Attachment_1_-_Statement_of_Work.docx

DOCX document 30 KB Posted

Attached to
GRTE REPLACE SM COURTESY DOCK
Solicitation number
140P1424Q0037
Issued by

About this file

This document is a Statement of Work (SOW) for replacing the Signal Mountain Public Boat Launch Courtesy Dock at Grand Teton National Park. The scope includes manufacturing, delivering, and installing a new 90'x8' floating courtesy dock with a 30'x5' aluminum gangway. The contractor may have the option to reuse the existing lakeside anchors if they are in sufficient condition. The work is to be performed between the award date and May 22, 2025, with a preference for installation in the spring or fall to minimize impact to park operations. The SOW outlines detailed technical specifications for the new dock, including the dock frame, flotation, decking, winches, bumpers, and gangway. It also specifies park requirements such as work hours, wildlife protection, and equipment restrictions. The associated federal contract opportunity is Solicitation Number 140P1424Q0037, "GRTE REPLACE SM COURTESY DOCK," issued by the Department of the Interior National Park Service Intermountain Region.

View the file

Other files

File Type Posted
Attachment_2_-_Anchor_Conditions.pdf PDF
Sol_140P1424Q0037.pdf PDF
Attachment_3_-_Courtesy_Dock_Photos.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

6Replace Signal Mountain Public Boat Launch Courtesy Dock Grand Teton National Park Scope of Work

A. Introduction

1. Grand Teton National Park needs a replacement for the courtesy dock at the Signal Mountain Public Boat Launch. The existing courtesy dock in place is in poor condition and requires frequent repair. The dock is removed from the lake every fall where it stays on the boat ramp for the winter until the lake melts in May. Because the dock does not have wheels, the dock is dragged approximately 250’ on its polyethylene floats every time it is put in and out of winter storage.

B. Scope

1. Base Bid:

i. Manufacture, deliver, and install replacement courtesy dock.

ii. Install new lakeside anchors of sufficient size and in correct position for new dock, accounting for size and weight of dock and the fluctuation of lake levels. Attach new lakeside anchors to dock with new contractor supplied cable. The existing land anchors will be reused with new contractor supplied cable.

iii. Contractor shall remove existing boat dock, lakeside anchors, and cable from boat ramp area and legally dispose of them in a landfill acceptable to authorities having jurisdiction. The existing dock is approximately 80’x8’ with an approximately 40’x4’gangway. See attached photos of existing dock. NPS staff will remove existing dock, lakeside anchors, and cable from lake and place on boat ramp.

2. Optional Reductive Bid Item:

i. If it is determined the existing lakeside anchors and cable are of sufficient size, in adequate condition, and in the correct position (or can be moved to the correct position), the existing lakeside anchors and cable will be reused. The contractor shall be responsible for ensuring the anchors are in the correct position or shall move the anchors to the correct position if necessary. This determination will be made based on the contractor’s proposal at time of award.

a. The existing lakeside anchors were surveyed for their condition in 2018 by NPS Submerged Resources. The report is attached to the SOW.

3. Optional Additive Bid Item:

i. If NPS staff is unable to remove existing dock, lakeside anchors, and cable from the lake as described in B.1.iii., the contractor shall be responsible for this task. This determination will be made at time of award.

4. Along with the proposal, the contractor shall state whether they will reuse existing lakeside anchors or install new lakeside anchors. If new anchors are installed, contractor shall state their plan for installing new anchors and removing existing anchors. If existing anchors are used, contractor shall state their plan for moving existing anchors to the correct position (if needed).

C. New Courtesy Dock Requirements

1. One courtesy dock consisting of: 90’ long x 8’ wide floating walkway with composite decking, winches, removable wheels, and a 30’ long x 5’ aluminum bridge with large, oversized tires on the shore end.

D. Specification of New Dock

1. Below are specifications based on the specifications of docks currently in use on Jackson Lake. Contractor shall submit specifications with quote/proposal. Where the contractor specifications differ from the park’s specifications, the contractor shall state the reason for the difference and how the proposed specifications meet the intent of the park’s specifications.

Proposed/quoted dock must meet or exceed the purpose of each specification below. Again, these specifications are based on docks currently being successfully used.

2. Dock Frame - 12" deep box truss frame made with main structural members constructed from EXTRA HEAVY DUTY 2½"x2½"x5/16" angle, frames connected with ½" diameter Grade 5 galvanized bolts.

3. Flotation – Black, 20" deep, rotational molded polyethylene encased floats, filled with expanded polystyrene and bolted to the dock frame with 3/8" diameter galvanized bolts and washers. Shell thickness shall be nominal .150 inches. Fifteen (15) year warranty on the polyethylene encased flotation. Approximate freeboard = 22".

4. Decking – 2" x 6" "Moisture Shield" composite decking attached to the steel frame with 5/16" screws.

5. Winch and Cable Anchors – 2-ton, 16" drum, Wintech (or approved equal) winches and stands with 5/8" galvanized cable attached to lakeside anchors. Four (4) winches on winch pedestal frames.

6. Bumper Board – Single row of 1" x 6" composite attached to frame with 5/16" self-tapping screws.

7. Bumper – Black heavy duty 3" single lip vinyl bumper on the full perimeter of the dock.

8. Cleats – 10" heavy-duty aluminum Tee cleats on 10' centers.

9. Wheels and Receivers – 12 sets.

10. Wheel Chocks – One chock provided per wheel.

11. Gangway – 5'x30' Aluminum bridge with non-skid aluminum decking and ADA rails. Bridge to have large, oversized tires on the shore end.

