remains in service if needed.
The perc area functioned nominally until late March of 2024 when the effluent discharge started to pond in the perc area rather than infiltrate quickly into the native soil as the design predicted. Two reasons for the inhibited percolation were identified by the plant operators, one, there was heavy unpredicted plant growth in the perc area and two, there appeared to be an organic biomass growing to a depth of 2 inches in the native soil. Another result of the ponding of the effluent is effluent leakage out the sidewall of the perc area.
D. Project Scope of Work. The Work consists of the following:
The Phantom Ranch Percolation/Evaporation Area, designed to infiltrate effluent discharge from the Phantom Ranch
Wastewater Treatment Plant (PR WWTP) quickly into the native soil, is not infiltrating properly and the effluent is ponding in the infiltration area.
To stop the ponding, increase the infiltration rate, and prevent effluent leakage through the sidewalls, this project proposes to:
1) Work to be done on one percolation area cell at a time. This will allow the PR WWTP to continue to operate.
2) Remove bird netting from current cell being worked on.
3) Remove one section of sidewall planks to allow small excavator access.
4) Excavate the interior sidewall perimeter of percolation area cell and install HDPE liner (see graphic slide #4, #5, & #7) and backfill.
5) Remove the top 2 inches of native soil from the cell being worked on. The removed native soil will be placed against the interior of the sidewall perimeter at 1:1 slope (see graphic slide #5). Install 6” metal landscape edging to retain slope of native soil placed at perimeter.
6) Place 3 inches of #57 gravel over surface of the percolation area using the previously installed landscape edging to define the limit of the gravel. Bed the effluent distribution piping in the 3 inches of gravel (see graphic slide #4
& #6).
7) Cover the 3 inches of gravel with weed barrier cloth (see graphic slide #8).
8) Place another 1 inch of gravel over weed barrier cloth. This will hold the weed cloth in place and prevent solar degradation.
9) Reinstall sidewall planks and bird netting. Bird netting may be damaged when removing. If so, replace in-kind.
Repeat process on adjacent percolation area cell.
GRCA PMIS #327717 GENERAL REQUIREMENTS Page 4
E. Project Sites: The work shall be conducted at (1) location. Scheduling and sequencing to be determined.
1. Project Site 1: Phantom Ranch
1.2 REFERENCE DOCUMENTS / REPORTS
A. General: The following reference documents / reports are attached or available upon request to supplement the information in the specifications:
1. NPS Forms (RFI, CM-16, and QC Daily Report)
2. Site specific project graphics. Graphics include site information, photographs, and project details.
1.3 CODES, STANDARDS, & REGULATIONS
A. General: The Contractor shall complete all work in accordance with the latest versions of applicable codes, standards, and regulations.
1.4 PERMITS
A. General: The Contractor shall obtain all applicable permits associated with the work and comply with all permit conditions furnished by the NPS. A general building permit is not required for work on NPS land;
however, the Contractor must still comply with state and local building code provisions.
1.5 GOVERNMENT-FURNISHED ITEMS
A. The Government may furnish products and materials for incorporation into the work. If the government furnishes products or materials for incorporation into the work:
1. The government will arrange and pay for delivery of government furnished items to the project site based on the contractor’s approved construction schedule.
2. After delivery, the government will inspect delivered items for damage. If items are damaged, defective, or missing, the government will arrange for replacement.
3. The contractor is responsible for receiving, unloading, and handling government furnished items at project site for use in the work.
4. The contractor is responsible for protecting government furnished items during storage, handling, and the work, including damage from exposure to the elements.
5. If government furnished items are damaged as a result of the contractor’s operations, the contractor shall repair or replace the items in-kind.
GRCA PMIS #327717 GENERAL REQUIREMENTS Page 5
Government-Furnished Items: The government will furnish the following products or materials for use on this contract: None anticipated at the outset of the contract.
1. Bid Option #1: Contractor to provide their own helicopter operation. Elements of specification section 01
65 50 will be applicable.
