This is a Request for Proposals (RFP) for a firm-fixed-price construction task order under a Multiple Award Indefinite Delivery/Indefinite Quantity (MATOC) IDIQ contract issued by the National Park Service (NPS), Department of the Interior.
The solicitation seeks proposals for water system improvements to meet fire protection requirements at Fossil Butte National Monument in Lincoln County, Wyoming. The work includes construction of a new 6-inch PVC fire water line serving the Visitor Center; installation of a new 45,000-gallon underground fiberglass water storage tank; connections to existing water supply lines; installation of a new fire pump; construction of a fire pump house with utility services; installation of a propane-fueled emergency generator within a cold-weather enclosure; piping from a new propane storage tank; electrical connections to the Visitor Center and pump house; construction of a site enclosure wall and grading at the generator location; and installation of an integrated fire suppression system within the existing Visitor Center. The project is set aside for Total Small Business, with a NAICS code of 236220 (Commercial and Institutional Building Construction) and a size standard of $45 million. The contract magnitude is valued between $1 million and $5 million. Performance is required to commence within 10 calendar days after notice to proceed and be completed within 595 calendar days (612 calendar days after award including final cleanup). Performance and payment bonds at 100 percent of the contract price are required within 10 calendar days after award. Proposals are due by 1:00 p.m. local time on July 20, 2026, submitted via email to the Contracting Officer. An organized site visit is scheduled for June 30, 2026, at 11:00 a.m. Mountain Daylight Time at the Fossil Butte Visitor Center in Kemmerer, Wyoming.
Evaluation will be conducted on a best-value basis using qualitative adjectival ratings without numerical scoring. The five evaluation factors are: (1) Project Experience—demonstrating similar projects completed within the past five years valued between $2 million and $5 million; (2) Key Personnel Experience—resumes for Project Manager (minimum five years managing $2 million+ projects), Superintendent (minimum five years field supervision), Quality Control Supervisor (minimum three years quality control experience), and On-Site Safety Supervisor (demonstrated construction safety program experience); (3) Schedule—Microsoft Project Gantt Chart format with at least 20 discrete activities, critical path identification, major milestones, long lead items, and predecessor/successor relationships, assuming September 14, 2026, notice to proceed; (4) Safety—company safety program overview, project-specific safety procedures, OSHA 300A logs for three prior calendar years, current EMR documentation, and safety supervisor credentials; and (5) Price—completed price schedule with supporting breakdown. All non-price factors are equally weighted and collectively equal in importance to price. Proposals must be submitted in two volumes: Volume I (Non-Price Proposal in PDF format covering Factors 1-4) and Volume II (Price Proposal in PDF format covering Factor 5). Each email transmission shall not exceed 25 MB. Liability insurance is required with minimum coverage of $200,000 per person, $500,000 per occurrence, and $500,000 property damage. Contractor must maintain an active registration in the System for Award Management (SAM) at proposal submission, award, and throughout contract performance. Final payment requires submission of all payrolls including subcontractors, SF 1413 statements for subcontractors, project schedule, progress reports, material submittals, test reports, as-built drawings, warranty of construction, and a signed Release of Claims (DI-137 form). Payment requests must be submitted electronically through the U.S. Department of the Treasury's Invoice Processing Platform (IPP).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P1426R0008_Amd_0001.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NO.
5. REQUISITION/PURCHASE REQUEST NO.
CODE
6. PROJECT NO.
8. ADDRESS OFFER TO
4. CONTRACT NO.
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
NEGOTIATED (RFP) REQUEST FOR PROPOSAL
3. DATE ISSUED PAGE OF
SEALED BID (IFB) INVITATION FOR BID
9. FOR
INFORMATION CALL
PAGES
140P1426R0008
NPS, IMR - Northern Rockies MABO PO Box 168 Mammoth Supply Center / 22 Stable St Yellowstone NP WY 82190 stacy_vallie@ios.doi.gov
PIR
Stacy Vallie 4064044167
06/22/2026
07/20/2026
10 595 FAR Clause 52.211-10
Project Name: Water System Improvements to Meet Fire Protection Requirements for Fossil Butte National
Monument
Type of Contract: Firm Fixed Price Construction Task Order
Set-Aside: Total Small Business
Magnitude (FAR 36.204): Between $1,000,000 and $5,000,000
NAICS CODE: 236220 - Commercial and Institutional Building Construction
SIZE STANDARD: $45.0M
The Government contemplates award of a firm-fixed price task order resulting from this solicitation.
