About this file

This document is a set of Questions and Answers related to Amendment 01 of Solicitation #140P1524Q0029 for the GLAC-HQ Fiber Internet Installation contract opportunity.

The key details are:

  • The National Park Service (NPS) is seeking to install new fiber optic cables and conduit to extend service from the park boundary to the Park Headquarters building.
  • The existing fiber optic infrastructure along US-2 is not owned by the National Park, but is believed to be owned by MtnMax or BNSF.
  • The Park Headquarters building is currently served by an outdated copper line from Lumen, and has no existing fiber optic infrastructure.
  • The contractor will be responsible for coordinating with local fiber optic service providers to extend service to the park boundary and the Park Headquarters.
  • No other solicitation clauses or dates are changed by this Amendment.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of the Interior

NATIONAL PARK SERVICE

CONTRACTING OPERATIONS - CENTRAL

1849 C Street

NW Washington, DC 20240

General: No other solicitation clauses or dates change with this Amendment.

Contracting Officer: Taylor Jones, Taylor_A_Jones@nps.gov, 520-780-9294

Solicitation #: 140P1524Q0029

Amendment #: 01

Fiber Optic Install – GLAC

Questions and Government Responses listed below:

QUESTIONS:

Question # Question Answer/Response

1. Regarding your bid document, specifically on page 32, it mentions, "An existing fiber optic line runs along US-2, with the service extension requirement from US-2 to the

Park's northern entrance at the Middle Fork Flathead

River bridge." Could you clarify if the National Park owns the existing dark fiber along US-2? If so, could you specify the connection point for this dark fiber? If not, may we request the ownership details of the fiber?

The Park does not own any fiber lines outside of the park boundary.

We believe MtnMax owns a line along US-2 close to West Glacier but the park does not know where it runs or ends.

We believe it’s BNSF fiber.

2. Do you already have an ISP? Is the job running fiber between buildings, or into new construction?

The Park Headquarters building is served by an outdated copper line that is serviced by Lumen. No fiber optic infrastructure exists between the Park Boundary and the Park

Headquarters building. See response to question 3.

3. Or is this bid for running from the ISP node all the way to the national park?

The Contractor will coordinate with local fiber optic service providers to extend service to the Park Boundary and to the Park Headquarters building. New fiber optic cables and conduit shall be installed.