1.6 PUBLIC / STAFF USE OF THE SITE
A. General: The project site will be open to staff during construction. The Contractor shall at all times conduct his operations to ensure the least inconvenience to the public and staff. Temporary closures may be permitted upon specific written approval of the Contracting Officer.
B. Other Contracts, Work, and Events: During the contract performance period, there may be other contracts, work, or events occurring in the park or within the project area limits that may affect the Contractor’s operations. The Contractor shall conduct his operations in consideration of these other activities. If the other activities are affecting the critical path of the construction schedule, the Contractor shall document the issue in the daily reports and report the issue to the Contracting Officer. The following contracts, work, or events are known to be occurring during the contract performance period: None anticipated at the outset of the contract.
1.7 CONTRACTOR USE OF SITE
A. General: Limit construction operations to the project area limits as outlined on the attached Site Location
Map.
B. Park Regulations: Ensure all personnel (contractors, subcontractors, and vendors) entering or working in the park are familiar with and obey all park regulations. Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity.
C. Park Entry: Vehicles associated with the Contractor shall be waived the entrance fee upon entering in a marked company vehicle or by providing the names of employees entering in personal vehicle(s). Please note that the entrance fee is waived only for the purpose of reporting directly to a specific work location. Any deviation for recreational purposes is subject to payment of required entrance fees.
D. Site Access: The contractor shall access the project site as outlined on the attached Site Location Map. Do not drive vehicles off road or access non-project areas without permission from the Contracting Officer or their representative.
E. Working Hours: Regular work hours shall be limited to daylight hours from 7:00 a.m. until 5:00 p.m.
Monday through Friday, excluding government holidays. Work outside regular hours requires advance approval from the Contracting Officer.
F. Staging and Storage: Confine the staging and storage of equipment and materials to the areas as shown on the
Site Location Map or as established at the preconstruction meeting. The Contractor will be responsible for the security of all equipment and materials at the jobsite.
G. Property Damage: The Contractor is required to report missing, lost, stolen, or damaged property occurring within the park. This report must be made to a Law Enforcement Ranger or Park Dispatch at the first available opportunity at: 928-638-7805
GRCA PMIS #327717 GENERAL REQUIREMENTS Page 6
H. No Smoking Policy: Smoking is prohibited inside or outside within 25 feet of any buildings in the park. This applies to existing buildings and buildings under construction or renovation. Discarding of tobacco products or debris anywhere other than into designated tobacco receptacles is considered littering and subject to fines.
I Construction Camp: The Contractor will be allowed to use one of the two bedrooms in the Phantom Ranch Trail Crew Bunk House during construction. The bedroom has three bunk beds that will accommodate up to 6 Contractor crew members. The bunk house has a full kitchen that will be shared with personnel who may be using the other half of the sleeping quarters. If the Contractor requires housing for more than 6 personnel at a time, Contractor can provide tent camping facilities in the volleyball court area adjacent to the bunk house. The Contractor shall provide a site plan and proposed tent enclosures for approval by the Contracting Officer prior to the beginning of construction. All personnel will be allowed to use the kitchen and bath facilities of the bunk house.
Contractor will only use the designated campsite area for overflow crew members that cannot be accommodated in the bunk house.
1. Clean and organize lodging facilities daily to mitigate exposure to rodents. Place trash into an NPS approved, Contractor-provided trash receptacle daily. The Contractor will use a helicopter to backhaul trash from the project site. The Contractor will not use any Park-provided dumpster or trash cans for personal trash or other project trash. Any food or trash stored outdoors must be kept in a hard-sided, rodent-proof container at all times.
2. Return the lodging and camping area facilities to pre-project condition at the completion of work. Any damage to lodging and camping area facilities will be repaired or replaced a no additional cost to the NPS, including, but not limited to: structures, deck, finishes, furniture, fixtures, and appliances.