See Section L "Instructions, Conditions and Notices to Offerors" for proposal submission specifics.
Continued...
1 32
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AWARD (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 12/2022) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT
27. PAYMENT WILL BE MADE BY
10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
Continued...
AMENDMENT
NUMBER
DATE.
NPS, IMR - Northern Rockies MABO PO Box 168 Mammoth Supply Center / 22 Stable St Yellowstone NP WY 82190
PIR
Stacy Vallie
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140P1426R0008
Offerors shall complete block 19 of the SF 1442 to acknowledge any solicitation amendments.
Questions shall be submitted in writing to
Stacy_Vallie@ios.doi.gov no later than 5 business days prior to the solicitation close date. No phone calls please.
Period of Performance: 09/14/2026 to
04/30/2028
00010 Water System, Electrical System and Fire
Protection for the Visitor Center
PART I – THE SCHEDULE
SECTION A – SOLICITATION/CONTRACT FORM
ALL BASE MATOC IDIQ CLAUSES APPLY TO THIS TASK ORDER.
This is a Request for Proposals (RFP), in accordance with the Specifications and Drawings and is issued on Standard Form (SF) SF1442 in the preceding pages.
The Government will evaluate all Proposals in an impartial manner and consideration will be given to those with the highest perceived value to the government based on responses to the evaluation factors identified in Section M.
In accordance with FAR subpart 16.505. A price evaluation will be performed to determine the reasonableness of the proposed price. Reasonableness will be determined considering other competitive prices received and comparison to the Independent Government Cost Estimate.
(END OF SECTION A)
SECTION B – SERVICES AND PRICES
Proposal pricing shall be provided in accordance with Section L and is incorporated herein. The contractor must furnish an itemized breakdown. Contractor shall use the Price Schedule provided as an attachment.
Project Title: Water System Improvements to Meet Fire Protection Requirements Location: Fossil Butte National Monument, Lincoln County, Wyoming Solicitation No.: 140P1426R0008 Park – PMIS NO.: FOBU - 282711
CONTRACT PRICE SCHEDULE
Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts govern. Round totals and extended prices to whole dollars.
SCHEDULE OF BASE ITEMS
CLINS TITLE QTY UNIT Unit Price Total Price
10 Water System, Electrical System and Fire Protection for the Visitor Center 1 LS
TOTAL BASE PRICE (CLIN 10):
All measurements and payment information are included in Division 01 Specifications Section 01 27 00 Definition of Contract Line Items.
(END OF SECTION B)
SECTION C – SPECIFICATIONS/DRAWINGS
ALL BASE MATOC IDIQ CLAUSES APPLY TO THIS RFP AND TASK ORDER
The work under this task order includes construction of a new 6-inch PVC fire water line serving the Visitor Center; installation of a new 45,000-gallon underground fiberglass water storage tank; connections to existing water supply lines; installation of a new fire pump; construction of a fire pump house and associated utility services;
installation of a new propane-fueled emergency generator within a cold-weather enclosure; piping from a new propane storage tank; electrical connections to the Visitor Center and new pump house; construction of a site enclosure wall and grading at the generator location; and installation of an integrated fire suppression system within the existing Visitor Center, including associated fire alarm and electrical work and restoration of finishes impacted by construction activities.
Specifications, drawings, and other supporting documents are attached and incorporated herein by reference. Refer to Section J.
A separate Title III Architect-Engineer (A-E) task order will be issued in accordance with the contract specifications to provide independent construction administration, observation, and quality assurance services throughout project execution. The A-E firm responsible for the original design shall perform these services to help ensure compliance with the design intent and maintain technical continuity throughout construction.
1452.236-70 Prohibition Against Use of Lead-based Paint - Department of the Interior (Jul 1996)
Paint containing more than .06 percent by weight of lead in paint, or the equivalent measure of lead in the dried film of paint already applied, shall not be used in the construction or rehabilitation of residential structures under this contract or any resulting subcontracts.
