Sol_140P1424Q0007_Amd_0003.pdf

PDF 92 KB Posted

Attached to
BICA - REPLACE FENCE Federal contract opportunity
Solicitation number
140P1424Q0007
Issued by
Department of the Interior National Park Service Intermountain Region

About this file

This document contains questions and answers regarding solicitation number 140P1424Q0007 from the National Park Service Intermountain Region to replace fencing at Yellowstone National Park. The solicitation requests the installation of wood posts and wood braces for the new fence. Brush removal and limited dirt work to construct access roads across gullies will be allowed with one week advance notice. The period of performance for the work is from April 1, 2024 to May 31, 2024.

View the file

Other files for this federal contract opportunity

Other files attached to BICA - REPLACE FENCE, newest first.
File Type Posted
Sol_140P1424Q0007_Amd_0005.pdf PDF
Sol_140P1424Q0007_Amd_0004.pdf PDF
Sol_140P1424Q0007_Amd_0002.pdf PDF
Sol_140P1424Q0007_Amd_0001.pdf PDF
B03_Wage_Determination_20230005_R03_06302023.pdf PDF
Sol_140P1424Q0007.pdf PDF
A04_40641655_BICA_Replace_Fence_SOW.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140P1424Q0007 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

PIR

Yellowstone NP WY 82190 Mammoth Supply Center / 22 Stable St PO Box 168 NPS, IMR - Northern Rockies MABO

11/16/20230003

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

11/16/2023

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of Amendment 0003 is to provide the questions (indicated as Q#) received in response to this solicitation and provide the answers (indicated as A#) to the questions received. This amendment does not extend the response due date. The response due date was extended with Amendment 0002.

Q1. Do we need pointed posts or round post with concrete. And also, are we able to install bracing in the corners and ends? It would help support when pulling the wire. We would like to use wood post on all the ends to pull to secure wire if possible.

A1. The government prefers pointed posts to limit ground disturbance. Yes, H-brace style bracing should be installed to support wire stretching where needed.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Stacy Vallie

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140P1424Q0007/0003

Q2. There is some fence left standing, but the statement of work says nothing about removing it.

Does the old fencing need to be removed?

A2. Box 10 of the SF 1442 indicates there is approximately 30 ft of wire and one anchor post to be removed from the area.

Q3. Is brush removal allowed?

A3. Brush removal will be allowed.

Q4. Will NPS have the fence line marked prior to building the new fence?

A4. The fence line will be well marked post survey.

Q5. Where the fence crosses large gullies can we build a nice road into and out of the gullies to facilitate building the fence? This will also allow the fence to remain standing longer.

A5. Yes however, any dirt work will have to be monitored by the park and will need a 1 week notice before they proceed.

Q6. Brush Removal: Could you confirm whether brush removal is permissible within the scope of the project?

A6. Brush removal will be allowed.

Q7. Government Survey and Fence Line Marking: The solicitation indicates that a government survey will be conducted prior to project commencement.

To ensure accurate alignment with project requirements, could you please specify if the fence line will be clearly marked during this survey?

A7. The fence line will be well marked post survey.

Q8. Construction of Roads across Gullies: In instances where the fence intersects large gullies, are we permitted to construct roads to facilitate ingress and egress from these areas?

Such roads would not only streamline the construction process but also contribute to the longevity of the fence structure.

A8. Yes however, any dirt work will have to be monitored by the park and will need a 1 week notice before they proceed.

Q9. Is there any potential that the award date

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

3 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140P1424Q0007/0003 gets moved to sooner date, so that work can begin

ASAP?

A9. The period of performance of this requirement will not be changed.

Q10. Could you please specify if we are to use wood braces or if they could be 2 7/8" drill stem pipe braces?

A10. The fence will require wood braces.

Period of Performance: 04/01/2024 to 05/31/2024