3. The use of TV in the canyon is not allowed unless otherwise approved by the Contracting Officer.
4. No telephone is available for Contractor use. See Section 01 73 40, Execution for requirements on phone installation, should Contractor require phone service.
5. Contractor to arrange a pre-move in and post-move out inspection of the bunkhouse with the Contracting
Officer.
6. Contractor will be allowed the use of one of the two refrigerators in the kitchen area and approximately one-half of the freezer space designated for bunk house occupants.
7. Comply with the NPS Code of Conduct for Bunkhouses and Bunkhouse_Checklist_contractor. Copies of these documents are provided as supplements to this Section, 01 11 00, Summary of Work.
8. Comply with NPS Backcountry Rules and Regulations for Grand Canyon National Park, which can be found at Backcountry Rules and Regulations - Grand Canyon National Park (U.S. National Park Service)
(nps.gov). A backcountry permit will not be required for personnel using the bunkhouse and campsite area in accordance with this specification.
9. Contractor will provide advance notification to the Contracting Officer of planned occupancy levels for the bunkhouse and campsite area. Provide notification at least one week in advance for each week while using the bunkhouse and campsite area.
1.8 INNER CANYON BUNKHOUSE CODE OF CONDUCT
Work
The primary purpose for Inner Canyon bunkhouse use is to facilitate the completion of NPS work projects. These are
NOT party trips and events. We expect all workers and participants to be fully engaged and actively participate in all required duties for the duration of each trip. This includes shared activities: loading and unloading, cooking, doing dishes, keeping facilities clean, and completing final facility cleaning prior to departure.
Cooperation
Bunkhouse users often consist of employees from different divisions, NPS contractors, and volunteers. Rangers are expected to walk through the bunkhouse to check fire and safety equipment, look for emergent issues (broken pipes, running water, fire hazards, etc.) and check security. Establishing good working relationships is essential in shared https://www.nps.gov/grca/planyourvisit/backcountry-regs.htm https://www.nps.gov/grca/planyourvisit/backcountry-regs.htm
GRCA PMIS #327717 GENERAL REQUIREMENTS Page 7 quarters and requires full cooperation from everyone. Do your part to keep the bunkhouse clean. People may be working difference work schedules, so maintaining quiet hours and respect for the sleep of others is mandatory!
Quiet Hours
There are park visitors camping nearby and other residents in close proximity. At these locations, voices and noise carries and echoes, and we do not want to impact the experience of others. Many campers are exhausted and go to sleep at dark.
Quiet hours must be observed at these facilities from 8pm to 6am. However, noise can be unreasonable at any time of day, when other people are disturbed through inconsiderate or reckless behavior. If there is any non-adherence to these rules, you may be contacted by a Law Enforcement Ranger.
Professionalism, Rules, Alcohol and Drug Policy
NPS rules and regulations will be adhered to at all times. The use of alcohol in the Inner Canyon Bunkhouses, campgrounds and overflow areas is prohibited during or after work hours. Likewise, transport of alcohol by NPS on-duty staff or livestock is prohibited. Illegal drugs are against the law and will not be tolerated. Federal drug laws apply. We expect everyone to be professionals at all times.
Noncompliance with rules or regulations may result in the offender being expelled from temporary backcountry quarters and/or revocation of privileges to use bunkhouses by the offending program/division.
Dark Skies
Grand Canyon National Park is conserving our Dark Skies. Please do your part by closing the blinds on all bunkhouse windows after dark.
Rodents
All of the Inner Canyon Bunkhouses are prone to mouse infestations. Please keep the door closed except when walking in or out of the bunkhouse. Maintain good housekeeping measures…sweep floors and wipe counters after each and every meal preparation. Store food properly (rodent proof containers) when not in use (no leftover sandwiches and trail mix in your backpack on the floor overnight, etc.) If you see mice (or mouse sign) in the bunkhouse, please follow the Integrated
Pest Management notification procedure.
Positive Attitude
Maintain a positive attitude, be flexible, patient, and open to learning from others. The way you interact with others and with the group as a whole has an impact on the work and the reputation of your particular crew, so please be positive and professional.