(End of clause)
(END OF SECTION C)
SECTION D - PACKAGING AND MARKING
Contractor initiated correspondence and submittals shall identify the task order number and the associated contract number. Task order requirements will be detailed at the task order level, but correspondence includes the Submittal Register and Construction Schedule/Reports. Submittals shall be submitted to the Contracting Officer's Representative (COR) and copied to the task order CO. If hard copies are required, specific task order documentation or meetings will detail submission addresses.
(END OF SECTION D)
SECTION E – INSPECTION AND ACCEPTANCE
The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(END OF SECTION E)
SECTION F – PERFORMANCE
Work shall be completed by skilled personnel per industry standards and manufacturer specifications.
52.211-10 Commencement, Prosecution, and Completion or Work (Apr 1984)
The Contractor shall be required to:
(a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed,
(b) prosecute the work diligently, and
(c) complete the entire work ready for use not later than 612 calendar days after award. The time stated for completion shall include final cleanup of the premises.
(END OF SECTION F)
SECTION G – CONTRACT ADMINISTRATION DATA
1. CONTRACT REPRESENTATIVES:
Contracting Officer (CO):
Stacy Vallie Stacy_Vallie@ios.doi.gov
Contracting Officer’s Representative (COR):
Charles Custer Charles_Custer@nps.gov
2. JOB SITE ADMINISTRATION
The Government’s designated COR will be available at the site to inspect the work as it progresses. The COR will prepare a Daily Log, beginning with the first day of the contract, detailing ground and weather conditions, work being performed, materials delivered, and notes of any problems or difficulties.
Government inspections do not relieve the Contractor of responsibility for providing adequate quality control measures. At the end of every day of work on this contract, The Contractor’s Superintendent, as defined below, shall contact the COR to review the daily log, and sign as the Contractor’s representative. Unless the Contractor’s Superintendent makes a contrary notation on the daily log, the log shall be presumed to be accurate for recording daily inspections and conditions, work accomplished, and notations of any issues as described above. In accordance with FAR 22.406.7(4) regular compliance checks may include comparison to daily inspector’s reports and daily logs of construction to ensure consistency in meeting compliance requirements.
Contractual problems, of any nature, which might occur during the life of the contract, must be handled in conformance with very specific public laws and regulations (e.g., Federal Acquisition Regulation), and must be referred to the CO for resolution. Only the CO is authorized to formally resolve such problems. Therefore, the contractor is hereby directed to bring all such contractual problems to the immediate attention of the CO.
The Contracting Officer (CO) is the only person authorized to approve changes or modify any of the requirements under this contract and notwithstanding any provisions contained elsewhere in this contract, the said authority remains solely with the CO. In the event the contractor effects any such change at the direction of any person other than the CO, the change will be considered made without authority and no adjustment will be made in the contract price to cover increase in costs incurred as a result thereof.
The contractor and the Government may agree to perform a no-cost field change. Field changes are made when the change appears to be mutually beneficial to all parties and would not require changing the negotiated line items. All field changes must be approved by the CO prior to execution.
All correspondence concerning this contract, such as requests for information (RFI), explanation of terms, and contract interpretation, shall be submitted to the CO.
3. FINAL PAYMENT
Final payment will be made only after receipt of all payrolls to include subcontractors, SF 1413 Statement of Acknowledgement for each subcontractor, project schedule, updated progress reports, material submittals, test reports, as-built drawings, warranty of construction, release of claims and any other documents requested by the contracting office as applicable. Contractor must provide a signed copy of the 'Release of Claims' to the Contract Administrator upon submittal of final invoice.
mailto:Stacy_Vallie@ios.doi.gov
4. AVAILABILITY OF UTILITIES SERVICES
Notwithstanding the provisions of contract clause FAR 52.236-14, Availability and Use of Utility Services, all reasonable required amounts of water, gas, electricity, etc., essential to contract performance shall be made available, at no cost to the contractor, from existing systems, outlets, and supplies. All temporary connections, outlets, and distribution lines as may be required will be installed by the contractor at the contractor's own expense.
5. UTILITIES CONSERVATION
The contractor will be required to participate in government energy conservation programs. For the purpose of this contract, utilities such as water, electricity, etc., will be furnished by the government at no cost to the contractor.