12. Attachment points for removing the dock from lake with a front-end loader for winter storage.

13. All steel shall be hot dip galvanized after fabrication.

E. Period and Place of Performance

1. Period of Performance:

i. Award Date through 05/22/2025

ii. Preference for timing of installation of new dock below in Section G.1.d.

iii. Signal Mountain Boat Ramp may be closed for up to one day for installation.

2. Place of Performance:

i. Signal Mountain Public Boat Launch Grand Teton National Park Moran, WY 83013 43.838626, -110.616693 F. Attachments

1. Signal Mountain Boat Ramp Courtesy Dock Anchor Conditions Report

2. Photos of existing courtesy dock

3. Price Schedule, to be filled and attached with quote G. Project Management and Coordination

1. Items required with quote:

i. Technical specifications and drawings/pictures of proposed items.

ii. Proposed Installation Plan

a. Plan will include means and methods of installation, necessary boat ramp and parking area closures, etc.

iii. Proposed Installation Schedule

a. First preference for installation of new dock is after the lake has melted but before the dock has been put back into the lake (end of April – May 9th) OR after the dock has been removed from the lake but before winter (October 16th – mid-November). These approximate dates are based on the Signal Mountain Lodge operating season. Note that the spring melt off date for Jackson Lake varies depending on the year and ice sometimes persists on the lake through mid-May.

b. Second preference for installation of new dock is before May 22nd OR after September 30th. These approximate dates are based on the Signal Mountain Marina operating season.

c. Boat ramp and dock receive heavy usage during the summer. Installation during the busy summer months between May 22nd and September 30th is not possible without significant impact to park visitors and concession operations. Every effort should be made to install new dock outside of these dates.

d. If installation occurs in the fall after the regular operating season and the dock has been placed in its winter storage position, the contractor will install the new dock to its summer position to demonstrate use and installation to park staff. Park staff will then move the dock to its winter storage position.

I. Park Specific Requirements

1. USE OF PREMISES

i. Storage of Materials and Equipment: If needed, the park will provide access to a staging area in vicinity of the Signal Mountain Boat Launch.

ii. Use of Park Housing: Housing will not be available. An RV space in the park may be made available if requested.

iii. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage, which may result from moving of equipment.

2. GOVERNMENT'S OCCUPANCY REQUIREMENTS

i. Road or boat ramp closures will be permitted, when required, upon specific approval of Contracting Officer.

3. WORK RESTRICTIONS

i. On-Site Work Hours: Work shall be performed during normal business working daylight hours only, and from 8 am to 6 pm, Monday through Thursday.

ii. Work outside normal business working hours permitted with prior approval from Contracting Officer. Requests shall be submitted one week prior to requested work outside normal business hours will occur. Due to the condensed installation schedule for this project, the park will accept longer working hours if it minimizes the days of boat ramp closure.

4. PROTECTION OF PARKS AND PUBLIC LANDS

i. All boats are required to have a Grand Teton Boat Permit prior to launching on any of the park’s waters. All watercraft using Wyoming waters are required to display a Wyoming Aquatic Invasive Species decal. The decal can be purchased online at the Wyoming Game and Fish Department website or from a variety of local vendors. All boats entering Grand Teton National Park are required to stop for an Aquatic Invasive Species (AIS) inspection.

ii. All vehicles and equipment that enter the Park are staged in association with this project shall be free of mud, weeds, seeds, plant material, and other unwanted substances upon entering the park.

iii. Do not operate or park any equipment off the paved roadway except in approved areas. Do not operate or store vehicles and equipment leaking oil, gas, or anti-freeze within the park boundaries. Do not drain oil, hydraulic fluids, anti-freeze, or other chemicals onto the ground within Park boundaries. Notify CO of any spill immediately. Contractor is responsible for the immediate cleanup of any spill.

iv. Do not feed or disturb wildlife within the Park boundaries. Store and handle food, fuel, food containers, dishes, or other attractants including toiletries, pet food/bowls, and any odorous item in a manner that does not attract bears, i.e. no food, pet food, garbage, drinks, trash, or food and drink containers except during actual use. All on site construction personnel are required to report all bear sightings in the work area or housing area to the Teton Interagency Dispatch Center and COR immediately.

v. In camping, picnic, and day-use front country areas, all food items must be attended to at all times or stored inside bear resistant food storage lockers, or inside hard-sided vehicles with doors locked and windows closed.

vi. In developed lodging areas and residences, all unattended food items must be stored inside a secure building or inside hard-sided vehicles with doors locked and windows closed so that food is not visible from the exterior.

vii. Temporarily suspend construction activities when a grizzly bear or wolf comes near the work site and creates a potential animal/human conflict. Immediately notify the CO and Teton Interagency Dispatch Center for resolution of any potential animal/human conflicts or of actual animal/human confrontations. If necessary, contractor, subcontractor, and employee may be required to carry bear pepper spray, if warranted by bear/human activity. The Government will not supply bear pepper spray. Maintain required distances from wildlife at all times.

viii. All of contractor’s personnel who will be working in the park must be given a wildlife briefing by GRTE staff prior to commencing work.

ix. Immediately remove all debris that falls into Jackson Lake.