SECTION 01 11 40 – WORK RESTRICTIONS
1.1 WORK RESTRICTIONS
A. General: The Contractor must comply with the following work restrictions:
B. Vehicles / Heavy Equipment:
1. Rules of the Road: All vehicles and heavy equipment will comply with posted traffic regulations, including speed limits and double-yellow center lane markings. Vehicles and heavy equipment shall take every safe opportunity to use paved roadside pullouts in order to allow faster moving traffic to pass.
Failure to comply with traffic regulations will result in a citation being issued to the driver.
2. Vehicle Parking: The contractor shall park vehicles and heavy equipment in designated areas as shown on the Site Location Map or as established at the preconstruction meeting. Vehicles are not permitted within long-term or overnight parking along park roads or in associated overlooks / pullouts.
GRCA PMIS #327717 GENERAL REQUIREMENTS Page 8
3. Driveways and Entrances: The contractor shall keep driveways and entrances serving the premises clear and available to the government, government employees, and emergency vehicles at all times.
4. Vehicle Exhaust: All vehicles will be properly maintained to ensure that the exhaust produced is within legal limits. Effects of excessive vehicle exhaust may be subject to enforcement of State and Federal laws regarding emissions as well as those regarding threatened and endangered species.
5. Spills: The Contractor shall be responsible for any cleanup efforts required in accordance with 40 CFR and all applicable state environmental quality laws regarding disposal and cleanup of hazardous / industrial wastes. The Contractor must immediately notify the Contracting Officer of spills.
6. DOT Compliance: All vehicles are to be compliant with all DOT requirements including but not limited to driver with appropriate license class, medical examiner card as appropriate with license class, carrying three (3) triangles or three (3) flares, mounted fire extinguisher, and valid DOT safety sticker.
7. Slow Vehicles: The Contractor is to notify the Contracting Officer of slow vehicles that may cause traffic delays or extended traffic lines. Vehicles that are slow are requested to enter the Park AFTER 2:00 p.m.
and exit the Park BEFORE sunset.
8. Oversized Vehicles: Oversized vehicles are defined as vehicles where the width of the vehicle or load exceeds one lane (i.e., beyond the center line of the paved road). Oversized vehicles must not exceed the clearances along the Park road corridor. Oversized vehicles will require an escort and drivers must avoid driving on the edges of the Park road. The Contractor is to notify the Contracting Officer of oversized vehicles, scheduled dates, and estimated arrival times at the park entrance; and the identity of who is escorting the vehicle (e.g., police, contractor, etc.). Vehicles that are oversized are requested to enter the
Park AFTER 2:00 p.m. and exit the Park BEFORE sunset.
9. Tracked Equipment: Heavy equipment with metal tracks will not be allowed on paved asphalt or concrete roads without adequate protection to prevent permanent track marks, spalling, and other damage. The method of protection (such as secured plywood or metal plates), shall also not damage the roads. Tracked vehicles will be allowed on non-paved surfaces as long as the terrain is restored to preconstruction condition. All damage created by tracked equipment shall be repaired / restored at no additional expense to the government.
10. Road & Weight Restrictions: All vehicle load, weight, and size limitations, as established by State law, apply to vehicles operated on the Park road (36 CFR § 4.11). No loads heavier than the current load rating for park roads and bridges will be permitted.
C. Resource Protection:
1. General: The Park is committed to protecting natural and cultural resources found within the park and adjacent lands. The Contractor must comply with the following rules and conditions:
2. Preservation of Natural Features: Prevent damage to natural surroundings.
a. Do not attach ropes, wires, guy lines, cables, or chains to trees or vegetation. Restore damaged areas and replace damaged trees, vegetation, and grass at no additional expense to the government.