6. OCCUPATIONAL SAFETY AND HEALTH ACT (OSHA) INSPECTIONS
The contractor shall be subject to inspections under the OCCUPATIONAL SAFETY AND HEALTH ACT (OSHA) program by inspectors of the Department of Labor.
7. INTERIM AND FINAL INSPECTIONS
1. Prior to covering, enclosing, or hiding any of type work, the Contractor must contact the Government representative to perform an interim inspection. Failure to contact the Government representative perform an interim inspection prior to concealment may result in the Contractor being required to uncover performed work sufficiently to allow for proper inspection.
2. When ready for final inspection, the Contractor shall notify the CO and COR, requesting a final inspection in writing to the CO. The final inspection shall normally be requested a minimum of three (3) calendar days before the desired date or as otherwise negotiated with the Contracting Officer.
3. The final inspection will be onsite with the Contractor, the Contracting Officer’s Representative, and Contract Specialist/Contracting Officer (when possible).
8. CONSTRUCTION CONTRACT ADMINISTRATION
Federal Acquisition Regulation (FAR) 36.211(b) requires agencies provide description of policies and procedures that apply to definitization of equitable adjustments for change orders under construction contracts and data on the time required to definitize equitable adjustments for change orders under construction contracts. This information can be found at: https://www.doi.gov/pam/acquisition/policy/constructioncontract.
DOI AAAP-0050 Notice to Contractors - Contractor Performance Assessment Reporting System (Dec 2015)
1) FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.
2) The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.
3) We request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO). Information in the report must be protected as source selection sensitive information not releasable to the public.
4) When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/.
5) Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/.
a) Contractor Representatives may then provide comments in response to the evaluation or return the evaluation without comment.
b) Your comments should focus on objective facts in the AO's narrative and should provide your views on the causes and ramifications of the assessed performance.
c) All information provided should be reviewed for accuracy prior to submission.
d) If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in the space provided, and then selecting “Accept the Ratings and Close the Evaluation”.
e) Your response is due within 60 calendar days after receipt of the CPAR. On day 15, the evaluation will become available in PPIRS-RC marked as “Pending” with or without comments and whether or not it has been closed.
f) If you do not sign and submit the CPAR within 60 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."
6) The following guidelines apply concerning your use of the past performance evaluation:
a) Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the CO for instructions.
b) Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.
c) Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes. 7) If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period. A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.
(End of notice)
Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (Feb 2021)
Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).
"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To https://www.cpars.gov/ https://www.cpars.gov/ constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.
The contractor shall submit a draft Invoice Package, including copies of the following documents, to the National Park Service’s (NPS) Contracting Officer’s Representative (COR) and Contract Specialist (CS) a minimum of 5 working days prior to submittal of the formal Invoice through IPP. Within 5 working days of receipt, the COR shall provide an acceptability recommendation to both the NPS CS and the contractor. If the COR recommends acceptance, the contractor shall submit a copy of the final version of the checklist and the Invoice Package to the NPS through IPP.
1. Completed copy of the COR’s final Construction Payment Request Checklist (Submit only with the formal submittal to IPP).
2. Completed copy of the Pay Estimate Form (including signed certification of subcontractor payments).
3. Completed copy of the Limitations on Subcontracting Report.
4. Information required by contract clause 52.232-27, Prompt Payment for Construction Contracts.
5. A copy of the current construction schedule (refer to project specification section 013216).
6. A copy of the current Schedule of Values. (refer to project specification section 013216).
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of St. Louis (FRBSTL) within 3 - 5 business days of the contract award date.
Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fiscal.treasury.gov or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
(End of Local Clause)
(END OF SECTION G)
https://www.ipp.gov/ mailto:IPPCustomerSupport@fiscal.treasury.gov
SECTION H - SPECIAL CONTRACT REQUIREMENTS
KEY PERSONNEL (Contractor shall complete section (a) listing Key Personnel per their technical proposal)
(a) The Contractor shall list the Key Personnel assigned to the resultant contract:
Project Manager:
Site Superintendent:
On-site Quality Control Supervisor:
On-site Safety Supervisor:
(b) During the first 60 days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 60-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.
(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. This clause will be modified to reflect any approved changes of key personnel.