3. Invasive Species Prevention: The introduction of non-native invasive species can threaten the Park’s rare and endangered species or can create new populations of non-native species not traditionally found in the Park. The Contractor is required to inform personnel, subcontractors, and vendors to thoroughly clean all vehicles, equipment, machinery, tools, supplies, and materials prior to packing / loading.
GRCA PMIS #327717 GENERAL REQUIREMENTS Page 9
a. Vehicles, machinery, and equipment must be clean and free of debris PRIOR to entering the park.
b. Vehicles, machinery, and equipment must be thoroughly pressure washed and visibly free of mud, dirt, plant debris, frogs, frog eggs, insects and other debris. A hot water wash is preferred. Areas of concern include bumpers, grills, hood compartments, areas under the battery, wheel wells, undercarriage, cabs, and truck beds.
b. The interior and exterior of vehicles, machinery, and equipment must be free of rubbish and food. The interiors of vehicles and the cabs of machinery must be vacuumed clean. Floor mats will be sanitized with a solution of >70% isopropyl alcohol or a freshly mixed 10% bleach solution.
c. Vehicles, machinery, and equipment may be subject to inspection PRIOR to entering the park. Initial inspections are typically performed at the loading dock, point of origin, or at a designated location outside park boundaries.
Contact the following park inspectors at least 3 days in advance of park entry or delivery to arrange for inspections:
Primary Inspector: TBD Backup Inspector: TBD
d. Vehicles, machinery, and equipment that do not pass inspection will be turned away.
e. Vehicles, machinery, and equipment leaving the park for any reason must be cleaned prior to re-entry into the Park and may require re-inspection at the Park’s discretion.
f. Vehicles, machinery, equipment, and materials remaining in the park over a 24-hour period may be inspected by the Park for invasive species.
g. In addition to visual inspection for plant debris, insects, soil, frog and frog eggs, testing for invasive ants is part of the inspection prior to entry into the park or at a predetermined location. To expedite the process, make sure vehicles, machinery, equipment, and staging areas used are clean as described in (b.) above.
h. The park reserves the right to conduct additional tests for ants at any time during the course of the project.
i. Base yards and staging areas in and outside the park must be kept free of invasive pests.
i. Base yards and staging areas may be inspected for invasive pests at the beginning of the project or at any other time the Park deems necessary.
j. Pest control records may be requested anytime at the Park’s discretion.
k. Vehicles and equipment stored outside of a base yard or staging area, such as a private residence, should be kept in a pest free area. Such vehicles or equipment may be subject to additional inspection and will be turned away if infested.
4. Endangered Species: Endangered species are protected by Federal law. Obey all park regulations.
Drivers must obey all traffic laws and watch for animals on or alongside road or at the jobsite. Contact
Park Dispatch at 911 immediately if animal is hit or injured or will not move off the road. The following measures are required to minimize disturbance to endangered wildlife:
GRCA PMIS #327717 GENERAL REQUIREMENTS Page 10
a. Work shall be conducted to ensure the work area is cleaned up at the end of each work shift so that loose tools, debris, and materials are not left out in a manner that could present a hazard to a listed species.
b. Noise and vibrations of equipment shall be kept to a minimum when working in the vicinity of a listed species.
c. Hazmat spill prevention protocols shall be employed when using gas-powered equipment.
d. Tarps shall be used to contain all paint chips and building debris from exterior surfaces that may fall to the ground.
e. Ensure loose nails and screws do not make it to the ground when working on exterior surfaces as these can be detrimental to listed species.
f. Ensure no standing water on tarps or other construction surfaces as this may be a breeding ground for mosquitoes.
5. Archaeological Resources: Archaeological resources are physical evidence of past human activity, including evidence of the effects of that activity on the environment. Archaeological resources are found above and below the ground and underwater. The Contractor, or designee, will observe all ground-disturbing activities in archaeological sensitive areas. If the Contractor discovers resources, the
Contractor shall stop work or relocate to a non-sensitive area and notify the Contracting Officer immediately. The Park may also have an Archaeological Monitor at the jobsite who is authorized to stop work upon discovery of archaeological resources. Archaeological resources typically found in the park or at the project site will be discussed further at the preconstruction meeting.
6. Soundscape / Noise: The Contractor shall minimize noise levels at the project site to protect the soundscape of the park. Perform noise-producing work in less sensitive hours of the day or week or as directed by the Contracting Officer.
The following sections are mitigations copied directly from the Letter of Compliance Completion for PEPC project
#112986 and are specific to this project.
Cultural Resources
• Although there is no surface evidence of archaeological resources, clearance to proceed is recommended with the condition that if concealed archeological resources are encountered during project activities, all necessary steps will be taken to protect them, and the Park Cultural Resources Manager will be notified immediately.
• Areas selected for staging equipment and materials are expected to be located in existing disturbed areas where there is no potential for archaeological resource disturbance. Contact the park's Cultural Resource Program Manager before creating/utilizing any staging areas not previously addressed or reviewed for this project.
• Fence type: To avoid a potential "adverse effect" a Natina steel chain link fencing and posts (providing weathering steel look) at the minimum height required by ADEQ is recommended for use at Hermits Rest and Yaki Point.
Human Health and Safety
• Contractor to submit a site-specific safety plan to PM/COR. PM/COR will send safety plan to the Park Safety Officer, Christina Ryan-Miller (christina_ryan-mi11er@nps.gov) prior to commencement of work. Safety plan shall demonstrate compliance with OSHA and other applicable safety laws. It shall include an emergency safety plan and shall list contractor points of contact.
Park Operations and Management
• Contractor will alert the PM/COR who will then contact commercial services Park representatives, Victoria St.
Clair (victoria stclair@nps.gov) or Laurie Dyer (laurie dyer@nps.gov) should there be any service interruptions affecting concessioners.
GRCA PMIS #327717 GENERAL REQUIREMENTS Page 11
Soils, Topography, Geology
• Although there is no surface evidence of paleontological resources, clearance to proceed is recommended with the condition that if concealed paleontological resources are encountered during project activities, all necessary steps will be taken to protect them. PM/COR will contact Science Resource Management, Mark Nebel and/or Anne Miller (Geosciences program staff) when notified by contractor that paleontological resources have been encountered.
Vegetation
• Vegetation material removed from Phantom Ranch during the project that is unusable for revegetation efforts shall be disposed in the Colorado River by throwing it off the Silver Bridge. Face upstream and look for boats, do not throw when boats are in-view upstream of the bridge. Wait until any boats have passed the bridge downstream by at least 1/4 mile. NPS staff shall work with the project manager to determine the appropriate location.
• Vegetation removal, especially for the Phantom Ranch project area, will be minimized to the greatest extent possible while allowing for construction to proceed. If needed, revegetation of native plants will occur.
• No other surface-disturbing work or vegetative clearing shall occur without written permission from an authorized representative of the National Park Service.
• Upon project completion, the vegetation program shall survey and monitor the project area for invasive plants and respond accordingly to eliminate any invasive species.
• Pruning necessary for the project, and for any future periodic maintenance in the area, will adhere to the park's pruning guidelines with the goal of retaining health and integrity of trees and shrubs treated. Damage to trees or roots in or adjacent to project areas during construction will be avoided as much as possible, if avoidance is not possible, root pruning guidelines will be followed. The pruning guidelines are available from Vegetation Program Management staff.
• Equipment and supplies should be staged and stored in already disturbed areas on site and should not create any new impacts to vegetation resources.
Wilderness
• Helicopter flights over areas of proposed wilderness would degrade opportunities to experience solitude.
• To minimize flights over areas of proposed wilderness: 1) sling loads will be arranged so as to minimize the number of flights required to complete all transportation necessary, and 2) materials, tools, equipment, etc. will be staged at the helibase so that they may be transported to the worksite on other scheduled flights to the extent possible.