(End of clause)
GREEN PROCUREMENT
To the extent that the construction services provided by the Contractor require provision of any of the types of products listed at https://sftool.gov/greenprocurement, the Contractor is expected to provide the green type of product unless that type of product is not available competitively within a reasonable time, at a reasonable price, is not life cycle cost efficient in the case of energy consuming products, or does not meet reasonable performance standards.
(END OF SECTION H)
https://sftool.gov/greenprocurement
PART II – CONTRACT CLAUSES
SECTION I – CONTRACT CLAUSES
ALL BASE MATOC IDIQ CLAUSES APPLY TO THIS RFP AND TASK ORDER
52.252-2 – Clauses Incorporated by Reference (Feb 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
http://www.acquisition.gov
52.222-90 Addressing DEI Discrimination by Federal Contractors (Apr 2026) – DEVIATION (May 2026) 52.226-7 Drug-Free Workplace (May 2024) 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving (May 2024) 52.236-26 Preconstruction Conference (Feb 1995) 52.244-5 Competition in Subcontracting (Dec 1996)
CLAUSES INCORPORATED BY FULL TEXT
52.219-14 Limitations on Subcontracting (Oct 2022) - DEVIATION (Jan 2026)
(a) This clause does not apply to the unrestricted portion of a partial set-aside.
(b) Definition.
Similarly situated entity, as used in this clause, means a first-tier subcontractor, including an independent contractor, that—
(1) Has the same small business program status as that which qualified the prime contractor for the award (e.g., for a small business set-aside contract, any small business concern, without regard to its socioeconomic status); and
(2) Is considered small for the size standard under the North American Industry Classification System (NAICS) code the prime contractor assigned to the subcontract.
(c) Applicability. This clause applies only to—
(1) Contracts that have been set aside for any of the small business concerns identified in 19.000(a)(3);
(2) Part or parts of a multiple-award contract that have been set aside for any of the small business concerns identified in 19.000(a)(3);
(3) Contracts that have been awarded on a sole-source basis in accordance with subparts 19.8, 19.13, 19.14, and 19.15;
(4) Orders expected to exceed the simplified acquisition threshold and that are—
(i) Set aside for small business concerns under multiple-award contracts, as described in 8.405- 5 and 16.505(b)(2)(i)(F); or
(ii) Issued directly to small business concerns under multiple-award contracts as described in 19.504(c)(1)(ii);
(5) Orders, regardless of dollar value, that are—
(i) Set aside in accordance with subparts 19.8, 19.13, 19.14, or 19.15 under multiple-award contracts, as described in 8.405-5 and 16.505(b)(2)(i)(F); or
(ii) Issued directly to concerns that qualify for the programs described in subparts 19.8, 19.13, 19.14, or 19.15 under multiple-award contracts, as described in 19.504(c)(1)(ii); and
(6) Contracts using the HUBZone price evaluation preference to award to a HUBZone small business concern unless the concern waived the evaluation preference.
(d) Independent contractors. An independent contractor shall be considered a subcontractor.
(e) Limitations on subcontracting. By submission of an offer and execution of a contract, the Contractor agrees that in performance of a contract assigned a North American Industry Classification System (NAICS) code for—
(1) Services (except construction), it will not pay more than 50 percent of the amount paid by the Government for contract performance to subcontractors that are not similarly situated entities. Any work that a similarly situated http://www.acquisition.gov/ https://www.acquisition.gov/far/19.000#FAR_19_000 https://www.acquisition.gov/far/19.000#FAR_19_000 https://www.acquisition.gov/far/subpart-19.8#FAR_Subpart_19_8 https://www.acquisition.gov/far/subpart-19.13#FAR_Subpart_19_13 https://www.acquisition.gov/far/subpart-19.14#FAR_Subpart_19_14 https://www.acquisition.gov/far/subpart-19.15#FAR_Subpart_19_15 https://www.acquisition.gov/far/8.405-5#FAR_8_405_5 https://www.acquisition.gov/far/8.405-5#FAR_8_405_5 https://www.acquisition.gov/far/16.505#FAR_16_505 https://www.acquisition.gov/far/19.504#FAR_19_504 https://www.acquisition.gov/far/subpart-19.8#FAR_Subpart_19_8 https://www.acquisition.gov/far/subpart-19.13#FAR_Subpart_19_13 https://www.acquisition.gov/far/subpart-19.14#FAR_Subpart_19_14 https://www.acquisition.gov/far/subpart-19.15#FAR_Subpart_19_15 https://www.acquisition.gov/far/8.405-5#FAR_8_405_5 https://www.acquisition.gov/far/16.505#FAR_16_505 https://www.acquisition.gov/far/subpart-19.8#FAR_Subpart_19_8 https://www.acquisition.gov/far/subpart-19.13#FAR_Subpart_19_13 https://www.acquisition.gov/far/subpart-19.14#FAR_Subpart_19_14 https://www.acquisition.gov/far/subpart-19.15#FAR_Subpart_19_15 https://www.acquisition.gov/far/19.504#FAR_19_504 entity further subcontracts will count towards the prime contractor's 50 percent subcontract amount that cannot be exceeded. When a contract includes both services and supplies, the 50 percent limitation shall apply only to the service portion of the contract;