Wildlife
• Wildlife Department personnel shall be notified/consulted when any wildlife must be disturbed or handled. They will be available to assist with moving/relocating wildlife, when necessary, and/or to make recommendations for relocating any disturbed animals.
• For any projects involving trenching or digging holes, provisions (generally in the form of ramps with a slope< 45°) must be made every 20-50' to allow for the escape of animals that may fall into these recesses, and/or they must be covered in such a way as to prevent animals (vertebrates) from falling in them.
• If condors visit a project site, project activities will cease until the condors leave on their own or until permitted personnel use approved techniques that result in condors leaving the area.
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS (CLIN’s)
1.1 LIST OF CONTRACT LINE ITEMS
GRCA PMIS #327717 GENERAL REQUIREMENTS Page 12
A. Contract Line Item No. 01:
1. Make repairs to the percolation area as defined in the scope of work and the summary of work
2. Measurement for payment will be in accordance with the schedule of values.
3. Payment will be made at the contract lump sum price in accordance with the percentage of work completed.
SECTION 01 31 00 – PROJECT MANAGEMENT
1.1 SUBMITTALS
A. Division 01 Submittal Documents: The following documents shall be submitted no later than 14 calendar days after contract award and a minimum of seven (7) calendar days prior to the Preconstruction Meeting. If all of these documents have not been received prior to the scheduled Preconstruction Meeting date, the meeting will be cancelled and the Notice to Proceed (NTP) will not be issued. Work shall not commence until written Notice to Proceed (NTP) has been issued.
1. Letter designating the Project Superintendent.
2. Construction Schedule - Submit a baseline schedule with start date, end date, major work activities and durations, estimated pre-final (substantially complete) and final (entirely complete) inspection dates, and other major milestones. Provide updates to baseline schedule as needed or as requested (when there is a change to the critical path).
3. Schedule of Values (SOV) – Submit a schedule of values with a breakdown of component work activities for which progress payments will be requested. The total costs for the component work activities shall equal the total contract price.
4. Accident Prevention Plan (APP) – Submit a “site specific” accident prevention plan with the following information (at a minimum). Refer also to PART 5 Safety Requirements.
a. Name of the supervisor responsible for executing the plan.
b. Emergency contact phone numbers (include NPS dispatch at 928-638-7805, or dial 911.
c. Map of local area emergency medical facilities relative to the jobsite.
d. First aid and emergency medical procedures / forms.
e. Company safety plan / protocol.
f. Job hazard analysis (JHA) completed for each major work activity.
5. Quality Control Plan (QCP) – Submit a “site specific” quality control plan with the following information
(at a minimum). Refer also to PART 6 Quality Requirements.
a. Name of the supervisor responsible for executing the plan.
b. Organizational flow chart showing key staff / subcontractors.
c. Qualifications of key staff and subcontractors with applicable licenses / certificates.
d. Communications and reporting plan / procedures / forms (include NPS daily report form, RFI form, and CM-16 form along with Contractor forms).
e. Testing and inspection procedures at all phases of the project (i.e. preparatory, initial, follow-up) to ensure quality, with steps for correction of work / re-work.
GRCA PMIS #327717 GENERAL REQUIREMENTS Page 13
6a. Storm Water Pollution Prevention Plan (SWPPP) – For projects with ground disturbance estimated to be greater than 1-acre. Not Applicable
6b. Under-An-Acre Pollution Prevention Plan (UPPP) - For projects with ground disturbance estimated to be less than 1-acre, complete and submit an UPPP to the NPS with best management practices (BMP’s) to prevent the discharges of pollutants. BMP’s shall be checked daily and after storm events to ensure they are performing as intended.
7. Construction Waste Management Plan – Submit a construction waste management plan that addresses storage, handling, and disposal of all trash, recyclables, non-hazardous construction waste, and hazardous waste generated from the execution of the work. Refer also to PART 8 Execution.
8. A list of Subcontractors for this project.
9. Written statements from subcontractors certifying compliance with applicable labor…
This is the start of the file's text. The full file is on GovTribe.