(2) Supplies (other than procurement from a nonmanufacturer of such supplies), it will not pay more than 50 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 50 percent subcontract amount that cannot be exceeded. When a contract includes both supplies and services, the 50 percent limitation shall apply only to the supply portion of the contract;
(3) General construction, it will not pay more than 85 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 85 percent subcontract amount that cannot be exceeded; or
(4) Construction by special trade contractors, it will not pay more than 75 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 75 percent subcontract amount that cannot be exceeded.
(f) The Contractor shall comply with the limitations on subcontracting as follows:
(1) For contracts, in accordance with paragraphs (c)(1), (2), (3) and (6) of this clause— ☒ By the end of the base term of the contract and then by the end of each subsequent option period; or ☐ By the end of the performance period for each order issued under the contract.
(2) For orders, in accordance with paragraphs (c)(4) and (5) of this clause, by the end of the performance period for the order.
(g) A joint venture agrees that, in the performance of the contract, the applicable percentage specified in paragraph
(e) of this clause will be performed by the aggregate of the joint venture participants.
(1) In a joint venture comprised of a small business protégé and its mentor approved by the Small Business Administration, the small business protégé shall perform at least 40 percent of the work performed by the joint venture. Work performed by the small business protégé in the joint venture must be more than administrative functions.
(2) In an 8(a) joint venture, the 8(a) participant(s) shall perform at least 40 percent of the work performed by the joint venture. Work performed by the 8(a) participants in the joint venture must be more than administrative functions.
(End of clause)
52.228-15 Performance and Payment Bonds-Construction (JUN 2020) – DEVIATION (May 2023)
(a)Definitions. As used in this clause- Original contract price means the award price of the contract; or, for requirements contracts, the price payable for the estimated total quantity; or, for indefinite-quantity contracts, the price payable for the specified minimum quantity. Original contract price does not include the price of any options, except those options exercised at the time of contract award.
(b)Amount of required bonds. Unless the resulting contract price is valued at or below the threshold specified in Federal Acquisition Regulation 28.102-1(a) on the date of award of this contract, the successful offeror shall furnish performance and payment bonds to the Contracting Officer as follows:
(1)Performance bonds ( Standard Form 25). The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.
(2)Payment Bonds ( Standard Form 25A). The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.
(3)Additional bond protection.
(i)The Government may require additional performance and payment bond protection if the contract price is increased. The increase in protection generally will equal 100 percent of the increase in contract price.
(ii)The Government may secure the additional protection by directing the Contractor to increase the penal amount of the existing bond or to obtain an additional bond.
https://www.acquisition.gov/far/28.102-1#FAR_28_102_1 https://www.gsa.gov/forms-library/performance-bond https://www.gsa.gov/forms-library/payment-bond
(c)Furnishing executed bonds. The Contractor shall furnish all executed bonds, including any necessary reinsurance agreements, to the Contracting Officer, within the time period specified in the Bid Guarantee provision of the solicitation, or otherwise specified by the Contracting Officer, but in any event, before starting work.
(d)Surety or other security for bonds. The bonds shall be in the form of firm commitment, supported by corporate sureties whose names appear on the list contained in Treasury Department Circular 570, individual sureties, or by other acceptable security such as postal money order, certified check, cashier's check, irrevocable letter of credit, or, in accordance with Treasury Department regulations, certain bonds or notes of the United States.
Treasury Circular 570 is published in the Federal Register or may be obtained from the:
U.S. Department of the Treasury Financial Management Service Surety Bond Branch 3700 East West Highway Room 6 F01 Hyattsville, MD 20782
Or via the internet at http://www.fms.treas.gov/c570/.
(e)Notice of subcontractor waiver of protection (40 U.S.C. 3133(c)). Any waiver of the right to sue on the payment bond is void unless it is in writing, signed by the person whose right is waived, and executed after such person has first furnished labor or material for use in the performance of the contract.
(End of clause)
52.252-6 Authorized Deviations in Clauses (Nov 2020)
As prescribed in 52.107(f), insert the following clause in solicitations and contracts that include any FAR or supplemental clause with an authorized DEVIATION. Whenever any FAR or supplemental clause is used with an authorized DEVIATION, the contracting officer shall identify it by the same number, title, and date assigned to the clause when it is used without DEVIATION, include regulation name for any supplemental clause, except that the contracting officer shall insert "(DEVIATION)" after the date of the clause.
(a) The use in this solicitation or contract of any Federal Acquisition Regulation 48 CFR Chapter 1 clause with an authorized DEVIATION is indicated by the addition of "(DEVIATION)" after the date of the clause.
(b) The use in this solicitation or contract of any 48 CFR Chapter 1 clause with an authorized DEVIATION is indicated by the addition of "(DEVIATION)" after the name of the regulation.
(End of clause)
NOTE: The clause DEVIATIONS noted with an asterisk (*) are associated with the Revolutionary FAR Overhaul (RFO). Approval by the Department of the Interior is currently pending.
1452.203-70 Restrictions on Endorsements-- Department of the Interior (Jul 1996)
The Contractor shall not refer to contracts awarded by the Department of the Interior in commercial advertising, as defined in FAR 31.205–1, in a manner which states or implies that the product or service provided is approved or endorsed by the Government, or is considered by the Government to be superior to other products or services. This restriction is intended to avoid the appearance of preference by the Government toward any product or service. The Contractor may request the Contracting Officer to make a determination as to the propriety of promotional material.
http://www.fms.treas.gov/c570/
1452.204-70 Release of Claims – Department of Interior (Jul 1996)
After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI–137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.
(End of clause)
1452.215-70 Examination of Records by the Department of the Interior (Apr 1984)
For purposes of the Examination of Records by the Comptroller General clause of this contract (FAR 52.215-1), the Secretary of the Interior, the Inspector General, and their duly authorized representative(s) from the Department of the Interior shall have the same access and examination rights as the Comptroller General of the United States.
(End of clause)
1452.228-70 Liability Insurance—Department of the Interior (Jul 1996)
(a) The Contractor shall procure and maintain during the term of this contract and any extension thereof liability insurance in form satisfactory to the Contracting Officer by an insurance company which is acceptable to the Contracting Officer. The named insured parties under the policy shall be the Contractor and the United States of America. The amounts of the insurance shall be not less than as follows:
$200,000.00 each person $500,000.00 each occurrence $500,000.00 property damage
b) Each policy shall have a certificate evidencing the insurance coverage. The insurance company shall provide an endorsement to notify the Contracting Officer 30 days prior to the effective date of cancellation or termination of the policy or certificate; or modification of the policy or certificate which may adversely affect the interest of the Government in such insurance. The certificate shall identify the contract number, the name and address of the Contracting Officer, as well as the insured, the policy number and a brief description of contract services to be performed. The contractor shall furnish the Contracting Officer with a copy of an acceptable insurance certificate prior to beginning the work.
(END OF SECTION I)
PART III – LIST OF DOUMENTS, EXHIBITS AND OTHER ATTACHMENTS
SECTION J – LIST OF ATTACHMENTS
Attachment Number
Title Number of Pages
1 Specifications – March 20 2026 655 2 Final 100% CDs 60 3 DOL Wage Determination, Lincoln County, Wyoming – WY20260041, 05/18/2026 6 4 Limitations on Subcontracting Template 1
(END OF SECTION J)
PART IV – REPRESENATIONS AND INSTRUCTIONS
SECTION K – REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS OF
OFFERORS OR RESPONDENTS
ALL BASE MATOC IDIQ CLAUSES APPLY TO THIS RFP AND TASK ORDER
Provisions Incorporated by Full Text:
52.201-1 Acquisition 360: Voluntary Survey (Sep 2023)
(a) All actual and potential offerors are encouraged to provide feedback on the pre-award and debriefing processes, as applicable. Feedback may be provided to agencies up to 45 days after award. The feedback is anonymous, unless the participant self-identifies in the survey. Actual and potential offerors can participate in the survey by selecting the following link: https://www.acquisition.gov/360.
(b) The Contracting Officer will not review the information provided until after contract award and will not consider it in the award decision. The survey is voluntary and does not convey any protections, rights, or grounds for protest. It creates a way for actual and potential offerors to provide the Government constructive feedback about the pre-award and debriefing processes, as applicable, used for a specific acquisition.
(End of provision)
52.204-90 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment (Nov 2025)
(a) Definitions. As used in this provision—
“Covered telecommunications equipment or services,” “reasonable inquiry,” “roaming,” “substantial or essential component,” and “telecommunications equipment or services” have the meanings provided in the clause at FAR 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
(b) Procedures. The Offeror shall review the list of excluded parties in the System for Award Management (SAM)
(https://www.sam.gov) for entities excluded from receiving federal awards for “covered telecommunications equipment or services”.
(c) Representation. The Offeror represents that—
☐ (1) It does provide covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system; or
☐ (2) It does not provide covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system.
(d) Disclosure. If the Offeror checked paragraph (c)(1) of this provision, the Offeror shall provide the following information as part of the offer:
(1) For covered equipment— https://www.sam.gov/
(i) The entity that produced the covered telecommunications equipment (include entity name, unique entity identifier, CAGE code, and whether the entity was the OEM or a distributor, if known);
(ii) A description of all covered telecommunications equipment offered (include brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); and
(iii) An explanation of the proposed use of covered telecommunications equipment and any factors relevant to determining if such use would be permissible under the prohibition referenced in FAR 52.204-25.
(2) For covered services—
(i) If the service is related to item maintenance: A description of the item being maintained (include brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); or
(ii) If not associated with maintenance, the Product Service Code (PSC) of the service being provided; and
(iii) An explanation of the proposed use of covered telecommunications services and any factors relevant to determining if such use would be permissible under the prohibition referenced in FAR 52.204-25.
(End of provision)
52.236-28 Preparation of Proposals – Construction (Oct 1997)
a) Proposals must be (1) submitted on the forms furnished by the Government or on copies of those forms; and
(2) manually signed. The person signing a proposal must initial each erasure or change appearing on any proposal form.
(b) The proposal form may require offerors to submit proposed prices for one or more items on various bases, including-
(1) Lump sum price;
(2) Alternate prices;
(3) Units of construction; or
(4) Any combination of paragraphs (b)(1) through (b)(3) of this provision.
(c) If the solicitation requires submission of a proposal on all items, failure to do so may result in the proposal being rejected without further consideration. If a proposal on all items is not required, offerors should insert the words "no proposal" in the space provided for any item on which no price is submitted.
(d) Alternate proposals will not be considered unless this solicitation authorizes their submission.
(End of provision)
SECTION L – INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERS
ALL BASE MATOC IDIQ PROVISIONS APPLY TO THIS RFP
52.252-1 Provisions Incorporated by Reference (Feb 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es): http://www.acquisition.gov
(End of provision)
52.214-34 Submission of Offers in the English Language (Apr 1991) 52.214-35 Submission of Offers in U.S. Currency (Apr 1991) 52.225-10 Notice of Buy American Requirement – Construction Materials (May 2014)
Provisions by Incorporated by Full Text:
52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction (Feb 1999)
(a) The offeror’s attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor’s aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for Minority Participation for Each Trade Goals for Female Participation for Each Trade
3.8% 6.9%
These goals are applicable to all the Contractor’s construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor’s compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60- 4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and
(3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor’s goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4.
Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in http://www.acquisition.gov/ excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the-
(1) Name, address, and telephone number of the subcontractor;
(2) Employer’s identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Promontory, Utah, Box Elder County.
(End of provision)
52.236-27 Site Visit (Construction) (Feb 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for June 30, 2026, at 11:00 a.m. Mountain Daylight Time.